Shaw Group, Inc. v. Bechtel Jacobs Co. (In Re IT Group, Inc.)

359 B.R. 90, 2006 Bankr. LEXIS 3356, 2006 WL 3580208
Procedural entryThis page is a short order in Shaw Group, Inc. v. Bechtel Jacobs Co. (In Re IT Group, Inc.). Read the opinion of the Court — 350 B.R. 166
United States Bankruptcy Court, D. Delaware·Decided December 8, 2006·No. 17-12624·Published

Opinion

MEMORANDUM OPINION 1

MARY F. WALRATH, Bankruptcy Judge.

Before the Court is the Motion of The Shaw Group, Inc., and Shaw Environmental, Inc. (collectively, “Shaw”) seeking prejudgment interest on the judgment entered in its favor against Bechtel Jacobs Company, LLC (“Bechtel”). For the reasons set forth below, the Court will grant the Motion, in part.

I. BACKGROUND

Shaw provides various engineering, construction, and consulting services. Bechtel is the environmental management contractor for the United States Department of Energy’s Oak Ridge Operations Office in Oak Ridge, Tennessee.

Prior to filing for chapter 11 relief, IT Group, Inc., and its affiliates (the “Debt *93 ors”) and Bechtel entered into four contracts (the “Subcontracts”), under which the Debtors were to perform various services. 2 Shortly after filing their bankruptcy petitions, the Debtors and Shaw entered into an Asset Purchase Agreement (“APA”), whereby Shaw agreed to acquire substantially all the Debtor’s assets, including three of the four Subcontracts. Shaw determined not to acquire the Portsmouth Contract. The Court entered a Sale Order approving the APA on April 25, 2002. The sale of assets occurred on May 3, 2002.

Subsequent to the sale, Shaw performed environmental remediation work under the acquired Subcontracts and Bechtel paid 90% of the invoiced amounts, retaining 10% pursuant to a provision in the Subcontracts (“Retention Provision”), whereby Bechtel was entitled to retain 10% of the balance until: (i) final acceptance of the work or (ii) the retention balance reached $1,000,000.

The retention amount on the TSCA Contract reached $1,000,000. As a result, on February 14, 2003, Shaw sent Bechtel an invoice for the full balance. Bechtel refused to pay the balance, asserting a right to offset any rejection damages under the Portsmouth Contract against the amounts due and owing under the TSCA and Tank Contracts. On December 17, 2004, Shaw filed an adversary complaint seeking declaratory relief and damages for breach of contract and unjust enrichment. Both parties moved for summary judgment. By Opinion and Order dated September 21, 2006, the Court granted Shaw’s motion and denied Bechtel’s motion. See Shaw Group, Inc. v. Bechtel Jacobs Co. (In re IT Group, Inc.), 350 B.R. 166, 182 (Bankr.D.Del.2006).

On October 2, 2006, Shaw filed a Motion for prejudgment interest, seeking interest in the amount of $490,663. Bechtel opposed the motion. Briefing is complete, and the matter is ripe for decision.

II. JURISDICTION

This adversary proceeding is a core matter over which the Court has jurisdiction pursuant to 28 U.S.C. §§ 1334 & 157(b)(2)(A).

III. DISCUSSION

A. Prejudgment Interest Under the Subcontracts

Bechtel contends that the Subcontracts expressly preclude the award of prejudgment interest. Specifically, the Subcontracts provide:

The Parties agree to make good faith efforts to settle any dispute or claim that arises under this Subcontract through discussion and negotiation. If such efforts fail to result in a mutually agreeable resolution, the Parties shall consider the use of alternative dispute resolution (ADR). In the event nonbinding mediation or arbitration is agreed upon, the site of the proceeding shall be Oak Ridge, Tennessee. The mediator or arbitrator shall allocate cost, except that there shall be no pre-decisional interest costs, and each Party shall bear its discretionary costs.

(Subcontracts, General Conditions, Exhibit A at 4 (emphasis added).)

Considering the agreement as a whole, the Court finds GC-4 unambiguous. The provision on which Bechtel relies describes the parties’ obligation to consider the use of ADR. If the parties choose mediation or arbitration as a means to resolve their dispute, then an award of pre-decisional *94 interest by a “mediator” or an “arbitrator” is precluded. In this case, however, Shaw chose to litigate its dispute in court. Therefore, the ADR provisions are inapplicable. No other provision in the Subcontracts precludes an award of prejudgment interest where the dispute is not mediated or arbitrated.

B. Applicable Law

Bechtel argues that the Subcontracts expressly require application of federal government contract law and, specifically, the Contract Disputes Act (“CDA”) to disputes involving the Subcontracts. See Contract Disputes Act of 1978, 41 U.S.C. §§ 601 et. seq.

Shaw, on the contrary, contends that the determination of an award of prejudgment interest on the judgments, which were based on state law claims of breach of contract and unjust enrichment, is governed by Tennessee law. See In re Payroll, Nos. 92-43150(ALG), 98-8405, 2005 WL 3789326, at *2 (Bankr.S.D.N.Y. July 28, 2005) (concluding that state law applied to prejudgment interest determination on breach of contract and negligence claims arising under state law).

The choice of law provision of the Subcontracts states:

The Parties agree that irrespective of the place of performance, this Subcontract shall be interpreted and all substantive issues presented for mediation, arbitration, dispute, claim, litigation or other effort at resolution shall be determined, in accordance with federal law of government contracts.... To the extent that the federal law of government contracts is not dispositive, the laws of the state in which the work is to be primarily performed shall apply.

(Subcontracts, General Conditions, Exhibit A at 4 (emphasis added).) Thus, the language of the Subcontracts mandates the application of the federal law of government contracts, as long as that law is dispositive on the issue.

Federal government contract law does govern the circumstances under which prejudgment interest may be granted. 41 U.S.C. § 611 (2006). See also Richlin Sec. Serv. Co. v. Chertoff, 437 F.3d 1296, 1301-02 (Fed.Cir.2006) (concluding that after prevailing on its claim, a contractor could recover interest for amounts actually paid).

Shaw argues, however, that the CDA does not apply here because the CDA generally does not apply to subcontractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Shaw Group, Inc. v. Bechtel Jacobs Co. (In Re IT Group, Inc.), 359 B.R. 90, 2006 Bankr. LEXIS 3356, 2006 WL 3580208 (Del. 2006).

359 B.R. 90 (Shaw Group, Inc. v. Bechtel Jacobs Co. (In Re IT Group, Inc.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Hill v. Goodwin
722 S.W.2d 668 (Court of Appeals of Tennessee, 1986)
Mitchell v. Mitchell
876 S.W.2d 830 (Tennessee Supreme Court, 1994)
Lockheed Martin Corp. v. United States
48 F. App'x 752 (Federal Circuit, 2002)