Lockheed Martin Corp. v. United States

48 F. App'x 752
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 30, 2002
DocketNo. 02-5042
StatusPublished
Cited by7 cases

This text of 48 F. App'x 752 (Lockheed Martin Corp. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lockheed Martin Corp. v. United States, 48 F. App'x 752 (Fed. Cir. 2002).

Opinion

LINN, Circuit Judge.

Lockheed Martin Advanced Environmental Systems, Inc. (“LMAES”) and Lockheed Martin Corporation (“LMC”) seek reversal of an order dismissing their lawsuit in the Court of Federal Claims for lack of subject matter jurisdiction. Because LMAES has not demonstrated privity with the government, we affirm the decision of the Court of Federal Claims. Because LMC raises for the first time on appeal an independent cause of action based on a guarantee of performance it offered, it has waived that argument, and we do not reach it in this appeal.

Beginning in the late 1940s, the government conducted research at the Idaho National Engineering and Environmental Laboratories (“INEEL”) complex near Idaho Falls, Idaho. Over time, the government released hazardous materials, including nuclear waste, at the site. In 1987, the Environmental Protection Agency (“EPA”) and the Department of Energy (“DOE”) agreed to clean up the site. This case involves a specific Superfund site called Pit 9, a nuclear waste site within the complex.

Lockheed Martin Idaho Technologies Company (“LMITCO”) entered into a cost-plus-fee management and operating (“M & O”) contract to oversee INEEL, superceding a previous contractor overseeing Pit 9. LMITCO is a wholly-owned subsidiary of the plaintiff parent corporation, LMC. As part of its M & O responsibilities, LMITCO entered into a firm-fixed-price subcontract (“the Pit 9 subcontract”) with the other plaintiff, LMAES, a subcontractor that is also a subsidiary of LMC.1 LMC guaranteed LMAES’ performance with respect to the subcontract, agreeing to return all subcontract money if LMAES did not perform. Because LMITCO, the prime contractor, and LMAES, a subcontractor, were both subsidiaries of LMC, the DOE required LMITCO to create a mitigation plan for this organizational conflict of interest.

The DOE retained contracting authority over the Pit 9 subcontract until LMITCO implemented the mitigation plan. The plan included a program oversight board and a sequestered technical oversight team of LMITCO employees. The mitigation plan required the program oversight board’s membership to include a DOE employee, a LMC employee, and an independent party chosen by both. The program oversight board’s responsibilities included, among other things: assuring that LMAES met subcontract specifications for soils treatment; making decisions regarding all change orders; handling directives that bore on LMC’s guarantee of LMAES’ performance; and ensuring that LMITCO did not perform any M & O activities under the Pit 9 subcontract. Under the mitigation plan, the program oversight board solely would direct LMAES’ work. By contrast, the sequestered technical oversight team would manage the Pit 9 subcontract administration.

[754]*754Work did not proceed smoothly at the jobsite, and LMAES was unable to perform much of the subcontract. As a result, LMITCO served a cure notice and terminated LMAES for default. In June 1998, plaintiffs brought suit in the Court of Federal Claims pursuant to the Contract Disputes Act (“CDA”), the Tucker Act, and the Fifth Amendment to the United States Constitution. Lockheed Martin Corp. v. United States, 50 Fed. Cl. 550, 552 (2001). In August 1998, LMITCO brought suit in the United States District Court for the District of Idaho against both LMAES and LMC. Lockheed Martin Idaho Techs. Corp. v. Lockheed Martin Advanced Envtl. Sys., Inc., No. 98-316E (D. Idaho filed Aug. 11, 1998). LMAES and LMC counterclaimed, raising the same claims that were raised in their suit filed in the Court of Federal Claims. The government moved to dismiss plaintiffs’ Court of Federal Claims lawsuit, arguing that the court did not have jurisdiction under Court of Federal Claims Rule 12(b)(1) because LMAES lacked privity with the government and that LMAES was contractually bound to litigate in Idaho. Lockheed Martin, 50 Fed. Cl. at 552. The government also moved to dismiss LMC’s takings claim, arguing that it failed to state a claim upon which relief could be granted. Id. The court stayed the government’s motion and required it to file an answer while LMAES sought and reviewed discovery documents from the Idaho litigation to establish jurisdiction in the Court of Federal Claims. Id. Following a series of dispositive motions, the Court of Federal Claims dismissed all claims except the takings claim for lack of jurisdiction and dismissed the takings claim on summary judgment. Id. at 566.

On appeal, the plaintiffs argue that the Court of Federal Claims erred by dismissing their claims. Plaintiffs contend that both LMAES and LMC have separate bases for privity with the government and, therefore, separate causes of action. Under LMAES’ cause of action, LMAES sets forth several theories why it has a contractual relationship with the government. LMAES contends that the government assumed LMITCO’s role as the prime contractor, controlled key Pit 9 management activities, and thus stepped into LMITCO’s shoes, putting the government in privity with LMAES. LMAES further argues that LMITCO was merely a government agent and, therefore, LMAES and the government were in privity. The parties refer to LMAES’ theories of privity as “direct control” or “direct dealings.” LMAES also argues that it was in privity with the government under the test set forth in United States v. Johnson Controls, Inc., 713 F.2d 1541, 1551 (Fed.Cir.1983) for recognizing exceptions to the general rule that subcontractors are not in privity with the government. Under LMC’s separate cause of action, it argues that LMC’s guarantee of performance constituted a contract between the government and LMC, and the government breached that separate contract.

The government argues that the express terms of the Pit 9 subcontract state that the CDA does not apply, and even if it did, the claim would not be ripe because there was no government contracting officer final decision on LMAES’ claim. The government also argues that LMAES cannot rely on the Tucker Act because LMAES’ “direct control” and “direct dealings” theories are not supported by existing law. The government further contends that the subcontractor does not fit into one of the recognized Johnson Controls exceptions. With respect to LMC’s contention that a breach of the guarantee of performance gives rise to a separate cause of action, the government argues that LMC did not raise that below and thus waived that argument.

[755]*755DISCUSSION

The United States Court of Federal Claims has jurisdiction to render judgment upon any claim against the United States founded upon any express or implied contract with the United States and to render judgment upon any claim by a contractor arising under Section 10(a)(1) of the CDA. 28 U.S.C. § 1491(a)(1)-(2) (2000). A contractor may bring an action directly on a claim in the United States Court of Federal Claims, notwithstanding any contract provision, regulation, or rule of law to the contrary. 41 U.S.C. § 609(a)(1) (2000). The term “contractor” means a party to a government contract other than the government. Id. § 601(4).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dunbar-Brown v. United States
Federal Claims, 2026
Ground Improvement Techniques, Inc. v. United States
108 Fed. Cl. 162 (Federal Claims, 2012)
Garreaux v. United States
77 Fed. Cl. 726 (Federal Claims, 2007)
Hansen v. United States
65 Fed. Cl. 76 (Federal Claims, 2005)
Moden v. United States
60 Fed. Cl. 275 (Federal Claims, 2004)
Blue Water Environmental, Inc. v. United States
60 Fed. Cl. 48 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
48 F. App'x 752, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lockheed-martin-corp-v-united-states-cafc-2002.