Shaw Constructors v. ICF Kaiser Engineers

Court of Appeals for the Fifth Circuit·Decided January 24, 2005·No. 02-30183·Published

Opinion

United States Court of Appeals Fifth Circuit

F I L E D

REVISED JANUARY 24, 2005

December 30, 2004

UNITED STATES COURT OF APPEALS For the Fifth Circuit Charles R. Fulbruge III Clerk

No. 02-30183

SHAW CONSTRUCTORS, INC.,

Plaintiff-Appellant, Cross-Appellee,

VERSUS

ICF KAISER ENGINEERS, INC., ET AL.,

Defendants,

PCS NITROGEN FERTILIZER, L.P.

Defendant-Appellee, Cross-Appellant

Appeal from the United States District Court For the Middle District of Louisiana

Before HIGGINBOTHAM, GARZA and DENNIS, Circuit Judges. DENNIS, Circuit Judge:

This is an action based on the Louisiana Private Works Act that requires the interpretation and application of the Louisiana Civil Code articles in the chapters on Third Party Beneficiary and

Dissolution of Contracts.

A subcontractor performed its part of the work in constructing a $38 million Nitric Acid Facility for the owner of an industrial plant. In the subcontract with the general contractor, the subcontractor “agrees to and does waive” its right to file claims or liens against the owner’s property. When the general contractor materially breached its primary obligation to pay the subcontractor the $5.3 million balance due for work on the owner’s facility, the subcontractor filed claims and privileges or liens against the owner’s property and brought suit against the owner under the Louisiana Private Works Act (“LPWA”).1 The owner filed a counter- claim, as third party beneficiary of the subcontract’s lien waiver provision, seeking the enforcement of that provision, the cancellation of the claims and liens filed, and the award of damages and attorneys’ fees. Applying Louisiana law in this diversity jurisdiction suit, we reverse the magistrate judge’s holding that the subcontractor may not raise against the owner- third party beneficiary’s demand the defenses it could have raised against the general contractor. Instead, we enter summary judgment sustaining the subcontractor’s right to regard the subcontract as dissolved and the parties restored to their pre-contract positions

1 La. R.S. § 9:4801, et seq. The subcontractor also brought suit against the general contractor, but these parties entered into a “Compromise Agreement,” described more fully herein, reserving the subcontractor’s rights against the owner.

when it became evident that the general contractor would not perform and had materially breached the subcontract.2 Because dissolution and restoration operate retroactively to have effect as of the day the subcontract was entered into, and because the subcontractor did not explicitly waive its right to dissolution, the dissolved lien waiver provision of the rescinded subcontract could not be invoked to preempt or bar the exercise of the subcontractor’s right to file claims and liens under the LPWA and seek to enforce them against the owner and its property.

I.

On September 17, 1997, PCS Nitrogen Fertilizer, L.P. (“PCS”), owner of an industrial plant near Geismar, Louisiana, entered into a $38 million contract (“Prime Contract”) with general contractor ICF Kaiser Engineering, Inc. (“Kaiser”) for design and construction of a structure named the “1265 STPD NITRIC ACID FACILITY.” The facility was built at the PCS plant straddling the boundary line between Iberville and Ascension Parishes.

Under the Prime Contract, PCS authorized Kaiser to subcontract portions of the work but specified that Kaiser would be responsible for the actions of subcontractors. The Prime Contract also provided that Kaiser would pay and discharge any lien that may be filed, and indemnify, defend, and hold PCS harmless from liens on

2 Id. arts. 2013, 2016, & 2018.

its property.3 In addition, the Prime Contract provided that Kaiser would reimburse PCS whatever costs PCS incurred in discharging any liens. Although the LPWA authorized PCS to protect itself against personal liability and privileges on its property under the Act by filing a notice of the contract and having Kaiser file a bond to protect subcontractors,4 PCS chose not to do so.

In January 1998, Kaiser subcontracted a portion of its work to Shaw Constructors, Inc. (“Shaw”).5 The subcontract states that Shaw agrees to provide labor, equipment, materials, and other construction services for the 1265 STPD NITRIC ACID FACILITY project and “agrees to and does waive its right to file any mechanic’s lien or claims of any sort or kind against [PCS’s] premises or any part thereof.”6 In exchange, Kaiser obligated

3 The common law term “lien” and civil law term “privilege”

will be used interchangeably throughout this opinion because the parties spoke of the terms as equivalent and as the differences between the terms are not relevant to our analysis.

4 La. R.S. § 9:4802(C).

5 PCS was not a party to the subcontract, and there was no privity between PCS and Shaw. However, the subcontract between Kaiser and Shaw referred to the Prime Contract between PCS and Kaiser, referred to PCS as “owner,” and stated that “Subcontractor hereby agrees to and does waive its right to file any mechanic’s lien or claims of any sort or kind against owner’s premises or any part thereof.”

6 The full text of the lien waiver clause provides:

Subcontractor hereby agrees to and does waive its right to file any mechanic’s lien or claims of any sort or kind against owner’s premises or any part thereof.

Subcontractor further agrees to obtain a written waiver

itself in the subcontract to make payments to Shaw, based on its monthly progress, within 45 days after receiving each of Shaw’s invoices.

As Shaw’s work progressed, Kaiser failed to make timely payments, and Shaw contemplated stopping work. Instead, on January 12, 1999, Shaw agreed to continue work in exchange for Kaiser making specifically scheduled payments and obtaining a payment bond for the remainder of the work on the project.

Nevertheless, Kaiser still failed to perform its obligation under the subcontract to pay for Shaw’s work. Instead, on January 26, 1999, Kaiser notified Shaw that it could or would not make any further payment under the subcontract. Shaw, which essentially had completed its work, wound up its portion of the project on February 1, 1999. At the time of Kaiser’s complete, material breach of the subcontract, it had failed to pay Shaw over $5.2 million for Shaw’s construction work on the PCS nitric acid facility. On January 27, 1999, Shaw filed and recorded statements of claim and privilege asserting its rights under the LPWA against PCS and its property

of the right to file any mechanic’s liens or claims of any sort or kind against Owner’s premises or any part thereof from any and all subcontractors, suppliers and materialmen at the time any subcontracts or purchase orders are issued in connection with the work. In accordance with Article 25E of Exhibit “C”, General Conditions for Subcontract, a “Release and Waiver of Lien” in the form of Appendix 1-A shall be executed by Subcontractor prior to release of each payment hereunder.

for Shaw’s uncompensated work on the PCS facility.

Free access — add to your briefcase to read the full text and ask questions with AI

Shaw Constructors v. ICF Kaiser Engineers, (5th Cir. 2005).

Shaw Constructors v. ICF Kaiser Engineers (Shaw Constructors v. ICF Kaiser Engineers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Peavey Co. v. M/V ANPA
971 F.2d 1168 (Fifth Circuit, 1992)
Ehrlicher v. St Farm Ins Co
171 F.3d 212 (Fifth Circuit, 1999)
Owsley v. San Antonio Independent School District
187 F.3d 521 (Fifth Circuit, 1999)
Lake Charles Diesel, Inc. v. General Motors Corp.
328 F.3d 192 (Fifth Circuit, 2003)
President of the Bank of Columbia v. Hagner
26 U.S. 455 (Supreme Court, 1828)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Norris Rader, Inc. v. Swilley
625 So. 2d 1125 (Louisiana Court of Appeal, 1993)
Bernard Lumber Co. v. Lake Forest Const.
572 So. 2d 178 (Louisiana Court of Appeal, 1990)
COLE-MIERS POST 3619 VFW v. State, Department of Revenue & Taxation
765 So. 2d 312 (Supreme Court of Louisiana, 2000)
Tate v. Charles Aguillard Ins. & Real Est.
508 So. 2d 1371 (Supreme Court of Louisiana, 1987)
Babineaux v. Grisaffi
180 So. 2d 888 (Louisiana Court of Appeal, 1965)
Morgan v. Audubon Const. Corp.
485 So. 2d 529 (Louisiana Court of Appeal, 1986)
Hibernia Nat. Bank v. Belleville
815 So. 2d 301 (Louisiana Court of Appeal, 2002)