Sharpless v. Zelley

37 Pa. Super. 102, 1908 Pa. Super. LEXIS 248
Superior Court of Pennsylvania·Decided July 15, 1908·No. Appeal, No. 120·Published·Cited by 2 cases

Opinion

Opinion by

Porter, J.,

The plaintiffs leased to the defendant a mortar mixing plant, in the borough of Darby, for a term of three years from July 1, 1905, at the rent of $2,250 for the term, $100 to be paid on the execution and delivery of the agreement and $325 on January 1,' 1906, etc.' The defendant paid the $100 required upon the execution and delivery of the lease, but did not pay the $325 called for by the lease on January 1, 1906, and the plaintiffs brought this action of assumpsit to recover that installment. The lease contained this covenant: “The lessor herein named hereby covenants and agrees to make repairs to the said mortar plant upon the said demised premises satisfactory to the lessee herein named, so that the same may be successfully operated by the said lessee; said repairs to be fully made and completed by the 1st day of July, a. d. 1905, and no liability for rent shall be incurred by the said lessee under this lease until such repairs have been made.” The defendant asserts that the plaintiffs failed to make the repairs called for by this covenant uf the léase and that because of such failure he is by said covenant relieved from liability to pay this installment of rent.

There was a conflict of evidence as to whether the plaintiffs had made the repairs required, and the defendant had accepted the work as done as a performance of the covenant of the lease. The defendant testified at the trial that the repairs were not satisfactory to him, but whether his objection to the manner in which the repairs were executed was made in good faith or was merely capricious was still a question for the jury: Singerly v. Thayer, 108 Pa. 291; Meacham v. Gardner, 27 Pa. Superior Ct. 296. The evidence did not entitle [109] the defendant to binding instructions and it would have been error in the court below to have entered judgment in his favor notwithstanding the verdict. The first, second and third specifications of error are overruled. The plaintiff had made out a prima facie case when she proved the execution of the lease and that the defendant went into possession under it, and the fourth specification of error is without merit.

The fifth and fourteenth specifications of error may be considered together. The fifth specification is based upon the following paragraph from the charge: “Because he (the defendant) occupying the premises .... he could have rescinded and walked away, but having taken possession he must pay what it was worth under this contract.” The fourteenth specification refers to the following paragraph of the charge:-“So that it is quite apparent that when July 1st came both parties understood that this contract had not been carried out to put this plant in operation by July 1st. The defendant went into possession and has been in possession since. What does he owe the plaintiff? He owes the plaintiff just the difference between what it would cost him to operate the machine as it has been and what it would have cost him if the plaintiff had put it in the repair that his lease provided for.” In view of the covenants of the lease and the testimony produced at the trial, we are of opinion that these instructions were erroneous. The covenant of the lease hereinbefore quoted required the plaintiff to make repairs to the said mortar plant “satisfactory to the lessee,” and expressly stipulated that no liability for rent should be incurred by the lessee until such repairs had been made. The intention of the parties to the lease manifestly was that the mortar plant should be fully repaired and ready for successful operation by July 1, 1905, but the covenant in question clearly indicates that they recognized that there was a possibility that the repairs could not be completed prior to that date, and to meet that contingency they expressly covenanted that the accruing of rent should be suspended until the repairs were completed. It was a fact admitted by both sides at the trial that the repairs were not completed and no part of the plant was ready to be put in operation until a [110] considerable period after July 1. The defendant, under an arrangement between the parties, did personally commence, during the latter part of June, going to the premises and assisting the plaintiff in making the repairs, the purpose of the parties being to get the plant in condition to start as soon as possible. The various parts of the machinery were started and tested during the progress of the repairs, but the plaintiff actually continued in the prosecution of the work of repairing the machinery until the last of September. So long as the plaintiff was actually engaged in the work of repair it could not reasonably be said that the repairs had been completed. The fact that a part of the plant had been put in operation did not change the contract of the parties. They had covenanted that the rent should not begin to run until the repairs were completed. The defendant was present upon the premises while the repairs were going on, but the plaintiff was in concurrent possession, under the covenants of the lease, for the purpose of making the repairs. The parties had in their contract left nothing to inference, they had incorporated a covenant which saved the defendant from all liability for rent prior to the time of the completion of the repairs. Under the undisputed evidence in the case and the covenants of the lease the defendant was not liable for rent of the premises for that part of the term prior to the last of September, 1905. The fifth and fourteenth specifications of error are sustained.

Free access — add to your briefcase to read the full text and ask questions with AI

Sharpless v. Zelley, 37 Pa. Super. 102, 1908 Pa. Super. LEXIS 248 (Pa. Ct. App. 1908).

37 Pa. Super. 102 (Sharpless v. Zelley) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gandy v. Klaw
112 A. 464 (Supreme Court of Pennsylvania, 1921)
Sharpless v. Zelley
47 Pa. Super. 84 (Superior Court of Pennsylvania, 1911)