Shady Tree Farms, LLC v. Omni Financial, LLC

206 Cal. App. 4th 131, 141 Cal. Rptr. 3d 412, 2012 WL 1840120, 2012 Cal. App. LEXIS 601
CourtCalifornia Court of Appeal
DecidedMay 22, 2012
DocketNo. F062924
StatusPublished
Cited by5 cases

This text of 206 Cal. App. 4th 131 (Shady Tree Farms, LLC v. Omni Financial, LLC) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shady Tree Farms, LLC v. Omni Financial, LLC, 206 Cal. App. 4th 131, 141 Cal. Rptr. 3d 412, 2012 WL 1840120, 2012 Cal. App. LEXIS 601 (Cal. Ct. App. 2012).

Opinion

Opinion

LEVY, Acting P. J.

Appellant, Shady Tree Farms, LLC (Shady Tree), delivered mature trees for the landscaping of a development known as Granite Park. When Shady Tree did not receive payment, Shady Tree recorded a materialman’s lien.

In this appeal, Shady Tree challenges the judgment on the pleadings entered in favor of respondent, Omni Financial, LLC (Omni), on Shady [134]*134Tree’s complaint to foreclose on its materialman’s lien. Shady Tree argues the trial court erred in finding that Shady Tree’s failure to serve a preliminary 20-day notice under Civil Code section 30971 prevented it from foreclosing on the lien.

The trial court correctly granted Omni’s motion for judgment on the pleadings. Accordingly, the judgment will be affirmed.

BACKGROUND

The Granite Park development covered several acres of property and was to be filled with a sports complex, restaurants and entertainment for all ages. The entities developing Granite Park were the Zone Sports Center, LLC (Zone), Granite Park Kids’ Foundation (Foundation), JEG Ventures, LLC (JEG), and High Speed Development, LLC.

Omni provided an $18 million construction loan to the Zone that was secured by a deed of trust on the properties owned by the Zone. Omni recorded the deed of trust in January 2006. Omni recorded a modification to this deed of trust in March 2007.

Shady Tree is in the business of growing and selling mature trees for landscaping. On August 11, 2008, Shady Tree entered into a contract with JEG to sell trees to the owners of Granite Park. Shady Tree agreed to deliver 1,879 trees for a price of approximately $3.2 million.

Between August 12, 2008, and November 10, 2008, Shady Tree delivered 959 trees to the Granite Park development. A landscaping company immediately planted 47 of these trees and the remaining trees were placed around the development for planting at a later date. The Granite Park entities assumed ownership and responsibility for the trees but failed to care for them. Eventually, all of the trees died.

Except for a $25,000 deposit, Shady Tree was not paid for the trees. On February 3, 2009, Shady Tree recorded a materialman’s lien against JEG, the Zone and the Foundation seeking to recover the balance due of $1,959,244.50 plus interest from September 1, 2008.

On April 2, 2009, Shady Tree filed the underlying action to enforce its materialman’s lien. Shady Tree further requested a declaration that its materialman’s lien had priority over Omni’s deed of trust. Shady Tree also sought to enjoin Omni from foreclosing on its deed of trust pending resolution of the priority issue.

[135]*135In February 2009, Omni recorded a notice of default against the Zone asserting that the Zone owed Omni over $21 million. In June 2009, Omni foreclosed and currently owns the property under a trustee’s deed.

Omni, along with defendant City of Fresno, filed a motion to remove Shady Tree’s materialman’s lien and expunge the lis pendens. Omni asserted that Shady Tree could not demonstrate the probable validity of its lien because Shady Tree was required to, and did not, serve a preliminary 20-day notice. The trial court agreed and granted the motion.

Thereafter, Omni moved for judgment on the pleadings. Omni argued that Shady Tree could not prevail on its cause of action for declaratory relief with regard to the priority of its lien because the lien had been removed. Omni further asserted that Shady Tree could not prevail on its cause of action to enjoin the foreclosure because Omni had already foreclosed. Shady Tree did not oppose the motion and judgment was entered in Omni’s favor.

DISCUSSION

Shady Tree argues that it was not required to give a preliminary 20-day notice to Omni before filing its materialman’s lien and therefore the trial court erred in removing its lien and granting judgment on the pleadings based on Shady Tree’s failure to serve such notice.

A mechanic’s lien is a claim against the real property upon which the claimant has bestowed labor or furnished materials. (Kim v. JF Enterprises (1996) 42 Cal.App.4th 849, 854 [50 Cal.Rptr.2d 141] (Kim).) A mechanic’s lien is perfected by filing a claim of lien within certain time limitations and by meeting other statutory requirements. (Ibid.) One such statutory requirement is the service of a preliminary 20-day notice. (§ 3097.)

The mechanics’ lien law is mandated by the California Constitution. (Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, 808 [132 Cal.Rptr. 477, 553 P.2d 637].) Due to this unique constitutional command, “the courts have uniformly classified the mechanics’ lien laws as remedial legislation, to be liberally construed for the protection of laborers and materialmen.” (Id. at pp. 826-827, fn. omitted.) Nevertheless, this liberal construction rule may not be applied to frustrate the Legislature’s manifested intent to exact strict compliance with the preliminary notice requirement. (Harold L. James, Inc. v. Five Points Ranch, Inc. (1984) 158 Cal.App.3d 1, 5 [204 Cal.Rptr. 494].) The Legislature “ ‘imposed the notice requirements for the concurrently valid purpose of alerting owners and lenders to the fact that the property or funds involved might be subject to claims arising from contracts to which they were not parties and would otherwise have no knowledge.’ ” (Ibid.)

[136]*136A mechanic’s lien itself is not recorded until after the completion of the work in question. (§§ 3115, 3116; Kim, supra, 42 Cal.App.4th at p. 855.) However, with certain exceptions, a claimant must serve a preliminary 20-day notice “not later than 20 days after the claimant has first furnished labor, service, equipment, or materials to the jobsite.” (§ 3097, subd. (d).) If a preliminary 20-day notice is required, a claimant shall be entitled to enforce a lien only if that preliminary 20-day notice has been given. (§ 3114.)

It is undisputed that Shady Tree did not serve a preliminary 20-day notice on Omni. Shady Tree argues that it was not required to do so under section 3097 because it was under direct contract with the owner.

Section 3097 provides, in relevant part:

“ ‘Preliminary 20-day notice (private work)’ means a written notice from a claimant that is given prior to the recording of a mechanic’s lien . . . and is required to be given under the following circumstances:
“(a) Except one under direct contract with the owner . . . , every person who furnishes labor, service, equipment, or material for which a lien . . . otherwise can be claimed under this title . . . , shall, as a necessary prerequisite to the validity of any claim of lien, . . . cause to be given to the owner or reputed owner, to the original contractor, or reputed contractor, and to the construction lender, if any, or to the reputed construction lender, if any, a written preliminary notice as prescribed by this section.
“(b) Except the contractor, ... all persons who have a direct contract with the owner and who furnish labor, service, equipment, or material for which a lien . . . otherwise can be claimed under this title, . . . shall, as a necessary prerequisite to the validity of any claim of lien, . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kinetic Systems, Inc. v. Federal Financing Bank
65 F. Supp. 3d 731 (N.D. California, 2014)
Brewer Corp. v. Point Center Financial
California Court of Appeal, 2014
Brewer Corp. v. Point Center Financial, Inc.
223 Cal. App. 4th 831 (California Court of Appeal, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
206 Cal. App. 4th 131, 141 Cal. Rptr. 3d 412, 2012 WL 1840120, 2012 Cal. App. LEXIS 601, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shady-tree-farms-llc-v-omni-financial-llc-calctapp-2012.