Kodiak Industries, Inc. v. Ellis

185 Cal. App. 3d 75, 229 Cal. Rptr. 418, 1986 Cal. App. LEXIS 1989
CourtCalifornia Court of Appeal
DecidedAugust 29, 1986
DocketCiv. 24625
StatusPublished
Cited by8 cases

This text of 185 Cal. App. 3d 75 (Kodiak Industries, Inc. v. Ellis) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kodiak Industries, Inc. v. Ellis, 185 Cal. App. 3d 75, 229 Cal. Rptr. 418, 1986 Cal. App. LEXIS 1989 (Cal. Ct. App. 1986).

Opinion

Opinion

SPARKS, J.

Under the Mechanics’ Lien Law (Civ. Code, § 3082 et seq.) a claimant who has a direct contract with the owner is required, as a prerequisite to the validity of any claim of lien, to give a preliminary notice to the construction lender or reputed construction lender that a mechanic’s lien may be placed against the property. (Civ. Code, § 3097, subd. (b).) This preliminary notice must be given no later than 20 days after the claimant has first furnished labor, service, equipment or materials to the jobsite. (Civ. Code, § 3097, subd. (c).) If the lien claimant has no actual knowledge of the identity of the construction lender, he is nevertheless charged with constructive notice of the lender’s identity when it is revealed either by the recorded construction deed of trust or by the public building permit on file. (Romak Iron Works v. Prudential Ins. Co. (1980) 104 Cal.App.3d 767 [163 Cal.Rptr. 869].)

This case poses two issues concerning the claimant’s duty to serve a preliminary notice on a construction lender or reputed construction lender. 1 The first question is whether the constructive notice imparted by those public records is imputed to a claimant only on the first day of work or whether that notice may be imputed anytime during the entire 20-day period. Construing the ambiguous statute most favorably to the lien claimant, we hold that constructive notice is imputed only on the first day of work. The second question is whether a prospective lender is a reputed construction lender within the meaning of the statute. We hold that he is if, but only if, a reasonable person, given the claimant’s information, would have been led to believe that the prospective lender is the actual lender.

*79 Procedural Background

Plaintiff Kodiak Industries is a plumbing contractor doing business as Pioneer Plumbing (Pioneer). In a trial to the court, Pioneer proceeded on two causes of action for foreclosure of its mechanic’s liens on 10 subdivision lots. At the time that Pioneer first commenced work, it neither had actual knowledge of any lender nor was any lender’s identity then discoverable from the public records. Believing it had no further duty to investigate, Pioneer did not serve any notice. Thereafter, and before the 20-day period expired, defendant Bank of America (Bank) became the actual construction lender and recorded its construction deed of trust.

The lower court found Pioneer’s rights cut off at the source for failure to give the mandatory preliminary notice to the Bank as construction lender within 20 days of commencing work at the jobsites. Although it rejected the claim that constructive notice had been imputed to Pioneer, the court ruled that “Section 3097 requires notice to prospective lenders under the facts herein.” Since the requisite notice had not been given, judgment was accordingly entered declaring that Pioneer did not have a lien on the lots in question and that it take nothing against the defendants. Pioneer appeals from this reading of the procedural requirements. We reverse.

Facts

Pioneer entered into two contracts with Hub Realty, Inc., doing business as Hub Construction, for the installation of plumbing facilities for houses to be built on 10 lots in a residential subdivision in Marysville. The properties subject to this litigation are located at two jobsites in the Gavin Estates subdivision (also known as East Park Estates) and consist of five lots each. The projects were numbered in Pioneer’s records as job 112 (covering lots 205, 207, 218, 219, and 220) and job 118 (covering lots 201, 202, 203, 204, and 217). Hub Realty was both the owner and the general contractor for Gavin Estates and used Pioneer’s services on an ongoing basis. The Bank, as it turned out, was the sole construction lender for the project.

Pioneer began work on job 112 on May 17, 1981, and finished it on August 20, 1981. It started work on job 118 on July 16, 1981, and finished on October 7, 1981. The construction permit from the City of Marysville for the lots covered by job 112 was issued on May 29, 1981 (12 days after work began), and the one for job 118 was issued on July 17, 1981 (1 day after work began). The space for the name of the “Construction Lender” was left blank on the permits. On May 27, 1981, Hub entered into a construction loan agreement with the Bank for $268,000 for construction of homes on the lots covered in job 112. It entered into a similar agreement *80 on July 21, 1981, with the Bank for $266,800 for the lots in job 118. The Bank recorded its construction deeds of trust on the lots covered in job 112 on May 28, 1981, 11 days after work began. It recorded similar deeds on the lots covered in job 118 on July 23, 1981, 7 days after work commenced. When it was not paid in full for its work, Pioneer recorded a mechanic’s lien claim for job 118 on October 20, 1981, in the amount of $16,357.40, and one for job 112 on October 26, 1981, for $9,091.40. The Bank, of course, never received a preliminary notice for either job. Pioneer then timely filed its action to foreclose these liens.

Pioneer’s witnesses testified it was their practice to serve notice on the construction lender if they learned of the lender’s identity when the work commenced. Indeed, in two previous jobs in April 1981 in the same subdivision project Pioneer sent preliminary notices to the Bank as the construction lender. In each instance, Hub had told Pioneer that Bank of America was the construction lender. On another occasion in the same period when dealing with Hub on a different project in another county, Pioneer had served the preliminary notice on Wells Fargo Bank after Hub identified that bank as the construction lender.

Pioneer’s witnesses also testified that at the start of each of the two jobs involved in this appeal, Hub was asked if there were a construction lender for the job. Although the witnesses no longer had a specific recollection of their conversations with Hub’s employees, based on their past practices they assumed in retrospect from the fact no notice had been sent to the Bank on either job that they were told no construction lender had been obtained. The trial court accepted this assumption as the true state of affairs. Pioneer did not undertake any independent investigation of Hub’s representation that there was no construction lender for the two jobs. Rick Shirley, the principal shareholder of Pioneer, testified that as he understood the Mechanics’ Lien Law, if there were no lender of record on the date work commenced, no preliminary notice to any subsequent lender was required. In his view, there was “no reason to go back and check.” He further testified that he was not surprised that Hub did not have a lender for these jobs because it was a “large concern” and might be “self-funding.”

In sum, no construction permit was filed before the start of either job, and the building permits which were eventually issued did not show the name of any construction lender. On both jobs, work started before the construction loan was consummated. The loan papers were not signed nor the construction deeds of trust recorded until a week or more after Pioneer began each job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brewer Corp. v. Point Center Financial
California Court of Appeal, 2014
Brewer Corp. v. Point Center Financial, Inc.
223 Cal. App. 4th 831 (California Court of Appeal, 2014)
Shady Tree Farms, LLC v. Omni Financial, LLC
206 Cal. App. 4th 131 (California Court of Appeal, 2012)
FORCE FRAMING, INC. v. Chinatrust Bank (USA)
187 Cal. App. 4th 1368 (California Court of Appeal, 2010)
Westfour Corp. v. California First Bank
3 Cal. App. 4th 1554 (California Court of Appeal, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
185 Cal. App. 3d 75, 229 Cal. Rptr. 418, 1986 Cal. App. LEXIS 1989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kodiak-industries-inc-v-ellis-calctapp-1986.