S&F Concrete Contractors, Inc. v. Strickland Systems, Inc.

3 Mass. L. Rptr. 617
CourtMassachusetts Superior Court
DecidedApril 25, 1995
DocketNo. CA933525
StatusPublished
Cited by1 cases

This text of 3 Mass. L. Rptr. 617 (S&F Concrete Contractors, Inc. v. Strickland Systems, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S&F Concrete Contractors, Inc. v. Strickland Systems, Inc., 3 Mass. L. Rptr. 617 (Mass. Ct. App. 1995).

Opinion

Whitehead, J.

Plaintiff S&F Concrete Contractors, Inc. (“S&F”) filed suit against defendants Strickland Systems, Inc., International Form Corporation (collectively “IFC”),1 and Dole J. Kelley, Jr., Consulting Structural Engineer, in connection with the collapse of a concrete bay that occurred during a concrete pour at the construction site of Digital Equipment Corporation’s manufacturing facility in Hudson, Mas[618]*618sachusetts (the “Digital project”). S&F alleges that the collapse was due to the failure of one or more of the twenty-two (22) steel columns IFC specially built to support the forming system during the concrete pour. IFC and S&F have filed cross-motions for summary judgment pursuant to Mass.R.Civ.P. 56(c).

BACKGROUND

Marshall Contractors was the general contractor on the Digital project. S&F is a concrete subcontractor. In June, 1992, S&F was awarded a subcontract for foundation work at the Digital project. In October, 1992, S&F was awarded a subcontract for slab and flooring work on certain buildings at the Digital project.

IFC designs, fabricates, and furnishes concrete forming systems. After a series of late summer and early fall meetings and negotiations between Peter Moskos (“Moskos”), an S&F Project Manager, and Jerry Koslowski (“Koslowski”), a Vice President at IFC, S&F agreed to lease the IFC concrete forming system known as the Flex-A-Form System, for use on the Digital project. Moskos and Koslowski had had prior dealings with each other in connection with S&Fs agreement to use the Flex-A-Form System on another project (the Deer Island project) in which it was involved. At the time of the negotiations regarding the Digitál project, S&F had not yet used the Flex-A-Form System on the Deer Island project.

In August, 1992, S&F sent drawings to IFC for the latter’s use in preparing a proposal for S&F’s rental of the Flex-A-Form System in connection with the Digital Project. On September 15, 1992, IFC issued its first proposal to S&F, which contemplated the rental of thirty thousand (30,000) square feet of forms. The second page of the September 15 proposal contained a paragraph which provided: “The terms on the reverse side of the Flex-A-Form contract, receipt of which is hereby acknowledged by signed acceptance below, shall apply except as noted above (copy enclosed).” S&F received the September 15, 1992 proposal, along with IFC’s General Terms And Conditions, which were not printed on the back side of the contract, but were enclosed on a separate sheet of paper. Paragraph 11 of the General Terms And Conditions provided:

Customer agrees to hold IFC harmless for any or all damages to property or persons while said equipment is in transit or while said equipment is in customer’s possession, including all expenses, damages, claims, suits and actions including costs and attorneys fees incurred directly or indirectly, out of or in connection with the leasing, maintenance or use of the material of IFC. Customer further agrees to carry insurance to cover such damages.

S&F did not sign IFC’s September 15 proposal.2

On October 29, 1992, after further negotiations, IFC issued a revised proposal to S&F for the rental of thirty thousand (30,000) square feet of forms. This proposal was identical in form to the prior proposal. S&F did not sign the October 29, 1992 proposal.

Subsequently, on November 23, 1992, IFC issued a third proposal, also identical in form to the prior proposals, for the rental of twenty thousand (20,000) square feet of forms.3 S&F did not sign the November 23 proposal as drafted. Instead, Moskos altered the payment terms and dates on page two of the proposal, and attached that page to a S&F Purchase Order, No. 3500, for the rental of twenty thousand (20,000) square feet of forms.4 Moskos signed Purchase Order No. 3500, and expressly acknowledged that it was issued in response to IFC’s November 23, 1992 proposal via the following notation: “per Int Form letter dated 11-23-92 (copy attached).”5

It soon became apparent that the Flex-A-Form System could not be utilized at the Digital project without post-shoring to support the system during the concrete pour. IFC designed and fabricated special columns for that purpose and S&F agreed to lease the columns.

On November 25, 1992, S&F issued a second Purchase Order, No. 3781, also signed by Moskos, for twenty-two (22) steel columns for use with the Flex-A-Form System. Moskos did not reference IFC’s November 23, 1992 proposal, or any other proposal, on Purchase Order No. 3781.

The IFC forming equipment was delivered to S&F in several shipments. Each shipment was accompanied by a Delivery Report, which contained the phrase ‘Terms and Conditions” in the top right hand corner. Each Delivery Report contained a list of “Conditions Governing Rental” on the front page. The next to last paragraph of the “Conditions Governing Rental” provided: “You agree to hold harmless this company for any or all damages to property or persons while said equipment is being used under this delivery order.” S&F accepted delivery of, and used the IFC forming equipment it had rented. S&F did not object to the Conditions Governing Rental.

On January 6, 1993, IFC submitted another proposal to S&F for the rental of ten thousand (10,000) square feet of forms. The January 6 proposal was identical in form to the prior three proposals. On January 11, 1993, Moskos issued Purchase Order No. 3786, for ten thousand (10,000) square feet of forms. Moskos expressly incorporated IFC’s January 6, 1993 proposal into the Purchase Order.

Meanwhile, on January 7, 1993, one of the concrete bays at the Digital project collapsed during a concrete pour. Approximately nineteen (19) people were injured. This suit followed.

DISCUSSION

I. Summary Judgment Standard

Summary judgment shall be granted where there are no genuine issues as to any material fact and [619]*619where the moving party is entitled to judgment as a matter of law. Cassessov. Commissioner of Correction, 390 Mass. 419, 422 (1983); Community Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976); Mass.R.Civ.P. 56(c). The moving party bears the burden of affirmatively demonstrating the absence of a triable issue, “and [further] that the moving party is entitled to judgment as a matter of law.” Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989).

A party moving for summary judgment who does not have the burden of proof at trial may demonstrate the absence of a triable issue either by submitting affirmative evidence that negates an essential element of the opponent’s case or “by demonstrating that proof of that element is unlikely to be forthcoming at trial.” Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991). Accord Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). “If the moving party establishes the absence of a triable issue, the party opposing the motion must respond and allege specific facts which would establish the existence of a genuine issue of material fact in order to defeat [the] motion.” Pederson, supra at 17. “[T]he opposing party cannot rest on his or her pleadings and mere assertions of disputed facts to defeat the motion for summary judgment.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LeBlanc v. Walsh Bros.
23 Mass. L. Rptr. 676 (Massachusetts Superior Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
3 Mass. L. Rptr. 617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sf-concrete-contractors-inc-v-strickland-systems-inc-masssuperct-1995.