Sexton v. Weaver

6 N.E. 367, 141 Mass. 273, 1886 Mass. LEXIS 183
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 27, 1886
StatusPublished
Cited by7 cases

This text of 6 N.E. 367 (Sexton v. Weaver) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sexton v. Weaver, 6 N.E. 367, 141 Mass. 273, 1886 Mass. LEXIS 183 (Mass. 1886).

Opinion

W. Abler, J.

The petitioner was employed as a carpenter and foreman, during the year 1883, by one Sheldon, who had contracts for building houses for the respondent and for several other persons. The petitioner worked upon the different houses, and payments were made to him by Sheldon, from time to time, on account of his work generally; but no account was kept of his work on the different houses, and no application of any payment was made for labor on any specific house. About January 1, 1884, Sheldon failed, and the petitioner’s last work upon the respondent’s house was on January 5. There was then due to him from Sheldon $192. He was to be paid three dollars a day, and he filed his certificate of lien and account of the amount due him for work on the respondent’s house for sixty-four days’ work, amounting to $192. In fact, he had worked upon the house more than sixty-four days, but only one day after November, and only fourteen days in November; during all the rest of November and December he was doing other work for Sheldon. As the payments by Sheldon to the petitioner were all on general account, and not appropriated, they would be applied to the earlier items, and would show that the petitioner was. paid for all the labor he had performed except the last sixty-four days. For so much of that as was upon the respondent’s house he would have a lien upon it, but not for such as was upon the houses of others, and not for work on the respondent’s house which had been paid for.

The respondent contends that the lien was dissolved by the failure to file a sufficient statement of account of the amount due. The account is general, for sixty-four days’ labor from July 31 to January 5, at three dollars a day. The first objection is, that the days on which labor was performed are not specified. The statute requires a “ statement of a just and true account of the amount due, with all just credits given.” The true amount, and not the items that make it up, is the material thing to be shown, and the items are not important for the purposes of the certificate, as they are in making or creating proof of the account. We cannot hold that, for this cause, the statement is insufficient.

[275]*275Another objection is, that the statement does not include all the labor that was performed by the petitioner upon the house, with credits for payments admitted to have been made. A sufficient answer is, that it does not include any labor for which payment is not claimed. That the petitioner had performed other labor which had been paid for, is immaterial.

Another ground upon which it is argued that the statement is insufficient is, that it includes about forty days’ labor on the respondent’s house which had been paid for. This appears to be true, and it would be fatal but for the provision of the statute that the validity of the lien shall not be affected by any inaccuracy in stating the amount due, unless it appears that the person filing the statement has wilfully and knowingly claimed more than is his due. The petitioner apparently claimed the right to apply the payments made to him by Sheldon to the amount due for labor on other houses than the respondent’s, and to leave the whole amount unpaid a charge on the respondent’s house. That the facts stated in the exceptions show that he had not the right to do so is not conclusive in law that he wilfully and knowingly claimed more than his due; and the statements in the exceptions that the court did not find that the petitioner wilfully and knowingly claimed more than was due, and that the certificate was a just and true account of his labor performed on the respondent’s house, with all just credits given, are conclusive that the validity of the lien cannot be affected by the excessive amount claimed.

The respondent, in her original answer, sets up that one Boston had filed a petition in the Superior Court for a lien upon the same property, and that this petitioner had been duly notified of the filing of that petition. At a subsequent term the respondent, by leave of court, filed a supplemental answer, that the respondent, on June 19, 1885, after the filing of her former answer, recovered judgment in the suit of Boston that the petition be dismissed. The petition of Boston was filed on February 4, returnable at the March term. This petitioner did not appear in that suit, but filed his petition on March 24.

So far as the pendency of the former suit was matter in abatement, the decision of the court below would be final; but the pendency of the suit is not alleged in the answer, and is not [276]*276relied on in the argument as matter in abatement, but in bar, upon the ground that the statute is to be construed as authorizing but one suit to enforce all kindred liens upon the same property; and that, when a suit to enforce one lien is commenced, all kindred lien creditors are parties to it, and the authority to bring a suit given by the statute is exhausted. Under the supplemental answer, the respondent contends that the petitioner is a party to the suit of Beston, bound by the judgment for the respondent; and that the judgment is properly pleaded. The question which has been argued by the parties, as arising on the pleadings, is whether a suit commenced by one creditor to enforce a lien, and prosecuted to judgment for the respondent, in which another creditor, who is served with notice, does not appear, is a bar to a suit by such other creditor.

The statute provides (Pub. Sts. c. 191, § 9,) that, “ unless a suit for enforcing the lien is commenced within ninety days after the person desiring to avail himself thereof ceases to labor on or to furnish labor or materials for the building or structure, the lien shall be dissolved.” Sections 16-18 provide for notice of the filing of the petition to the owner of the building and the debtor, and to all other creditors who have a lien of the same kind upon the same estate. Section 19 provides that every creditor having a lien under the statute upon the property may appear and prove his claim.

The argument for the petitioner is, that the statute gives to each creditor the right to bring a suit to preserve and enforce his lien. The argument for the respondent is, that the statute provides for but one final decree and sale of the property, under which the proceeds are to be distributed among all the creditors, and as, by inference, this must be upon the suit first commenced, it excludes the authority to commence another suit in which a final decree cannot be entered.

The statute provides, when a suit is commenced, for notice to all lien creditors, either personal or by publication; that all such creditors may appear and prove their claims, and that each may contest the claim of every other, and provides for trial by jury ; that the court shall “ ascertain and determine the amount due to each creditor who has a lien under this chapter upon the property in question; ” that claims due, but not payable, shall be [277]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valentine Lumber & Supply Co. v. Thibeault
130 N.E.2d 873 (Massachusetts Supreme Judicial Court, 1955)
HOUSTON FIRE AND CASUALTY INSURANCE CO. v. Hales
279 S.W.2d 389 (Court of Appeals of Texas, 1955)
Kinkead v. Hartley
143 N.W. 591 (Supreme Court of Iowa, 1913)
Donnelly v. Butler
102 N.E. 917 (Massachusetts Supreme Judicial Court, 1913)
E. I. Dupont DeNemours Powder Co. v. Culgin-Pace Contracting Co.
92 N.E. 1023 (Massachusetts Supreme Judicial Court, 1910)
Sandberg v. Victor Gold & Silver Mining Co.
66 P. 360 (Utah Supreme Court, 1901)
Whalen v. Collins
41 N.E. 124 (Massachusetts Supreme Judicial Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
6 N.E. 367, 141 Mass. 273, 1886 Mass. LEXIS 183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sexton-v-weaver-mass-1886.