Sequatchie Concrete Service, Inc. v. Cutter Laboratories

616 S.W.2d 162, 1980 Tenn. App. LEXIS 424
CourtCourt of Appeals of Tennessee
DecidedNovember 21, 1980
StatusPublished
Cited by17 cases

This text of 616 S.W.2d 162 (Sequatchie Concrete Service, Inc. v. Cutter Laboratories) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sequatchie Concrete Service, Inc. v. Cutter Laboratories, 616 S.W.2d 162, 1980 Tenn. App. LEXIS 424 (Tenn. Ct. App. 1980).

Opinion

OPINION

PARROTT, Presiding Judge.

In these consolidated cases appellant, Se-quatchie Concrete Service, Inc., appeals the chancellor’s granting to both appellees sum *164 mary judgment that denied enforcement of a materialman’s lien when the original lien claim contained an erroneous property description.

The facts were stipulated. Sequatchie Concrete Services, Inc., hereinafter referred to as “Sequatchie Concrete,” entered into a parol contract with Edwin Tate, d/b/a Tate Masonry Company, to supply concrete products for use in construction work at the Hamilton County plant facilities of Cutter Laboratories, hereinafter referred to as “Cutter Labs.” Tate was a subcontractor under a contract for the plant improvements between R. S. Noonan, Inc., general contractor, and Cutter Labs. Pursuant to the parol contract, as of March 31, 1979, Sequatchie Concrete had furnished Tate Masonry $12,414.99 worth of masonry products which were incorporated into Cutter Labs’ improvements. Tate signed Sequat-chie Concrete’s invoices which specified service charges at the rate of 1½ percent per month. Nothing has been paid on the Tate account and Richard Jahn has been appointed trustee pursuant to Edwin Tate’s adjudication of bankruptcy on June 8, 1979.

On April 18, 1979, within 90 days of the time Sequatchie Concrete furnished the last materials to Tate for incorporation into Cutter Labs’ improvements, Sequatchie Concrete notified Cutter Labs by letter that it was claiming a materialman’s lien and enclosed a copy of a notice of lien, which was also filed at the register’s office that day. Cutter Labs owns three adjacent lots and the notice of lien contained an erroneous property description of a parking lot area instead of a description of the lot where the plant improvements were made. Sequatchie Concrete filed an action on June 25, 1979, seeking enforcement of its lien against Cutter Labs and requesting attachment be levied on the same property that had been mistakenly described in the notice of lien. On August 8, 1979, approximately 110 days after the notice of lien was given, Sequatchie Concrete filed an amended complaint correctly describing the Cutter Labs property where the improvements actually were made and another attachment was issued.

Following Tate’s adjudication of bankruptcy, because R. S. Noonan, the general contractor with Cutter Labs, owed Tate $8,348.19, Noonan filed a complaint of inter-pleader asking the court to make an adjudication whether he should pay the sum to R. P. Jahn, Tate’s trustee in bankruptcy, or to Sequatchie Concrete. Noonan is obligated by its contract with Cutter Labs to hold Cutter Labs harmless from any mechanics’ and materialmen’s liens against their real property and seeks to avoid double payment of the sum.

The chancellor, in granting summary judgment for the appellees, specifically found that the lien notice and attachment did not describe Cutter Labs’ improved property and that no attachment of the improved property was made within 90 days following the notice of lien. Therefore, the court held that Sequatchie Concrete had failed to perfect a lien upon the improved property within the legally prescribed time. Furthermore, the chancellor ruled that as to the funds R. S. Noonan owed Tate there was no trust existing in favor of Sequatchie Concrete and those funds should pass to Tate’s trustee in bankruptcy.

Appellant’s first contention is that it properly perfected a valid materialman’s lien including Cutter Labs’ improved property that should be enforced by the court. When the lien dispute is limited to between the owner and supplier, written notice alone to the owner is sufficient to perfect the lien as between those two parties. Tennessee law requires only a simple form of notice to initially alert the property owner as to the supplier’s claim. See Reeves v. Henderson & Co., 90 Tenn. 521, 18 S.W. 242 (1891). Failure to properly register the notice with a correct description of the improved property as required under T.C.A. § 64-1117 only affects the furnisher’s rights as opposed to subsequent purchasers or lienors. Walker Supply Company, Inc. v. Corinth Community Development, Inc., 509 S.W.2d 514 (Tenn.App.1974). Although Sequatchie Concrete’s letter of notice to Cutter Labs contained the erroneous property descrip *165 tion of the parking lot, its explanation of the construction contract under which the lien was being claimed was sufficient to alert the property owners that the improved parcel of land was actually the property upon which the furnisher sought to impress the lien.

However, enforcement of a mechanic’s or materialman’s lien is a statutory right and strict compliance with T.C.A. § 64-1101 et seq. is required. General Electric Supply v. Arlen Realty & Development Corporation, 546 S.W.2d 210 (Tenn.1977); Eatherly Construction Company v. DeBoer Construction, Inc., 543 S.W.2d 333 (Tenn.1976), and cases cited therein. T.C.A. § 64-1126 requires that liens be enforced by attachment only; such attachment to issue “upon petition ... setting forth the facts, describing the property, and making the necessary parties defendant.... ” (Emphasis added.) Although T.C.A. § 64-1126 contains no reference as to time limitations for making attachment, T.C.A. § 64-1115 prescribes the time for filing suit by reference to the lien continuing “until the final termination of any suit for enforcement brought within ...” 90 days of the notice of lien. The Tennessee Supreme Court recently held that:

We are of the opinion that when a lien claimant has timely filed his complaint with the clerk, praying for writ of attachment, and when that writ has actually been issued by the clerk of the sheriff within the time period prescribed in T.C.A. § 64-1115, then the suit has been “brought” within the meaning of the statute .... (General Electric Supply v. Arlen Realty & Development Corp. supra at 213-14)

In the instant case a lawsuit was initiated and attachment of the wrong property was levied within 90 days of the notice of lien. However, not until after 110 days from the notice of lien was the error in property description corrected and Cutter Labs’ improved property properly attached, which does not comply with the statutory requirements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vulcan Materials Co. v. Gamble Construction Co.
56 S.W.3d 571 (Court of Appeals of Tennessee, 2001)
D.T. McCall & Sons v. Seagraves
796 S.W.2d 457 (Court of Appeals of Tennessee, 1990)
In Re Null's Service, Inc.
109 B.R. 301 (W.D. Tennessee, 1990)
Burleson Construction Co. v. White (In re White)
106 B.R. 501 (E.D. Tennessee, 1989)
First American Bank of Nashville, N.A. v. Woods
734 S.W.2d 622 (Court of Appeals of Tennessee, 1987)
Weems v. Paul R. Walker Co. (In re James)
78 B.R. 159 (E.D. Tennessee, 1987)
Wilson v. Mettetal (In Re Mettetal)
41 B.R. 80 (E.D. Tennessee, 1984)
Wilson v. Estes (In Re Wilson)
30 B.R. 91 (E.D. Tennessee, 1983)
Weill v. Evans Lumber Co. (In Re Johnson)
25 B.R. 889 (E.D. Tennessee, 1982)
Kannon v. Blalock (In Re Blalock)
15 B.R. 33 (E.D. Tennessee, 1981)
Witt Building Material Co. v. Barker (In Re Barker)
14 B.R. 852 (E.D. Tennessee, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
616 S.W.2d 162, 1980 Tenn. App. LEXIS 424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sequatchie-concrete-service-inc-v-cutter-laboratories-tennctapp-1980.