Selico v. Intercontinental Bulktank Corp.

733 So. 2d 1240, 98 La.App. 4 Cir. 0763, 1999 La. App. LEXIS 1514, 1999 WL 326393
CourtLouisiana Court of Appeal
DecidedMay 12, 1999
Docket98-CA-0763
StatusPublished
Cited by7 cases

This text of 733 So. 2d 1240 (Selico v. Intercontinental Bulktank Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Selico v. Intercontinental Bulktank Corp., 733 So. 2d 1240, 98 La.App. 4 Cir. 0763, 1999 La. App. LEXIS 1514, 1999 WL 326393 (La. Ct. App. 1999).

Opinion

733 So.2d 1240 (1999)

Lee SELICO
v.
INTERCONTINENTAL BULKTANK CORPORATION, et al.

No. 98-CA-0763.

Court of Appeal of Louisiana, Fourth Circuit.

May 12, 1999.

*1241 Walter Z. Steinman, Charles P. Neely, Wyncote, Pennsylvania, Attorneys For Plaintiff/Appellee Lee Andre Selico.

Gerard T. Gelpi, G. Beauregard Gelpi, Gelpi, Sullivan, Carroll & Gibbens, New Orleans, Louisiana, Attorneys for Defendants/Appellants Intercontinental Bulktank Corporation and Maritime Overseas Corporation.

Court composed of Judge WILLIAM H. BYRNES III, Judge STEVEN R. PLOTKIN and Judge PATRICIA RIVET MURRAY.

PATRICIA RIVET MURRAY, Judge.

International Bulktank Corporation and Maritime Overseas Corporation appeal a judgment in favor of seaman Lee Selico based on negligence and unseaworthiness as well as a judgment notwithstanding the verdict awarding Mr. Selico pre-judgment interest on the award for damages caused by unseaworthiness. We affirm.

*1242 FACTS:

On May 28, 1987, Lee Selico, a merchant seaman, was employed by International Bulktank Corporation (IBC) aboard the M/V Overseas Alaska, a steam tanker, as a "deck engine utility." On that date the ship was docked in the port of New Orleans undergoing an annual coast guard inspection. Mr. Selico was working in the engine room under the supervision of the first and second assistant engineers while the coast guard officers were inspecting the boiler. He had followed the second assistant engineer, as instructed, to the top of the boiler in order to put a "gag" on the steam valve so that the boiler could be raised to capacity in order to be inspected. Mr. Selico and the engineer had climbed a catwalk onto the slanted side of the boiler, and Mr. Selico followed in order to assist him. The engineer realized that he needed more tools in order to complete gagging off the valve, and asked Mr. Selico to return to the machine shop for them. Mr. Selico testified that he turned around and went back the way he had come, but he slipped and lost his footing. He reached for the hand railing in order to catch himself, and pulled his shoulder out of place. The second engineer picked him up vertically, and stood him on the catwalk, then called for the first engineer who helped get Mr. Selico to the lower engine room where they were able to work his shoulder back into place with some effort after approximately a half hour. Mr. Selico testified that his fall was caused by a combination of the slant of the top of the boiler and the build-up of soot and moisture on its surface.

When asked by the medical officer, who had been called by the engineer, if he wanted to continue working, Mr. Selico replied that he needed to keep his job. He indicated to the officer that he did not need to see a doctor at that time. He testified that he was told that he should ask for treatment later if he felt it was needed.

Mr. Selico continued to work for approximately two weeks. Although he was not doing anything too strenuous, he continued to have problems with his shoulder, which remained sore. On approximately June 14 or 15 Mr. Selico was working in the engine room, and reached for some tools. When he did so he felt as if his shoulder was going to come out of place again, and realized that he needed medical attention. He advised the mate that it did not appear that his shoulder was getting better from the injury on May 28, and he asked to see a doctor. The mate filled out a requisition for medical attention, and Mr. Selico was taken to a doctor in New York. Mr. Selico gave the doctor the history of the accident on May 28. He also gave a history of a football injury to his shoulder in high school, as well as two or three other occasions when his shoulder "popped out" out of place, the most recent having occurred approximately two years before this accident. Following an examination and xray, the doctor determined that Mr. Selico was not fit for duty. Mr. Selico returned to the ship, and arrangements were made for him to return to New Orleans.

On June 19, following his return to New Orleans, Mr. Selico consulted Dr. Walter Brent, an orthopedic surgeon. Dr. Brent diagnosed a dislocating left shoulder. He was of the opinion that Mr. Selico had a severe rotator cuff injury, and recommended surgery to form a new anterior part of the rotator cuff. As Dr. Brent explained, the procedure would involve exposing the shoulder joint, taking out the labrum (cartilage attached anteriorly), freshening the bone on the anterior of the labrum, and placing the glenoid cavity of the shoulder joint tightly on the "freshened up" bone so that it would heal in this position. He also recommended that the muscles be plicated back and tightened slightly in front of this area.

Dr. Brent performed the surgery on June 25. The surgery disclosed that the anterior capsule and the labrum were completely torn from the anterior part of the *1243 attachment of the glenoid, which Dr. Brent found was consistent with trauma caused by a recent injury. In his opinion this most likely happened as Mr. Selico grabbed onto something and received a severe jerk when he attempted to break his fall in the engine room.

Mr. Selico remained in the hospital for nine days and was seen by Dr. Brent on several occasions following his discharge. He began physical therapy in mid-July and was discharged by Dr. Brent on November 9, 1987. At that time Mr. Selico lacked approximately fifteen degrees external rotation and approximately five degrees internal rotation of the shoulder. Dr. Brent felt that this was an excellent result. Although he assigned a ten percent partial disability of the upper extremity, he opined that Mr. Selico could return to his work as a merchant seaman. Mr. Selico returned to this work on December 6, 1987.

Following testimony by Mr. Selico and Dr. Brent, and the introduction of various exhibits, the plaintiff rested. The trial court denied a defense motion for directed verdict. The defendants then rested without calling any witnesses.

The jury answered interrogatories finding that: the Alaska was unseaworthy on May 28, 1987, and the unseaworthiness was a proximate cause of injuries to Mr. Selico; that Maritime Overseas Corporation and International Continental Bulktank Corporation were negligent on May 28, 1987, and their negligence contributed to the injury sustained by Mr. Selico; that 50% of Mr. Selico's injuries were attributable to unseaworthiness and 50% to negligence; that Mr. Selico's lost wages were $17,845.01, and his past, present and future suffering, disability, mental anguish and loss of capacity for enjoyment of life was $125,000.00; that he was not negligent in a manner that contributed to his injuries; and that Mr. Selico was not entitled to recover pre-judgment interest.

The court entered judgment in accordance with the verdict on October 17, 1997. On December 19, 1997, the court granted Plaintiffs Motion for Judgment Not Withstanding the Verdict and awarded prejudgment interest as to one-half of the lost wage award and one-half of the damage award.

The defendants have appealed assigning three errors by the trial court: 1) the court erred in awarding plaintiff pre-judgment interest; 2) the jury's findings of negligence and unseaworthiness are not supported by the evidence; and 3) the jury erred when it failed to find Mr. Selico to be contributorily negligent.

DISCUSSION:

Defendants do not take issue with the charges given the jury, but contend that the evidence does not support the findings of negligence and unseaworthiness.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
733 So. 2d 1240, 98 La.App. 4 Cir. 0763, 1999 La. App. LEXIS 1514, 1999 WL 326393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/selico-v-intercontinental-bulktank-corp-lactapp-1999.