Seater Construction Co. v. Rawson Plumbing, Inc.

2000 WI App 232, 619 N.W.2d 293, 239 Wis. 2d 152, 2000 Wisc. App. LEXIS 945
CourtCourt of Appeals of Wisconsin
DecidedSeptember 27, 2000
Docket99-3203
StatusPublished
Cited by7 cases

This text of 2000 WI App 232 (Seater Construction Co. v. Rawson Plumbing, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seater Construction Co. v. Rawson Plumbing, Inc., 2000 WI App 232, 619 N.W.2d 293, 239 Wis. 2d 152, 2000 Wisc. App. LEXIS 945 (Wis. Ct. App. 2000).

Opinion

SNYDER, J.

¶ 1. Rawson Plumbing, Inc., appeals from a judgment of the trial court in favor of *155 Seater Construction Co., Inc. Seater, a general contractor, brought an action against Rawson, a subcontractor, pursuant to the doctrine of promissory-estoppel. Seater alleged that Rawson submitted a subcontractor bid to do the plumbing work on a construction project that Seater relied upon in submitting its general contractor's bid. Seater was awarded the construction contract, after which, it alleged, Raw-son refused to honor its subcontractor bid. After a trial to the court on the grounds of promissory estoppel, the trial court ruled in favor of Seater on a breach of contract basis. Rawson appeals, arguing that no contract existed between it and Seater and therefore no breach could occur. Rawson further argues that Seater has no right to recover on the grounds of promissory estoppel. We affirm the judgment of the trial court pursuant to the doctrine of promissory estoppel.

FACTS

¶ 2. Seater is a general contractor in Racine, Wisconsin. On August 7,1997, Seater offered a written bid proposal to the City of Waukesha (city) for the construction of an administrative office building and storage facility (the project).

¶ 3. Most of the work on the project was to be performed by subcontractors employed by Seater. On August 7,1997, the deadline for submitting bids for the project, Rawson submitted a written subcontract bid to Seater offering to perform certain portions of the project's plumbing work for $179,663. Rawson's bid did not include all of the required plumbing work for the project but excluded certain oil/grease lubrication lines and equipment. Another subcontractor submitted a bid for this excluded plumbing work in the amount of $62,825. Rawson's bid combined with this second sub *156 contractor's bid encompassed all of the necessary plumbing work and had a combined bid total of $242,458. This was the lowest bid that Seater received for all of the needed plumbing work and was therefore used by Seater and incorporated into its bid to the city. Seater's bid of $4,341,000 was accepted by the city as the lowest bid for the project.

¶ 4. In mid-September 1997, Seater received the project contract from the city. The city had not signed the contract, but sent the contract to Seater for its signature and for the attachment of the appropriate bonds and insurance documents. Seater then sent a letter to Rawson, dated September 15,1997, indicating that Seater would be sending Rawson a written subcontract agreement after the city signed the project contract. On or about September 17, 1997, Seater signed the project contract, attached the necessary paperwork, and returned the contract to the city for the city's signatures. The city signed the contract on September 29, 1997. Seater received a fully executed copy of the contract sometime during the first week of October 1997.

¶ 5. On or about October 7,1997, Seater received a construction bulletin from the city's architects for the project, asking about potential contract price adjustments if portions of the project were to be changed. Some of the proposed project changes involved the plumbing work. Seater then sent a letter to Rawson, dated October 10, 1997, asking Rawson about price adjustments if the proposed changes were implemented. Rawson sent a written response, dated October 20, 1997, informing Seater that a subcontract price increase of $9222 would be necessary if the proposed changes were required. Seater then forwarded *157 this information to the city in a letter dated October 27, 1997.

¶ 6. On November 5,1997, Seater sent Rawson a written subcontract agreement for Rawson's work on the project. On that same day, Michael Wiedenbeck, Seater's manager for the project, called Mark Derouin, Rawson's president. Wiedenbeck informed Derouin of the project's progress and notified him of the date Raw-son would be needed on the project site to start the plumbing work. Rawson was scheduled to begin the plumbing work on November 17,1997.

¶ 7. On November 12, 1997, Rawson called Seater and requested three sets of the plans and specifications for the project. Seater mailed the plans and specifications to Rawson that same day.

¶ 8. On November 17,1997, Rawson did not show up at the project site as planned. On November 19, 1997, Seater mailed a written copy of the project schedule to Rawson. By the first week of December, Rawson still had not reported to the project site; on December 9, 1997, Seater sent a facsimile to Rawson, reminding Rawson that it should have reported to the project site on November 17,1997.

¶ 9. On December 16, 1997, Derouin called Wiedenbeck and informed him that because of an error in the subcontract bid, Rawson would not be able to complete the work at the agreed-upon price. Seater immediately contacted other plumbing subcontractors who had submitted Seater bids in August Í997, but none were available to take the job. The only subcontractor available, Kaelber Company, agreed to do the work if it became necessary.

¶ 10. On or about December 19,1997, Jeff Stacy, the president of Seater, called Derouin. Derouin informed Stacy that Rawson could not do the plumbing *158 work at its original bid amount because there had been a mistake in the bid proposal. Derouin told Stacy that Rawson would need more money to do the necessary work, and Derouin promised that he would submit a dollar amount to Seater. Seater's attorney then sent a letter to Rawson, dated December 23,1997, demanding that Rawson honor its original subcontractor bid.

¶ 11. On December 30,1997, Rawson sent Seater a facsimile indicating that Rawson could complete the project plumbing work for $209,663; this amount was $30,000 more than Rawson's original bid. On or around that same date, Stacy called Derouin to further discuss this matter. Stacy informed Derouin that Rawson's original bid was in the normal bid range when the excluded work was considered. Derouin again informed Stacy that he had made a bid error. Stacy proposed that Seater pay an additional $14,000 to Rawson under the subcontract agreement, and Derouin agreed to that amount.

¶ 12. On or about January 2, 1998, Wiedenbeck prepared and sent to Rawson a change order providing for the payment of an additional $14,000 to Rawson under its subcontract. The change order noted the amount of the added payment and stated "Adjustment to bid day proposal error per Mark." On or about January 5, 1998, Rawson sent Seater a facsimile indicating that Rawson disagreed with the aforementioned language and insisting that the language of the change order read:

Rawson original proposal expired, renegotiated. Contract adjustment agreed to, in full, by both parties. Total add $14,000.00. New contract amount shall be $193,663.00.

*159 ¶ 13. Seater refused to make this requested change in the language of the change order and wanted to use its proposed language. Rawson then sent another facsimile to Seater, dated January 5, 1998, indicating that it would not do the project plumbing work unless Rawson's proposed language change was implemented in the change order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Darrell Martez Smith
Court of Appeals of Wisconsin, 2022
CG Schmidt Inc. v. Permasteelisa North America
142 F. Supp. 3d 755 (E.D. Wisconsin, 2015)
Uniek, Inc. v. Dollar General Corp.
500 F. Supp. 2d 1158 (W.D. Wisconsin, 2007)
Knauf Realty, LLC v. Prudential Real Estate Affiliates, Inc.
486 F. Supp. 2d 855 (W.D. Wisconsin, 2007)
State v. Sloan
2007 WI App 146 (Court of Appeals of Wisconsin, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2000 WI App 232, 619 N.W.2d 293, 239 Wis. 2d 152, 2000 Wisc. App. LEXIS 945, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seater-construction-co-v-rawson-plumbing-inc-wisctapp-2000.