Seagate Technology, LLC v. Western Digital Corporation, Sining Mao

Court of Appeals of Minnesota·Decided January 25, 2016·No. A15-760·Unpublished

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA

IN COURT OF APPEALS

A15-0760

Seagate Technology, LLC,

Appellant,

vs.

Western Digital Corporation, et al., Respondents,

Sining Mao,

Respondent.

Filed January 25, 2016

Reversed and remanded

Rodenberg, Judge

Hennepin County District Court File No. 27-CV-06-19000

Lewis A. Remele, Jr., Mark R. Bradford, Jeffrey R. Mulder, Frederick E. Finch, Bassford Remele, P.A., Minneapolis, Minnesota (for appellant)

Michael D. Schissel (pro hac vice), Arnold & Porter LLP, New York, New York; and Clifford M. Greene, Larry D. Espel, Sybil L. Dunlop, Greene Espel PLLP, Minneapolis, Minnesota (for respondents Western Digital Corporation and Western Digital Technologies, Inc.)

George W. Soule, Soule & Stull LLC, Minneapolis, Minnesota (for respondent Sining Mao)

Considered and decided by Rodenberg, Presiding Judge; Schellhas, Judge; and Reilly, Judge.

UNPUBLISHED OPINION

RODENBERG, Judge Appellant Seagate Technology, LLC (Seagate) challenges the district court’s denial of its request for an award of post-arbitration-award interest, arguing that the district court erred in interpreting the underlying arbitration award as having determined post-award interest. Because we conclude that the arbitrator did not decide the issue of post-award interest, and because the plain language of Minn. Stat. § 549.09 (2014) mandates post-award interest on the amount of the entire award, we reverse and remand.

FACTS

The lengthy procedural history of this case, which we do not recite here, is included in the previous opinions of this court and the Minnesota Supreme Court. See Seagate Tech., LLC v. W. Digital Corp., 854 N.W.2d 750, 753-57 (Minn. 2014), aff’g 834 N.W.2d 555 (Minn. App. 2013). Those opinions, collectively “Seagate I,” generally concern the arbitrator’s authority.

The supreme court issued its opinion in Seagate I on October 8, 2014, affirming this court’s reinstatement of the arbitrator’s final award. 854 N.W.2d 750. On October 13, 2014, respondents Western Digital Corporation and Western Digital Technologies, Inc. (together, Western) offered to satisfy what Western considered to be the full award amount, $773,404,103.74. Seagate accepted that amount as partial payment, but maintained that Western owed a balance of $28,884,751.64, because the total award amount as of December 24, 2014, including post-award interest, was $802,288,855.38. The discrepancy in the parties’ calculations results from disagreement

over whether the arbitrator’s final award provided the method for calculating post-award interest.

Seagate sought a declaratory judgment concerning the correct computation of interest. The parties brought cross-motions in the district court: Western sought a declaration that it had fully satisfied its liability, and Seagate sought judgment for what it claimed was the unpaid balance of the award, with interest. The narrow issue before the district court was the correct computation of interest owing on the arbitrator’s award. Western based its interest calculation on the principal amount of the arbitrator’s interim award, $525,000,000. Seagate based its interest calculation on a principal amount of $630,431,501, the sum of the arbitrator’s compensatory-damages award plus the interest included in the final award.

The district court ruled for Western, construing the final award as having addressed both pre- and post-award interest. This appeal followed.

DECISION

I. Standard of review.

We review a district court’s interpretation of legal documents, such as arbitration awards, de novo. See Halla Nursery, Inc. v. City of Chanhassen, 781 N.W.2d 880, 884 (Minn. 2010) (“[W]e review de novo the district court’s interpretation of [a] stipulation and judgment.”); Star Windshield Repair, Inc. v. Western Nat. Ins. Co., 768 N.W2d 346, 348 (Minn. 2009) (“[W]e independently review a lower court’s interpretation of [an] insurance policy.”); Alpha Real Estate Co. of Rochester v. Delta Dental Plan of Minn., 671 N.W.2d 213, 221 (Minn. App. 2003) (“[T]he construction of [an unambiguous

contract provision] is a question of law for the court to resolve, and this court need not defer to the district court’s findings.”), review denied (Minn. Jan. 20, 2004) (quotations omitted). Western argues in a footnote in its brief that Ray v. City of Maple Grove, 519 N.W.2d 466 (Minn. App. 1994), review denied (Minn. Sept. 16, 1994) and Johnson v. Newbold, No. A06-760, 2007 WL 583332 (Minn. App. Feb. 27, 2007), when read together, suggest that we should review the district court’s interpretation of the arbitrator’s award for clear error. The narrow issue here, however, concerns the availability of prejudgment interest, which both parties agree that we review de novo. Duxbury v. Spex Feeds, Inc., 681 N.W.2d 380, 390 (Minn. App. 2004), review denied (Minn. Aug. 25, 2006). Our de novo review requires us to consider the four corners of the arbitrator’s final award and Minn. Stat. § 549.09. We do not evaluate the merits of the underlying dispute between the parties. The issue before us is one of law concerning which we do not defer to the district court. De novo review is appropriate.

II. Our opinion and the Minnesota Supreme Court’s opinion in Seagate I did not resolve the issue of post-award interest.

Western argues that the recitation of this case’s procedural history in our opinion and in the supreme court’s opinion in Seagate I should guide our interpretation of the arbitrator’s final award. The district court relied on language in those opinions to conclude that the arbitrator decided the issue of post-award interest.

The references to “post-award interest” in the Seagate I opinions are contained in each court’s recitation of background information. The issue then on appeal was whether the arbitrator exceeded his authority in imposing sanctions. Seagate I, 854 N.W.2d at

760. Neither we nor the supreme court considered the question of the proper interest calculation because the question in Seagate I was binary: should or should not the arbitrator’s final award be vacated for having exceeded the arbitrator’s authority? Id. at 765. The characterizations of interest are not necessary to the holdings in Seagate I, and are therefore dicta. See State v. Naftalin, 246 Minn. 181, 208, 74 N.W.2d 249, 266 (1956) (defining “dicta” as “expressions in a court’s opinion which go beyond the facts before the court and therefore are . . . not binding on subsequent cases”).

It is worth noting in this context that the statements of the appellate courts concerning interest in Seagate I arose from the parties’ and the district court’s characterizations of the magnitude of the arbitrator’s final award. Both parties have taken a mercurial approach to the issue of post-award interest. In Seagate I, each advanced a position concerning post-award interest exactly opposed to that party’s present arguments. Western argued then, attempting to demonstrate the claimed outrageousness of the award, that the arbitrator’s final award included compensatory damages and pre- award interest for a total of approximately $630 million, with interest accruing at the rate of $173,000 per day. The $173,000 per day figure can only be replicated by using a principal amount of $630,431,501.1 Conversely, Seagate argued in Seagate I that interest was accruing at $143,835.61 per day. That figure can only be arrived at by computing

1 $630,431,501 principal x 0.10 interest rate = $63,043,150.10 annual interest. $63,043,150.10 ÷ 365 days = $172,720.95 daily interest. $172,720.95 x 7 days = $1,209.046.65 weekly interest. This calculation, and that which follows in note 2 infra, are for illustration only. The parties appear to have “rounded” to the next-lowest cent. Our present purpose does not involve focusing on the parties’ rounding standards.

Free access — add to your briefcase to read the full text and ask questions with AI

Seagate Technology, LLC v. Western Digital Corporation, Sining Mao, (Mich. Ct. App. 2016).

Seagate Technology, LLC v. Western Digital Corporation, Sining Mao (Seagate Technology, LLC v. Western Digital Corporation, Sining Mao) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Aufderhar v. Data Dispatch, Inc.
452 N.W.2d 648 (Supreme Court of Minnesota, 1990)
Alpha Real Estate Co. of Rochester v. Delta Dental Plan of Minnesota
671 N.W.2d 213 (Court of Appeals of Minnesota, 2003)
Myers v. Hearth Technologies, Inc.
621 N.W.2d 787 (Court of Appeals of Minnesota, 2001)
State Ex Rel. Foster v. Naftalin
74 N.W.2d 249 (Supreme Court of Minnesota, 1956)
Halla Nursery, Inc. v. City of Chanhassen
781 N.W.2d 880 (Supreme Court of Minnesota, 2010)
Ray v. City of Maple Grove
519 N.W.2d 466 (Court of Appeals of Minnesota, 1994)
Duxbury v. Spex Feeds, Inc.
681 N.W.2d 380 (Court of Appeals of Minnesota, 2004)
Lessard v. Milwaukee Insurance Co.
514 N.W.2d 556 (Supreme Court of Minnesota, 1994)
Lienhard v. State
431 N.W.2d 861 (Supreme Court of Minnesota, 1988)
Arthur Allen Hogenson v. Michael W. Hogenson
852 N.W.2d 266 (Court of Appeals of Minnesota, 2014)
Seagate Technology, LLC v. Western Digital Corporation, Sining Mao
854 N.W.2d 750 (Supreme Court of Minnesota, 2014)
Hoit v. Berger-Crittenden Co.
84 N.W. 48 (Supreme Court of Minnesota, 1900)
Seagate Technology, LLC v. Western Digital Corp.
834 N.W.2d 555 (Court of Appeals of Minnesota, 2013)