Sea Crest Construction Corp. v. United States

59 Fed. Cl. 473, 2004 U.S. Claims LEXIS 27, 2004 WL 322952
Procedural entryThis page is a short order in Sea Crest Construction Corp. v. United States. Read the opinion of the Court — 59 Fed. Cl. 615
United States Court of Federal Claims·Decided February 19, 2004·No. No. 02-261C·Published

Opinion

[474]*474ORDER

HODGES, Judge.

Sea Crest filed a motion for reconsideration of the January 8 Order granting summary judgment on Drawing No. 1 and denying plaintiffs Rule 56(f) motion as Moot. We held that defendant was authorized under its contract with plaintiff to reject Drawing No. 1 as nonconforming. We conferred with the parties on February 11 and denied plaintiffs motion for reconsideration on February 13. Sea Crest Constr. Corp. v. United States, No. 02-261C (Fed.Cl. Feb. 13, 2004). This Order will address the reasons for that ruling in more detail.1

I. Drawing No. 1

This case involves a government contract for design and construction of a housing development called Stoney Lonesome II at West Point, New York. Sea Crest sent defendant a letter before contract award stating that the contractor would require an allowance for rock excavation. This July 3, 1995 letter stated that plaintiff had included “an allowance for 10,000 cubic yards of rock excavation for site trenching and building foundations.” Plaintiff made a similar statement in a July 20 letter. Defendant responded on July 26 by requiring that Sea Crest remove the allowance for excavation2 and submit a Best and Final Offer. Plaintiff complied the next day.3

The Corps awarded the Contract to Sea Crest based on its July 27, 1995 Best and Final Offer. The BAFO stated, “to minimize rock drilling and blasting ... some revisions to the site will be necessary. In accordance with the RFP, the items described ... above will be performed in conjunction with the approval of the Army Corps of Engineers. Pod A, F, B, & C will be included in phase 1, pod G and D will be in phase 2.”

Plaintiff and defendant met following contract award to discuss the site design. Sea Crest provided a drawing at the meeting that differed from the design that plaintiff had submitted with its BAFO. This was Drawing No. 1. The drawing showed a long loop road with houses facing the street. Plaintiff knew that the Corps wanted the pod configuration that Sea Crest submitted with its BAFO and referred to in the July 27 letter that accompanied it.4 The Government rejected Draw[475]*475ing No. 1 because it did not comply with the Corps of Engineers’ Request for Proposals on the project.

The record does not show why Sea Crest submitted a new, nonconforming drawing after contract award. Its BAFO design had been accepted by the Government. Plaintiffs counsel stated during a February 11 telephone conference that Drawing No. 1 was an effoi't to recoup an allowance for blasting and rock-removal costs that the Corps had rejected during pre-bid negotiations. Plaintiff submitted an affidavit that includes the following statement: “Sea Crest proposals for the project were conditioned on certain site work allowances. The pre-award discussions and agreements that wex’e included in the Best and Final Offer and subsequently denied to Sea Crest resulted in excessive site work costs.” (Riverso Aff. If 3). It is difficult to know what this means. If pre-award agreements resulted in excessive work costs but nevertheless were included in the BAFO, plaintiff must have adopted them. The BAFO was plaintiffs final offer, and defendant accepted it.

Plaintiff submitted five affidavits with its opposition to defendant’s motion for summary judgment. The affidavits did not “set forth specific acts showing that there is a genuine issue for trial” with regard to the issue of Drawing No. 1. Rule 56(e). They consisted of legal opinions and conclusory factual assertions that did not meet the requirements of Rule 56.

Mr. DiSimone was Sea Crest’s Contract Administrator and Project Manager. His affidavit states that Sea Crest proposed at a September 18 pre-work meeting to “revise the layout of the housing units, in accord with pre-award agreements, in order to protect the environment and to minimize the amount of excavation and fill, as offered in the BAFO that had been accepted by the Corps.” (DiSimone Aff. 113). Mr. DiSimone does not say what “px-e-award agreements” are implicated. The BAFO states, “to minimize rock drilling and blasting ... some revisions to the site will be necessary. In accordance with the RFP, the items described ... above will be performed in conjunction with the appx*oval of the Army Corps of Engineers.” If the parties had agreements concerning excavation problems or the environment that are not in the Contract, these may be subject to the parole evidence rule. Counsel have not argued this issue.

Mr. DiSimone added the following:

Drawing No. 1 was responsive to the RFP, made the most economic and non-destrue-tive use of the site, minimized cut and fill in accordance with Sea Crest’s BAFO, allowed for 160 units and provided an efficient and flexible use of a site that was encumbered by its size, historic prohibitions, environmental sensitivity and a restriction that no final grade could exceed 10%.

(DiSimone Aff. 113). Whether Drawing No. 1 was responsive to the RFP is a legal issue. WThether it made the most economic and nondestructive use of the site is Mr. DiSi-mone’s opinion. Defendant had the right to insist on a site plan that was consistent with its needs, and for which it was willing to pay.

Next, affiant states that the Government rejected Drawing No. 1 and insisted on the “clustered or pod arrangement conceptualized in Sea Crest’s pre-award proposals.” Id. at 114. He states that the Corps disregarded the BAFO provision that Sea Crest could revise the site plan “in conjunction with the approval of the Corps.” Id. He added, “Sea Crest was required to design and build a site layout without an opportunity to make any revisions that would minimize excavation and fill, as previously agreed at the time of award.” Id. He does xxot say what “previously agreed” x'efers to here. The BAFO provided that Sea Crest could revise the site plan with the Corps’ approval. Plaintiff has not drawn our attention to other agreements, which in any event could be subject to the pax-ole evidence rule.

“It was made clear to the Sea Crest representatives present at these meetings that the ultimate decision-making authority for the Project was Colonel Colaciceo and the DHPW representatives and not the Corps, [476]*476with which Sea Crest had the Contract.” Id. at 115. The affiant states that this was a “material departure from the terms of the Contract.” Id. Plaintiff did not make such an argument, however, which is a legal one. Affiant does not make clear what significance such a fact would have.

“The rejection of Drawing No. 1 violated a number of contract provisions.” Id. at H 6. This is a legal conclusion. Paragraph 6 describes the relative importance of various aspects of the project that relate to the RFP. These are factors that the Government considered in awarding the Contract. The Government awarded the Contract to Sea Crest. Pre-award evaluation factors have little application to the legal issues at hand.

Paragraphs 7 and 8 merely restate criteria set forth in the Corps’ requirements for overall site design. Mr. DiSimone does not offer facts that create genuine issues. He states in paragraph 9 that Drawing No. 1 was designed to meet the contract requirements, but he does not mention the cul-de-sacs or the pod design that the Corps wanted. In his opinion, Drawing No.

Free access — add to your briefcase to read the full text and ask questions with AI

Sea Crest Construction Corp. v. United States, 59 Fed. Cl. 473, 2004 U.S. Claims LEXIS 27, 2004 WL 322952 (uscfc 2004).

59 Fed. Cl. 473 (Sea Crest Construction Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sea Crest Construction Corp. v. United States
59 Fed. Cl. 615 (Federal Claims, 2004)