S.E. Johnson Companies, Inc. v. Northern Indiana Public Service Co.

852 N.E.2d 1, 2006 Ind. App. LEXIS 1589, 2006 WL 2338034
CourtIndiana Court of Appeals
DecidedJune 21, 2006
Docket90A05-0512-CV-738
StatusPublished
Cited by4 cases

This text of 852 N.E.2d 1 (S.E. Johnson Companies, Inc. v. Northern Indiana Public Service Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.E. Johnson Companies, Inc. v. Northern Indiana Public Service Co., 852 N.E.2d 1, 2006 Ind. App. LEXIS 1589, 2006 WL 2338034 (Ind. Ct. App. 2006).

Opinions

OPINION

BAKER, Judge.

Appellant-defendant S.E. Johnson Companies, Ince. (Johnson) appeals the trial court's grant of summary judgment in favor of appellee-plaintiff Northern Indiana Public Service Company (NIPSCO), regarding NIPSCO's claim against it for negligence. Specifically, Johnson contends that the trial court erred in concluding that Johnson was negligent as a matter of law when one of its employees sawed through an underground natural gas pipe owned by NIPSCO while performing a construction project for the City of Fort Wayne (the City). In essence, Johnson contends that it was merely acting as an employee and following the City's instructions and, therefore, it was not subject to the provisions of the Damage to Underground Facilities Act (DUFA).1 Concluding that summary judgment was properly entered for NIPSCO, we affirm the judgment of the trial court.

FACTS

During the fall of 1999, Johnson was hired by the City to complete a road construction project that included an area on New Haven Avenue in Fort Wayne. Johnson had been awarded the project pursuant to a bidding process, and the City supplied it with a set of road plans. The plans were stamped with a "Holey Moley-Don't Dig Blind" icon and a toll-free telephone number. Appellant's App. [3]*3p. 206. The purpose of the "Holey Moley" campaign was to "encourage contractors to call the number ... to ensure that when you're going to be cutting in the right-of-way that you're aware of where the facilities are so that you can limit the damage that might happen." Id. at 206-07. Among other things, the plans identified the location of a four-inch gas line that had been installed by NIPSCO in 1981. The gas line was marked with a "G" for gas. Id. at 206, 210-13.

When the project initially began in 1999, the City had spray painted the areas of pavement that they wanted Johnson to saw and remove. Johnson's project manager, Larry Houchins, called in for locations of underground facilities along New Haven Avenue. These locations were marked in painted colors that signified the particular service: yellow for gas, orange for telephone, and red for electric. While the markings indicated lateral location, they did not indicate depth.

Thereafter, on March 29, 2000, Houchins again telephoned for a location of underground facilities along New Haven Avenue, including the area where the gas pipe was located. Houchins was aware that the locate service had to be given two full days to complete the task. This particular request was the first one made that year for a locate on the project affecting the 4300 block of New Haven Avenue. Houchins sought to have the painted lines for the underground facilities re-marked, and he made the foreman of the crew, Chuck Mer-gy, aware that he had called in the locate. The locate request was made for work to be done on and after March 31, because Houchins believed that it did not need a locate for "sawing pavement," which was to be performed on March 30. Appellant's App. p. 92, 187-88. However, Mergy believed that a locate service is typically contacted to locate "[aJnything in the ground that is relevant to the Holey Moley deal." Id. at 92, 187-88, 217-19.

On March 30, when the employees at Johnson began sawing the pavement, neither the asphalt foreman nor Mergy were aware of the depth of the concrete through which the saw was cutting. The saw used to perform the work had a studded cireu-lar blade, approximately five to seven feet in diameter and four to five inches in width, and it could be deployed hydraulically to less than half its full height.

During this process, Johnson was unaware of the specific depths of the other layers of the road that the erew had drilled from the top of the roadbed, including the asphalt. Hence, without a locate, Mergy did not know the depth at which the gas line was buried. He was aware that locates had been made in the roadway from the previous fall, and that the reason for such locates was to identify the underground facilities existing beneath the roadway where the Johnson crew was performing its work. As a road contractor, Mergy did not often examine the road plans, and he agreed that the contractor relies upon the locator to inform him where underground lines are buried.

When the saw blade cut completely through the bottom of the concrete, it eventually ripped through NIPSCO's steel pipe, causing natural gas to escape. The fire department was summoned and a factory nearby was vacated. Thereafter, NIPSCO work crews were dispatched to the scene to make the repairs. To effect the repairs, NIPSCO servicemen had to eut out a four-foot by four-foot section of the concrete that the saw had cut through, and a new piece of steel that was approximately two feet in length had to be inserted. This piece was then attached to the existing pipe with couplings.

As a result of this incident, NIPSCO filed a complaint for damages against [4]*4Johnson on February 26, 2001, alleging that Johnson had violated DUFA and, as a result, damaged NIPSCO's utility facilities "through excavation, demolition or other means." Appellant's App. p. 8. Both parties filed motions for summary judgment, and following a hearing, the trial court granted summary judgment in favor of NIPSCO on October 17, 2005. In relevant part, the trial court's order granting Johnson's motion provided as follows:

(4) As an exeavator, Johnson owed a duty under the Damage to Underground Facilities Act (DUFA) to serve notice upon NIPSCO and other affected utilities of its intent to excavate at least two (2) full working days before commencement of the work, including the starting date, anticipated duration and type of excavation to be conducted, the location of the proposed excavation, and the approximate depth of excavation.
(5) NIPSCO had a right to install its steel gas pipe beneath New Haven Avenue pursuant to Ind.Code 8-20-1-28 but it had no corresponding duty under DUFA, absent the prescribed notice, to notify Johnson, or to others using the roadway, of the existing depth of its service pipe; nor did NIPSCO owe a duty under DUFA to install or maintain its service pipe at a particular depth.
(6) The Johnson road crew forem[eln were, prior to March 30, 2000, aware of the existence of underground facilities beneath New Haven Avenue, and were further aware of their duty to contact the operators of the underground facilities to obtain locates of such facilities, including the depth of the respective facilities.
(7) Johnson negligently breached its duty to NIPSCO by failing to provide it with timely notice of its intent to excavate into New Haven Avenue on March 30, 2000 and/or failing to await performance of a locate as required by DUFA. (8) As an excavator, Johnson owed NIP-SCO a duty under DUFA to plan its excavation to avoid damage to underground facilities, and to maintain a clearance of two feet on either side of its buried service pipe or to at least expose the facility....
(9) Johnson further negligently breached its duty to NIPSCO by failing to expose the underground facilities through hand excavating methods and by excavating blindly through the street with its exeavation equipment, thereby striking and damaging the NIPSCO gas service pipe beneath the street.
(10) Johnson's negligent violations of the DUFA proximately caused NIPSCO damages, including loss of natural gas and the cost to repair its damaged service pipe.
[[Image here]]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alexander v. Marion County Sheriff
891 N.E.2d 87 (Indiana Court of Appeals, 2008)
Cinergy Corp. v. St. Paul Surplus Lines Insurance Co.
873 N.E.2d 105 (Indiana Court of Appeals, 2007)
S.E. Johnson Companies, Inc. v. Northern Indiana Public Service Co.
852 N.E.2d 1 (Indiana Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
852 N.E.2d 1, 2006 Ind. App. LEXIS 1589, 2006 WL 2338034, Counsel Stack Legal Research, https://law.counselstack.com/opinion/se-johnson-companies-inc-v-northern-indiana-public-service-co-indctapp-2006.