SDM Corp. v. United States

36 Cont. Cas. Fed. 75,819, 19 Cl. Ct. 607, 1990 U.S. Claims LEXIS 72, 1990 WL 18471
CourtUnited States Court of Claims
DecidedMarch 1, 1990
DocketNo. 171-89C
StatusPublished

This text of 36 Cont. Cas. Fed. 75,819 (SDM Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SDM Corp. v. United States, 36 Cont. Cas. Fed. 75,819, 19 Cl. Ct. 607, 1990 U.S. Claims LEXIS 72, 1990 WL 18471 (cc 1990).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This action is before the court on defendant’s motion for summary judgment pursuant to Rule 56 of the United States Claims Court. Plaintiff seeks to hold defendant liable under the contract for the costs and profits associated with the production of a second set of first article test units because 1) defendant ordered the alleged production or 2) defendant failed to inspect the parts and components of the originally manufactured test units prior to their assembly necessitating the construction of a second set of test units.

FACTS

On August 30, 1984, the United States Department of the Army awarded contract # DAAA09-84-C-0942 (contract) for the production of specially equipped trailers to serve as survival stations during chemical warfare to SDM Corporation (SDM). The resulting fixed-price contract required the construction of ninety-six M68 Filters, Utilities with Accessories, and final assembly of the survival stations in government furnished trailers. In addition, the assembly of the complete survival station necessitated the use of other government furnished equipment, such as gas engines.

The contract contained explicit first article testing requirements, i.e., an initial delivery of four units of the production quantity of completed survival stations for first article testing. The contract specified that the testing would include government inspection of all sub-assemblies and parts used in the assembled product. The first [608]*608article units, therefore, had to be manufactured using the same processes and procedures that would be used in the production of all subsequent units.

The contract, while contemplating final satisfaction of the agreement, nevertheless provided for the failure of first article testing. Upon the request of the Contracting Officer plaintiff could make any necessary changes, modifications or repairs to a disapproved first article or assemble a second first article and submit it for testing. Either of these options were to be exercised at plaintiff's expense. Alternatively, the contract allowed defendant to waive these contractual provisions and obligate the government to pay the additional costs incurred in producing a second first article for testing. Any of the three options chosen obligated plaintiff to bear all costs necessitated by re-testing.

By July of 1985, the parties had modified the contract to provide a time extension for first article testing because of government delays in furnishing government furnished equipment and technical clarifications. By further modification defendant authorized SDM to procure long leadtime items according to a schedule that specified the amount of contract money to be expended on the purchase of these items. Defendant authorized these purchases in order to enable plaintiff to be in a position to be able to meet the future contract delivery schedules.

Between April and May of the following year, defendant inspected the first article units at plaintiff’s plant. As a result of this inspection, defendant issued seven Quality Deficiency Reports and, on May 15, 1986, notified plaintiff that the government disapproved and rejected plaintiff’s first article units. The rejection was based in the main on plaintiff's inadequate maintenance of contractually required records.

On July 18, 1986, plaintiff notified defendant that it was ready for defendant to re-test the earlier rejected first article units whenever the government found the necessary paperwork satisfactory. In that letter, plaintiff made reference for the first time to the continuation of 100% testing of a second set of first article test units. After receiving this letter, plaintiff met with defendant on August 28,1986 to clarify the requirements under the contract for retesting the original set of first article units. At this meeting, plaintiff complained that it had not formally offered the original first article units for testing, and, therefore, the government could not reject plaintiff's first article based on the preceding inspections. The senior official at the meeting for defendant, Product Control Manager Warren J. Wolfe, noted the objection. However, Mr. Wolfe only discussed with plaintiff possible options under the contract to correct the problems delineated in the quality deficiency reports. At this meeting, the parties resolved that plaintiff would correct the deficiencies in the original first article units at plaintiff’s expense per the terms of the contract and defendant would adjust the testing schedule accordingly.

On September 2, 1986 defendant notified plaintiff that the government was willing to continue first article testing on the first set of first article units if the faults noted in the seven quality deficiency reports had been corrected. On September 10, 1986, the parties again modified the contract to re-establish a delivery schedule. On September 11, plaintiff wrote defendant specifying its corrections to the test units. On February 27, 1987 the government finally approved the first set of first article test units but, on March 23, 1987, terminated the contract for the convenience of the government.

In the resulting termination negotiations, plaintiff sought relief for the building of a second set of first article test units, and alleged that the government had ordered plaintiff to construct a second set. Defendant formally rejected this claim on April 12,1988 and plaintiff filed suit in this court on March 29, 1989 seeking to recover the costs associated with its work on the second first article units. Thereafter, defendant moved for summary judgment. While this motion was fully briefed and pending before the court, defendant amended its answer to assert counterclaims against plaintiff under RUSCC 15(a) and 13(f). Be[609]*609cause defendant’s counterclaim had not been briefed by either party at this time, this decision does not reach the issues raised in defendant’s counterclaim.

DISCUSSION

Summary judgment is appropriate when a court finds that there is no genuine issue of material fact and that the movant is entitled to summary judgment as a matter of law. Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987). The court must resolve all significant doubt over factual issues, if any, in favor of the nonmovant and draw all reasonable inferences against the party whose motion is being considered. Id. at 1390-91. Defendant has supported its motion with affidavits and other evidence which unopposed would establish its right to judgment. Plaintiff’s response did not sit idle and rest upon the general denials in its pleadings or otherwise but proffered rebuttal evidence in its attempt to create a genuine factual dispute. Sweats Fashions, Inc. v. Pannill Knitting Co., 833 F.2d 1560, 1562 (Fed.Cir.1987) (citations omitted). However, a genuine factual dispute would exist only if, on the entirety of the record, a reasonable jury could resolve a factual matter in favor of the non-movant. Id.

The critical issue disputed in the present action is whether defendant was obligated to pay for the costs and profits associated with producing a second set of first article test units prior to government approval of the original first article.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Sweats Fashions, Inc. v. Pannill Knitting Company, Inc.
833 F.2d 1560 (Federal Circuit, 1987)
International Business Investments, Inc. v. United States
35 Cont. Cas. Fed. 75,668 (Court of Claims, 1989)
Miami Metropolitan Building Corp. v. United States
180 Ct. Cl. 503 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,819, 19 Cl. Ct. 607, 1990 U.S. Claims LEXIS 72, 1990 WL 18471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sdm-corp-v-united-states-cc-1990.