Scully v. Otis Elevator Co.

275 N.E.2d 905, 2 Ill. App. 3d 185
CourtAppellate Court of Illinois
DecidedOctober 12, 1971
Docket53867
StatusPublished
Cited by36 cases

This text of 275 N.E.2d 905 (Scully v. Otis Elevator Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scully v. Otis Elevator Co., 275 N.E.2d 905, 2 Ill. App. 3d 185 (Ill. Ct. App. 1971).

Opinion

2 Ill. App.3d 185 (1971)
275 N.E.2d 905

VERONICA SCULLY et al., Plaintiffs-Appellees, Appellants-Cross-Appellants,
v.
OTIS ELEVATOR COMPANY, et al., Defendants-Appellants-Cross-Appellees — (J.L. SIMMONS COMPANY, INC., Counter-Plaintiff-Appellant.)

No. 53867.

Illinois Appellate Court — First District.

October 12, 1971.
Rehearing denied November 9, 1971.

*186 *187 *188 *189 *190 John J. Sullivan and William J. Harte, both of Chicago, for appellants.

Forrest L. Tozer, Thomas W. Dempsey, and Clausen, Hirsh, Miller & Gorman, all of Chicago, for appellees.

Judgment affirmed.

Mr. JUSTICE STAMOS delivered the opinion of the court:

Plaintiffs, as widow and lineal heirs of the decedent Robert Scully, instituted this action against defendants alleging violations of the Structural Work Act (Ill. Rev. Stat. 1961, ch. 48, par. 60-69.) Defendants in the cause were Otis Elevator Company, J.L. Simmons Co., Inc. and the architectural firm of Berners, Scober & Kilp. A counter-claim for indemnity was also instituted by Simmons against Otis. The jury found in favor of plaintiffs and against Otis and Simmons. Damages were assessed at $400,000 in favor of plaintiff Veronica Scully and $150,000 in favor of each of the minor plaintiffs. The jury also found in favor of Berners, Schober & Kilp and against plaintiffs. On the counter-claim the jury found in favor of counter-defendant Otis and against counter-plaintiff Simmons.

Plaintiffs and defendants, Otis and Simmons, all filed post-trial motions requesting judgments notwithstanding the verdicts or in the alternative, new trials. In its post-trial motion, Otis also requested a remittitur as alternative relief. The trial court denied all the post-trial motions contingent upon the two minor plaintiffs, by their mother and next friend, filing written consents in reduction of judgment. The consents to remittitur were filed and the court entered judgments in favor of plaintiff Veronica Scully in the amount of $400,000; in favor of the minor plaintiff John Scully in the amount of $95,000; and in favor of the minor plaintiff Kathleen Scully in the amount of $105,000. Otis appeals from the judgments entered against it and in favor of the plaintiffs. Simmons appeals from the judgments entered against it and in favor of the plaintiffs and *191 counter-defendant Otis. Plaintiffs cross-appeal from the entry of the remittitur.

The evidence reveals that defendant, Berners, Schober & Kilp, was hired to design an addition to St. Joseph's Hospital in Joliet, Illinois. It was to prepare preliminary plans and prime contract and generally administer construction. Eleven prime contracts were awarded in the construction of the addition. No sub-contracts were involved. Two of these contracts were awarded to defendants Simmons and Otis. Simmons contracted with the hospital to handle all of the general work including excavation, masonry, concrete and finishing. Simmons was also directed by the architects to prepare a critical path schedule of the work in order to coordinate the efforts of the other contractors. Otis contracted to install eight elevators and dumbwaiters. The Simmons and Otis contracts provided that Simmons was to prepare the shafts for the installation of the elevators.

On July 25, 1962, Robert Stein, an architect, told James Dempsey, Otis' foreman, that he wanted Otis to work on elevator shafts six and seven, since the bricklayers and terrazzo men were being delayed in their work schedules in that area. However, Dempsey informed Stein that Otis could not work on those shafts because Simmons had constructed a bricklayers' scaffold over shaft seven at the eighth floor. Later the same day, Vern Castell, Simmons' Construction Superintendent, informed Dempsey that he would make arrangements with his bricklayer foreman, James Delaney, to prepare for Otis' work.

The next morning at 8:30 A.M. Dempsey told Delaney that openings would have to be cut in the scaffold over shaft seven to enable Otis to proceed with the installation of the elevators. The openings were necessary so that plumb lines could be dropped into the shaft to accurately align the elevator guide rails. Dempsey also told Delaney that there would be men working beneath the scaffold in the shaft cleaning out the pit which extended seven feet below basement level. The pit had been designed to accommodate equipment capable of stopping an elevator's descent. Delany at first objected to the opening of the holes for safety reasons, but eventually consented. Dempsey told Simmons' carpenters the size and location of the required openings. After the openings were cut some of Simmons' bricklayers placed pallets of bricks on the scaffold to facilitate their work in the area. They also took the metal retaining bands off the pallets. Dempsey went to the tenth floor and dropped four plumb lines in shaft six[*] and four plumb lines in shaft seven. The plumb *192 lines extended from the tenth floor, through the openings in the scaffold, to the basement.

Dempsey intended to anchor the plumb lines in the basement. However, when he went to the basement, he discovered that Simmons' laborers were cleaning out the elevator pit. When Dempsey discovered Simmons' workers in the pit, he warned them that bricklayers were working above them on the scaffold. Since Dempsey was unable to proceed with the measurements until the pit was cleaned, he returned to shaft one where he had been working previously.

Later in the day Dempsey returned to the pit in shaft seven and learned that the Simmons' workers were unable to dry the pit due to a drainage problem. Castell asked Scully, plaintiffs' decedent and a plumber, to help with the problem. Scully obtained a test plug and handed it down to one of the men in the pit. As he leaned over to look into the pit, he was struck on the head and fatally injured by a brick which fell from the scaffold. The only bricklayers working in the shaft were on the eighth floor scaffold. On the eighth floor Delaney had seen two or three bricks fall through one of the openings in the scaffold. The bricks fell because of the vibration caused by the hydraulic buggy that Simmons' workers were using to carry the brick pallets. Shortly before the accident, Melville Anderson, Simmons' masonry foreman and Delaney's superior, had seen the openings in the scaffold and told someone to cover them. The openings were again ordered to be covered by Delaney just before the accident.

Otis contends that there was no proof that it had "charge" of the work within the meaning of section 9 of the Structural Work Act, hence it is entitled to a judgment notwithstanding the verdict. Alternatively Otis contends that it is entitled to a new trial, since the verdict finding it liable under the Act was against the manifest weight of the evidence.

• 1-3 Section 9 of the Structural Work Act renders liable, "any * * * contractor * * * having charge of the erection, construction, repairing, [or] alteration * * * of any building * * * within the provisions of this act," who wilfully violate its provisions.

In Larson v. Commonwealth Edison Co. (1965), 33 Ill.2d 316, the court was confronted with the issue of whether there was a need to instruct jurors with the definition of the statutory words "having charge of." The court stated at page 323:

"We do not believe such a need exists.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KHOURY VS. SEASTRAND C/W 65007/65172
2016 NV 52 (Nevada Supreme Court, 2016)
Rub v. Consolidated Rail Corp.
Appellate Court of Illinois, 2002
Schrock v. Shoemaker
640 N.E.2d 937 (Illinois Supreme Court, 1994)
Joyce v. Explosives Technologies International, Inc.
625 N.E.2d 446 (Appellate Court of Illinois, 1993)
Harvel v. City of Johnston City
586 N.E.2d 1217 (Illinois Supreme Court, 1992)
DeYoung v. Alpha Construction Co.
542 N.E.2d 859 (Appellate Court of Illinois, 1989)
Pickett v. Yellow Cab Co.
537 N.E.2d 933 (Appellate Court of Illinois, 1989)
Beeding v. Olin Chemical Corp.
446 N.E.2d 873 (Appellate Court of Illinois, 1983)
Kinsey v. Kolber
431 N.E.2d 1316 (Appellate Court of Illinois, 1982)
Stach v. Sears, Roebuck & Co.
429 N.E.2d 1242 (Appellate Court of Illinois, 1981)
Norton v. Wilbur Waggoner Equipment Rental & Excavating Co.
403 N.E.2d 108 (Appellate Court of Illinois, 1980)
Liepelt v. Norfolk & Western Railway Co.
378 N.E.2d 1232 (Appellate Court of Illinois, 1978)
Frederick v. Zeigler Coal Co.
372 N.E.2d 730 (Appellate Court of Illinois, 1978)
Crothers v. La Salle Institute
370 N.E.2d 213 (Illinois Supreme Court, 1977)
Peluso v. Singer General Precision, Inc.
365 N.E.2d 390 (Appellate Court of Illinois, 1977)
Gasiorowski v. Homer
365 N.E.2d 43 (Appellate Court of Illinois, 1977)
Taskay v. Foschi Brothers Inc.
358 N.E.2d 730 (Appellate Court of Illinois, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
275 N.E.2d 905, 2 Ill. App. 3d 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scully-v-otis-elevator-co-illappct-1971.