Scovill Fasteners, Inc. v. Northern Metals, Inc.

692 S.E.2d 840, 303 Ga. App. 246, 2010 Fulton County D. Rep. 1163, 71 U.C.C. Rep. Serv. 2d (West) 263, 2010 Ga. App. LEXIS 323
CourtCourt of Appeals of Georgia
DecidedMarch 29, 2010
DocketA09A2268
StatusPublished
Cited by7 cases

This text of 692 S.E.2d 840 (Scovill Fasteners, Inc. v. Northern Metals, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scovill Fasteners, Inc. v. Northern Metals, Inc., 692 S.E.2d 840, 303 Ga. App. 246, 2010 Fulton County D. Rep. 1163, 71 U.C.C. Rep. Serv. 2d (West) 263, 2010 Ga. App. LEXIS 323 (Ga. Ct. App. 2010).

Opinion

Doyle, Judge.

Northern Metals, Inc. sued Scovill Fasteners, Inc. for breach of contract based on Scovill’s failure to pay for metal raw material delivered to Scovill by Northern. Scovill counterclaimed, alleging that Northern had breached by failing to deliver the metal in compliance with contractual specifications and deadlines. Following a bench trial, the trial court awarded Northern certain damages, including pre-judgment interest, offset by other damages awarded to Scovill. Scovill filed this appeal contending that the trial court erred by (1) considering parol evidence in interpreting a written two-week delivery deadline, and thereby barring certain cover damages for deliveries past the deadline, (2) denying Scovill’s counterclaim for certain alleged overcharges, and (3) awarding pre-judgment interest pursuant to OCGA § 7-4-16. For the reasons that follow, we affirm in part and reverse in part.

While we apply a de novo standard of review to any questions of law decided by the trial court, factual findings *247 made after a bench trial shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses. Because the clearly erroneous test is in effect the same standard as the any evidence rule, appellate courts will not disturb fact findings of a trial court if there is any evidence to sustain them. 1

So viewed, the evidence shows that in late 2003, Scovill issued a Request for Quotation (“RFQ”) to suppliers of raw materials for Scovill’s metal fastener manufacturing business. Northern responded and was called to meet to discuss the terms of the contract. The RFQ included a provision stating that pricing would be discounted by two percent if Scovill paid within forty-five days of shipment; Northern negotiated a change, memorialized in an RFQ update, that deleted the discount and required Scovill to pay within sixty days of shipment. The RFQ also included a provision stating that lead times for delivery would be “[o]ne week for designated stock keeping items, [two] weeks for all other items.” In the RFQ, Scovill promised to provide “a forecast of usage quarterly for the three months going forward,” to allow suppliers to obtain necessary stock. Before Northern was awarded the contract, Northern made it clear to Scovill that it would need a three-month lead time to begin stocking any items, because they were coming from overseas suppliers. Northern was selected as a provider under the RFQ to supply a Georgia-based plant. Northern was also selected to provide a onetime delivery of material to a Scovill facility in Hong Kong.

From the beginning of the contract in February 2004, Scovill encountered delays with Northern’s shipments to both the Georgia facility and the Hong Kong facility. Based on the delays, Scovill refused to pay for the shipments within the required 60-day time frame, and in some cases (including the Hong Kong shipment), Scovill did not pay at all despite ultimately receiving and accepting the material. In December 2004, Scovill instructed Northern not to order any more material from its overseas supplier, and Northern informed Scovill that it would not ship any more material until certain outstanding balances were paid. The last shipment Scovill received was in March 2005.

Northern sued Scovill for breach of contract seeking damages for unpaid principal on shipped material, unpurchased material, interest, and attorney fees. Scovill answered and counterclaimed, seeking payment for overcharges and cover damages it incurred as a result of *248 the delayed shipments. Following a bench trial, the trial court ruled that Scovill failed to pay for certain delivered material and entered judgment against Scovill for $281,175.29 in principal (for the material) and $109,320.86 in interest for delayed payment. The trial court also entered judgment against Northern for $21,710.45 for certain of Scovill’s cover damages and Northern’s overcharges. Scovill now appeals.

1. Relying on the parol evidence rule, Scovill contends that the trial court erred in denying its claim for cover damages incurred when materials over the stock amounts were not delivered within the written two-week deadline provided in the RFQ. We disagree.

At trial, the evidence showed that to execute the contract, Scovill issued blanket purchase orders containing specifications for material but no amounts or actual delivery dates. Then, on an as-needed basis, Scovill would issue Northern “releases” that specified how much of what material was needed. Northern expected that it could rely on Scovill’s three-month lead time to obtain material from its overseas supplier and keep material in stock for timely release to Scovill. At times, the three-month predictions were overwhelmed by Scovill’s requirements, and for various other reasons, including a fire at the overseas mill, most if not all of Northern’s shipments were ultimately delayed.

The trial court found that, due to Northern’s delays, Scovill “did in fact obtain metal product from other vendors at a higher cost than what it had contracted to pay [Northern] for the same product.” However, the court ruled that Scovill was not entitled to all of the cover damages it sought, specifically excluding cover damages “where the amount of metal product purchased from other venders exceeded the amounts required to be kept on hand in the annual usage and stock requirement document provided by [Scovill] to [Northern].”

This ruling was based on the nature of the negotiated RFQ process and evidence of a mutual understanding between Scovill and Northern that Northern was ordering material from overseas and would need three months to obtain any amounts of material it would deliver under the contract. Scovill acknowledges that conversations occurred to this effect, but it now argues that, despite the clear communication by Northern, Northern was bound by the written RFQ provision defining delivery deadlines as “[o]ne week for designated stock keeping items, [two] weeks for all other items.” In essence, Scovill argues that the written two-week deadline for “all other items” is dispositive as to any material it ordered.

As this was a contract for the sale of goods, we analyze the *249 contract and its execution under the Uniform Commercial Code. 2 Pursuant to OCGA § 11-2-202:

Terms with respect to which the confirmatory memo-randa of the parties agree or which are otherwise set forth in a writing intended by the parties as a final expression of their agreement with respect to such terms as are included therein may not be contradicted by evidence of any prior agreement or of a contemporaneous oral agreement but may be explained or supplemented:
(a) By course of dealing or usage of trade (Code Section 11-1-205) or by course of performance (Code Section 11-2-208); and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
N.D. Georgia, 2026
SER U-Haul v. Hon. Paul Zakaib, Jr., Judge
West Virginia Supreme Court, 2013
State ex rel. U-Haul Co. v. Zakaib
752 S.E.2d 586 (West Virginia Supreme Court, 2013)
Rollins, Inc. v. Carrier Corporation
Court of Appeals of Georgia, 2012
Carrier Corp. v. Rollins, Inc.
730 S.E.2d 103 (Court of Appeals of Georgia, 2012)
Kitchen International, Inc. v. Evans Cabinet Corp.
714 S.E.2d 139 (Court of Appeals of Georgia, 2011)
Securities & Exchange Commission v. Price
108 F. Supp. 3d 1342 (N.D. Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
692 S.E.2d 840, 303 Ga. App. 246, 2010 Fulton County D. Rep. 1163, 71 U.C.C. Rep. Serv. 2d (West) 263, 2010 Ga. App. LEXIS 323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scovill-fasteners-inc-v-northern-metals-inc-gactapp-2010.