Schuster Construction Services, Inc. v. Painia Development Corp.

651 N.W.2d 749, 251 Mich. App. 227
CourtMichigan Court of Appeals
DecidedAugust 23, 2002
DocketDocket 228809
StatusPublished
Cited by4 cases

This text of 651 N.W.2d 749 (Schuster Construction Services, Inc. v. Painia Development Corp.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schuster Construction Services, Inc. v. Painia Development Corp., 651 N.W.2d 749, 251 Mich. App. 227 (Mich. Ct. App. 2002).

Opinion

Zahra, P.J.

Defendant Painia Development Corporation 1 appeals by delayed application for leave to appeal granted from an order denying defendant summary disposition and granting plaintiff summary disposition in this action for foreclosure of a lien under the Construction Lien Act (cla), MCL 570.1101 el seq. We affirm in part, vacate in part, and remand for proceedings consistent with this opinion.

I. FACTS and procedure

Defendant is the owner and developer of the Ariel Square Condominium project in Detroit. Defendant recorded a notice of commencement with the Wayne County Register of Deeds, as required by the cla. *229 MCL 570.1108. Defendant hired Roper to perform rough carpentry work on the project, for a contract amount in excess of $200,000.

Plaintiff leased a forklift to Roper for use on the Ariel Square project. The forklift was delivered to Roper at the work site on July 30, 1998, and remained there until retrieved by plaintiff on March 10, 1999. Plaintiff claims to have billed Roper $11,652.63 for use of the forklift and received payments of only $1,728.88, leaving a balance due of $9,923.75.

Defendant paid Roper the full contract amount through a series of partial payments. Defendant made its final payment to Roper of $4,500 on February 18, 1999. Roper submitted a sworn statement in connection with that final payment, which did not list any supplier or other lien claimant. See MCL 570.1105(2) and MCL 570.1110(1). Roper did not submit a sworn statement in connection with any of the other partial payments it received.

Plaintiff filed a notice of furnishing under the cla on April 29, 1999. See MCL 570.1109. Plaintiff does not claim to have otherwise notified defendant of its interest before defendant paid Roper in full. 2 On May 25, 1999, plaintiff recorded a claim of lien against the project with the Wayne County Register of Deeds. See MCL 570.1107.

Plaintiff filed this action to foreclose the hen on November 23, 1999. Defendant moved for summary disposition on the basis that it paid Roper in full in *230 reliance on Roper’s sworn statement before plaintiff filed its notice of furnishing. The trial court granted summary disposition for plaintiff. Judgment was entered on June 15, 2000, entitling plaintiff to a construction lien in the amount of $9,923.75, plus costs and attorney fees in the amount of $4,944.50, and statutory interest. Defendant’s claim of appeal to this Court was dismissed because of plaintiff’s unresolved claim against Roper. 3 This Court eventually granted defendant’s delayed application for leave to appeal. 4 Thereafter, defendant filed a motion with this Court for peremptoiy reversal. That motion was denied 5 and this appeal ensued.

H. ANALYSIS

A. STANDARD OF REVIEW

This Court reviews de novo a trial court’s decision on a motion for summary disposition. Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999). Likewise, issues arising from the interpretation and application of statutes are reviewed de novo. Oakland Co Bd of Co Rd Comm’rs v Michigan Property & Casualty Guaranty Ass’n, 456 Mich 590, 610; 575 NW2d 751 (1998). In reviewing a motion under MCR 2.116(C)(10), this Court considers the affidavits, *231 pleadings, depositions, admissions, or any other documentary evidence submitted in a light most favorable to the nonmoving party to decide whether a genuine issue of material fact exists. Ritchie-Gamester v City of Berkley, 461 Mich 73, 76; 597 NW2d 517 (1999); Rollert v Dep’t of Civil Service, 228 Mich App 534, 536; 579 NW2d 118 (1998). All reasonable inferences are resolved in the nonmoving party’s favor. Hampton v Waste Mgt of Michigan, Inc, 236 Mich App 598, 602; 601 NW2d 172 (1999).

B. PLAINTIFF’S CLAIM FOR A CONSTRUCTION LIEN UNDER THE CLA

Defendant first argues that the trial court erred in interpreting the cla to allow plaintiff to take a lien. Defendant claims it had the right to rely on Roper’s sworn statement, which did not name any other lien claimant, and that plaintiff’s hen was barred because plaintiff failed to timely tile a notice of furnishing within twenty days of supplying the forklift.

The primary goal of judicial interpretation of statutes is to ascertain and give effect to the Legislature’s intent. Frankenmuth Mut Ins Co v Marlette Homes, Inc, 456 Mich 511, 515; 573 NW2d 611 (1998). If the plain and ordinary meaning of a statute is clear, judicial construction is neither necessary nor permitted. Elia v Hazen, 242 Mich App 374, 381; 619 NW2d 1 (2000). We may not speculate regarding the probable intent of the Legislature beyond the words expressed in the statute. In re Schnell, 214 Mich App 304, 310; 543 NW2d 11 (1995). When reasonable minds may differ regarding the meaning of a statute, the courts must look to the object of the statute, the harm it is designed to remedy, and apply a reasonable construe *232 tion that best accomplishes the purpose of the statute. Marquis v Hartford Accident & Indemnity (After Remand), 444 Mich 638, 644; 513 NW2d 799 (1994).

In Vugterveen Systems, Inc v Olde Millpond Corp, 454 Mich 119, 121-124; 560 NW2d 43 (1997), our Supreme Court provided a useful overview of the parties’ interests under the cla:

The [cla] is based on an exchange of information between the owner of the property, the general contractor, subcontractors, material suppliers, and laborers. See [1 Cameron, Michigan Real Property Law (2d ed)] § 19.18, pp 802-803. The act creates this flow of information through a series of documents that provide the information necessary to allow the parties to protect their interests. McAlpine & Keating, Construction Liens in Michigan, § 4.1, p 4-3.
Normally, this flow of information begins with the property owner. The act requires an owner to file a notice of commencement with the register of deeds before any improvement is made on the property. MCL 570.1108; MSA 26.316(108). See McAlpine & Keating, supra, § 4.5, pp 4-7 to 4-8____
After the notice of commencement is filed, any entity listed in the act who performs improvements on the property is required to provide notice that it has begun work through a notice of furnishing. MCL 570.1109; MSA 26.316(109). McAlpine & Keating, supra, §§ 4.13-4.16, pp 4-13 to 4-16. In most cases, a subcontractor is required to provide a notice of furnishing to the owner and the general contractor within twenty days after first furnishing labor or material. MCL 570.1109(1); MSA 26.316(109)(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carol Dubuc v. Copeland Paving Inc
Michigan Court of Appeals, 2016
Straub v. Collette
657 N.W.2d 178 (Michigan Court of Appeals, 2003)
Steelcon, Inc. v. Bennett & Wright Group, Inc.
257 F. Supp. 2d 895 (E.D. Michigan, 2003)
Cox v. SYLVAN TREETOPS RESORT
651 N.W.2d 749 (Michigan Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
651 N.W.2d 749, 251 Mich. App. 227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schuster-construction-services-inc-v-painia-development-corp-michctapp-2002.