Carol Dubuc v. Copeland Paving Inc

CourtMichigan Court of Appeals
DecidedMarch 29, 2016
Docket325228
StatusUnpublished

This text of Carol Dubuc v. Copeland Paving Inc (Carol Dubuc v. Copeland Paving Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carol Dubuc v. Copeland Paving Inc, (Mich. Ct. App. 2016).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

CAROL DUBUC and DENNIS DUBUC, UNPUBLISHED March 29, 2016 Plaintiffs/Counter- Defendants/Appellants,

v No. 325228 Livingston County Circuit Court COPELAND PAVING INC., LC No. 13-027785-CK

Defendant/Counter-Plaintiff/Cross- Defendant,

AJAX MATERIALS CORPORATION,

Defendant/Counter-Plaintiff/Cross- Plaintiff/Appellee,

and

ESSEX PARK LAW OFFICE P.C.,

Counter-Defendant.

Before: GLEICHER, P.J., and MURPHY and OWENS, JJ.

PER CURIAM.

Plaintiffs Carol and Dennis Dubuc filed suit challenging construction liens taken against their property by a paving contractor and asphalt supplier. The circuit court ultimately upheld the supplier’s lien and ordered the Dubucs to make payment, and the paving company withdrew its claim. The Dubucs take issue with being held liable for the supplier’s $32,574 lien when they had already made a down payment to the contractor and owed significantly less than the lien amount under their general contract. Despite the Dubucs’ many appellate challenges to this award, the court properly interpreted the Construction Lien Act (CLA), MCL 570.1101 et seq. and held the Dubucs liable for the full lien amount. The court also properly awarded the supplier its reasonable attorney fees and costs under the act. We affirm.

-1- I. BACKGROUND

Carol and Dennis Dubuc own Essex Park Law Office. On May 30, 2013, the Dubucs contracted with Copeland Paving to repave their parking lot.1 Copeland entered into a subcontract with Ajax Materials Corporation to supply the necessary asphalt. When Ajax supplied the materials, it served a “notice of furnishing” on the Dubucs through Essex Park. The Dubucs contended that Copeland did not properly grade the parking lot, which caused runoff water to flood a building in the office park. The Dubucs further accused Ajax of supplying, and Copeland of using, less asphalt than contracted for.

The Dubucs had submitted a down payment to Copeland of $25,963. As a result of the difficulties experienced, the Dubucs withheld the remainder due—$24,504. Copeland in turn did not pay Ajax $32,574, which included a time-price differential, owed for the asphalt supplied. Both Copeland and Ajax recorded liens against Essex Park for the amounts owed as permitted by the CLA.

The Dubucs subsequently filed breach of contract and fraud claims against Copeland and Ajax based on the allegedly deficient work and shortfall of asphalt used.2 Ajax and Copeland responded with countercomplaints against the Dubucs and Essex Park to foreclose on their liens. Copeland accused the Dubucs of breaching their contract by failing to pay the full contract price. And Ajax filed a cross-complaint against Copeland for payment under the subcontract.

Ultimately, Ajax filed a motion for summary disposition of the Dubucs’ claims while the claims between Copeland and the Dubucs were still being fleshed out through discovery. The circuit court ruled in Ajax’s favor. The Dubucs conceded that they had no contract with Ajax and therefore no breach of contract claim. Moreover, any discrepancy in the amount of asphalt provided was too minimal to support an intent to defraud. The court also ruled in Ajax’s favor regarding the validity of its construction lien. As the Dubucs were ordered to pay the entirety of Ajax’s damages, Ajax withdrew its cross-complaint against Copeland. Several months later, Copeland and the Dubucs and Essex Park stipulated to dismiss their claims against each other.

The circuit court further ordered the Dubucs to pay Ajax’s attorney fees and costs. The court supported its decision on several grounds, including its finding that the Dubucs’ challenge to Ajax’s lien was frivolous and that the CLA required reimbursement for such fees.

The Dubucs now appeal the circuit court’s award of summary disposition in Ajax’s favor, specifically by challenging the validity of Ajax’s construction lien. They also appeal the court’s award of attorney fees and costs to Ajax.

1 Another property owner within the business park also secured Copeland’s services. That contract is not at issue in this case. 2 The Dubucs filed suit in district court. The action was later transferred to the circuit court because the actual amount in controversy exceeded the district court’s jurisdictional limits.

-2- II. VALIDITY OF THE CONSTRUCTION LIEN

The circuit court entered summary disposition in Ajax’s favor pursuant to MCR 2.116(C)(8) and (C)(10). We review de novo a circuit court’s summary disposition resolution. Zaher v Miotke, 300 Mich App 132, 139; 832 NW2d 266 (2013).

A motion under MCR 2.116(C)(8) “tests the legal sufficiency of the complaint on the basis of the pleadings alone to determine if the opposing party has stated a claim for which relief can be granted.” Begin v Mich Bell Tel Co, 284 Mich App 581, 591; 773 NW2d 271 (2009). We must accept all well-pleaded allegations as true and construe them in the light most favorable to the nonmoving party. Id. The motion should be granted only if no factual development could possibly justify recovery. Id. [Zaher, 300 Mich App at 139.]

“A motion under MCR 2.116(C)(10) ‘tests the factual support of a plaintiff’s claim.’ ” Id. at 139, quoting Walsh v Taylor, 263 Mich App 618, 621; 689 NW2d 506 (2004). Summary disposition is warranted under this rule “if there is no genuine issue regarding any material fact and the moving party is entitled to judgment as a matter of law.” West v Gen Motors Corp, 469 Mich 177, 183; 665 NW2d 468 (2003). This Court must consider “the pleadings, admissions, affidavits, and other relevant documentary evidence of record in the light most favorable to the nonmoving party to determine whether any genuine issue of material fact exists to warrant a trial.” Walsh, 263 Mich App at 621. “A genuine issue of material fact exists when the record, giving the benefit of reasonable doubt to the opposing party, leaves open an issue upon which reasonable minds might differ.” West, 469 Mich at 183.

The meat of this case revolves around the CLA, which is “intended to protect the interests of contractors, workers, and suppliers through construction liens, while protecting owners from excessive costs.” Vugterveen Sys, Inc v Olde Millpond Corp, 454 Mich 119, 121; 560 NW2d 43 (1997). The foundation of these protections is “an exchange of information between the owner of the property, the general contractor, subcontractors, material suppliers, and laborers.” Id. The documents that must be posted, recorded, or exchanged “provide the information necessary to allow the parties to protect their interests.” Id.

Here, Ajax protected its interests by serving a notice of furnishing to the Dubucs when it supplied asphalt to be incorporated into the Dubucs’ property. Ajax also recorded a lien against the Dubucs’ property to secure its right to payment for that asphalt. The Dubucs challenge the validity of Ajax’s lien on several grounds. First, they contend that the lien was invalid at its inception pursuant to MCL 570.1107(6) of the CLA. MCL 570.1107 governs the rights of parties to file liens against an owner’s property. It provides, in relevant part:

(1) Each contractor, subcontractor, supplier, or laborer who provides an improvement to real property has a construction lien upon the interest of the owner or lessee who contracted for the improvement to the real property, as described in the notice of commencement given under [MCL 570.108 or MCL 570.108a], the interest of an owner who has subordinated his or her interest to the mortgage for the improvement of the real property, and the interest of an owner who has required the improvement. A construction lien acquired pursuant to this

-3- act shall not exceed the amount of the lien claimant’s contract less payments made on the contract.

* * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robinson v. City of Edmond
160 F.3d 1275 (Tenth Circuit, 1998)
Smith v. Khouri
751 N.W.2d 472 (Michigan Supreme Court, 2008)
West v. General Motors Corp.
665 N.W.2d 468 (Michigan Supreme Court, 2003)
Schuster Construction Services, Inc. v. Painia Development Corp.
651 N.W.2d 749 (Michigan Court of Appeals, 2002)
Reed v. Reed
693 N.W.2d 825 (Michigan Court of Appeals, 2005)
Harvlie v. Jack Post Corp.
760 N.W.2d 277 (Michigan Court of Appeals, 2008)
Vugterveen Systems, Inc. v. Olde Millpond Corp.
560 N.W.2d 43 (Michigan Supreme Court, 1997)
Begin v. Michigan Bell Telephone Co.
773 N.W.2d 271 (Michigan Court of Appeals, 2009)
Walsh v. Taylor
689 N.W.2d 506 (Michigan Court of Appeals, 2004)
Detroit Public Schools v. Conn
308 Mich. App. 234 (Michigan Court of Appeals, 2014)
Netting Co. v. Touscany
225 N.W. 556 (Michigan Supreme Court, 1929)
Michigan Pipe & Valve-Lansing, Inc. v. Hebeler Enterprises, Inc.
808 N.W.2d 323 (Michigan Court of Appeals, 2011)
PIC Maintenance, Inc. v. Department of Treasury
809 N.W.2d 669 (Michigan Court of Appeals, 2011)
Zaher v. Miotke
832 N.W.2d 266 (Michigan Court of Appeals, 2013)
Souden v. Souden
844 N.W.2d 151 (Michigan Court of Appeals, 2013)
Rental Properties Owners Ass'n v. Kent County Treasurer
308 Mich. App. 498 (Michigan Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Carol Dubuc v. Copeland Paving Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carol-dubuc-v-copeland-paving-inc-michctapp-2016.