Schroeder v. Northern States Power Co.

176 N.W.2d 336, 46 Wis. 2d 637, 1970 Wisc. LEXIS 1110
CourtWisconsin Supreme Court
DecidedApril 28, 1970
Docket215
StatusPublished
Cited by9 cases

This text of 176 N.W.2d 336 (Schroeder v. Northern States Power Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schroeder v. Northern States Power Co., 176 N.W.2d 336, 46 Wis. 2d 637, 1970 Wisc. LEXIS 1110 (Wis. 1970).

Opinion

Heffernan, J.

It was undisputed that the medium-pressure gas main located 42 inches below the surface of the road in front of the Saley home was defectively welded. Northern States Power Company, hereinafter referred to as the power company, points out, however, that, although the weld was defective, it had properly contained the gas from 1928 until the time of the explosion in 1966. It contended that the cause for the disjointing of the weld in January, 1966, was negligently performed city excavation work in the street during *641 June, 1965. The only issue on this appeal is whether the jury’s verdict, finding the city of La Crosse causally negligent in that respect, is supported by credible evidence. In Cedarburg Light & Water Comm. v. Allis-Chalmers (1967), 33 Wis. 2d 560, 564, 148 N. W. 2d 13, 149 N. W. 2d 661, the court said:

“Upon review in this court we are committed to the rule that the judgment must be upheld if there is any credible evidence which under any reasonable view admits of an inference supporting the verdict. Burlison v. Janssen (1966), 30 Wis. (2d) 495, 141 N. W. (2d) 274; Zweifel v. Milwaukee Automobile Mut. Ins. Co. (1965), 28 Wis. (2d) 249, 137 N. W. (2d) 6. Our search is only for evidence supporting the jury’s findings. Olson v. Milwaukee Automobile Ins. Co. (1954), 266 Wis. 106, 62 N. W. (2d) 549, 63 N. W. (2d) 740. These standards apply not only as to the presence of negligence but also as to the existence of causation. Milwaukee & Suburban Transport Corp. v. Royal Transit Co. (1966), 29 Wis. (2d) 620, 139 N. W. (2d) 595; Krause v. Menzner Lumber & Supply Co. (1959), 6 Wis. (2d) 615, 95 N. W. (2d) 374.”

The evidence revealed that a 36-inch sewer main had been laid in the center of the road at a depth of 17 feet below the road’s surface. Two gas mains were located south of the center line of the road. A low-pressure main was 36 inches below the surface, and a medium-pressure main — the main that ruptured — was located 42 inches below the surface of the road.

In the spring of 1965 the city of La Crosse experienced the worst flood conditions in its history. The Saley home was located within a few blocks of the Black river. Shortly after the subsidence of the flood conditions, a depression appeared in the street surface in front of the Saley home. The area was barricaded until such time as repairs could be made. In June, 1965, the area was excavated, and it was found that there was a break in the sewer main and in the riser which connected with the *642 sanitary sewer laterals that ran from the Saley home and from the home across the street. The evidence indicated that, during the flood conditions, water had flowed into the sewer and carried with it a portion of the earth that had supported the roadway. When the street was deprived of its subterranean support, it collapsed in the area of the break.

To rectify this situation, the city excavated the street to the level of the broken sewer main 17 feet below the surface of the street. A large area of the blacktop was removed, and the patch that was subsequently placed on the surface of the road was approximately 29 feet in length and 22 feet in breadth. The evidence revealed that this patch was in part placed directly above the area of the broken main. Only a portion of the street area that was broken open was, however, actually excavated to sewer depth. There was evidence to indicate that the city made a rectangular excavation approximately 8 feet by 8 feet in size directly over the break in .the sewer. There was testimony that indicated that the edge of the excavation was approximately a foot and a half from the weld, the disjointing of which caused the fatal explosion six months later.

There was also evidence which the power company contends indicates that the area of the medium-pressure main where the break occurred was within the confines of the excavation, at least in the earlier stages of the excavation. The power company bases this contention upon the fact that, during the course of this excavation, it was necessary for the power company to disconnect the service lateral to the Saley home.

It is undisputed that the city had done the excavation which exposed the service line to which the power company had attached a temporary bridge so that gas service at the Saley home would not be interrupted while the city’s excavation work was going on. Photographs reveal that the disconnection point on the service line was *643 directly over the medium-pressure line which had fractured and within a few inches of where the fracture occurred. The city contended, however, that, as it excavated, sheeting was placed around the perimeters of its excavation to prevent any lateral shift of earth from outside of the work area. The record was replete with testimony .that the entire subsurface soil consisted of river sand, a soil that is notorious for lack of bearing capacity unless properly compacted. It was the contention of the power company and of the plaintiff that the city had failed to properly compact the soil when back-filling the excavation.

After the gas explosion a trench was dug by the power company parallel to the broken main. When the earth was removed from atop the main, the pipe rose an appreciable amount. It was the contention of the plaintiff and of the power company that this was evidence of a diminution of the support of the earth under the pipe. The power company claimed that it was this condition which occasioned the break in the pipe.

When the city completed its repairs to the main sewer and the riser, the earth was replaced and, according to the testimony of Grant Haugstad, a sewage department supervisor, the sand was tamped with a hand tamper every two feet. This procedure was followed until the excavation was filled to the top of the riser, approximately 5 feet above the level of the main sewer and 12 feet below the road surface.

There was testimony to show that good backfilling practice would have dictated flushing water into the excavation to compact the soil. This was not done, according to the city’s witnesses, because the concrete had not yet set. There was evidence to show that, had the city been willing to wait another day, the concrete would have set and the backfilling at this point could have been accomplished by flushing as well as tamping. Although there was evidence that flushing was used after the com *644 pletion of .the fill to the riser level, a careful reading of the transcript reveals no flushing or puddling thereafter. The backfilling continued by alternately filling in a foot and a half or two feet of sand and then hand tamping.

The power company took the position that backfilling by filling and tamping only every two feet and flushing on but one occasion was negligence. That such negligence caused the loss of support to the pipe was demonstrated when the pipe sprang up when the surface earth was removed.

There was also some testimony that the city had used an excessively thick blacktop patch. The city countered this evidence by introducing the results of earth borings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steinberg v. Jensen
553 N.W.2d 820 (Court of Appeals of Wisconsin, 1996)
Olson v. Ratzel
278 N.W.2d 238 (Court of Appeals of Wisconsin, 1979)
Clark v. Corby
249 N.W.2d 567 (Wisconsin Supreme Court, 1977)
Weiss v. Holman
207 N.W.2d 660 (Wisconsin Supreme Court, 1973)
Shier v. Freedman
208 N.W.2d 328 (Wisconsin Supreme Court, 1973)
Grube v. Moths
202 N.W.2d 261 (Wisconsin Supreme Court, 1972)
Gustavson v. Milwaukee & Suburban Transport Corp.
191 N.W.2d 39 (Wisconsin Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
176 N.W.2d 336, 46 Wis. 2d 637, 1970 Wisc. LEXIS 1110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schroeder-v-northern-states-power-co-wis-1970.