Schmidt v. . Reed

30 N.E. 373, 132 N.Y. 108, 43 N.Y. St. Rep. 490, 87 Sickels 108, 1892 N.Y. LEXIS 1163
CourtNew York Court of Appeals
DecidedMarch 8, 1892
StatusPublished
Cited by53 cases

This text of 30 N.E. 373 (Schmidt v. . Reed) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schmidt v. . Reed, 30 N.E. 373, 132 N.Y. 108, 43 N.Y. St. Rep. 490, 87 Sickels 108, 1892 N.Y. LEXIS 1163 (N.Y. 1892).

Opinion

*112 Bradley, J.

At the time stipulated by the contract for its performance the parties came together. The plaintiff was ready to complete the purchase and the defendants had prepared a deed which they proposed to deliver. The plaintiff declined to accept it because he had learned that the time for the maturity of the mortgage, subject to which the title was to be conveyed, was two years earlier than it was represented to be by the contract. This was a mistake of the defendants without fraud or purpose on their part to deceive the plaintiff. The effect of this provision of the contract was that the payment of the principal sum of the mortgage without default in payment of interest should not be enforcible within five years from November 1, 1886. And this provision could be satisfied by an instrument effectually extending until then the time of its payment. When the parties were together on November 15, 1888, the stipulated time to complete the sale and purchase, the defendants, at the time of tendering their deed, also tendered to the plaintiff ample security against any possible damage by reason of the mistake in respect to time of the maturity of the mortgage which was refused by the plaintiff. The defendants also then requested a postponement of the time of performance of the contract for a.week or ten days to enable them to obtain and deliver to the plaintiff an instrument of extension of the time of payment of the mortgage corresponding with that mentioned in the contract. This the plaintiff also refused to grant. On November twenty-third, eight days after that meeting of the parties, the defendant having obtained it from the mortgagee, tendered to the plaintiff a written extension of the time of payment of the principal sum of the mortgage to November 1, 1891, and sufficient money to pay for recording it, with a deed of conveyance of the premises. The plaintiff refused to receive them. He had on the same day and prior to the tender commenced this action by service on the defendant Schmohl, of which the other defendant, when he made the tender, was not advised.

The question is whether this offer of performance at that time by the defendants constituted a defense to the action and *113 entitled tliem to specific performance. "While at law the stipulated time of performance of a contract for the sale and conveyance of land is of the essence of the contract, it is not essentially so in equity, and there, when the situation of the parties and property remains unchanged, relief will not necessarily he defeated by delay. But where there are no circumstances of acquiescence in the delay, reasonable diligence is requisite to such relief. (Edgerton v. Peckham, 11 Paige, 352; Hubbell v. Von Schoening, 49 N. Y. 326.)

The parties to a contract may by its terms make the time of performance essentially important and its observance in that respect requisite to relief. (Benedict v. Lynch, 1 John. Ch. 370.) And when that is not so either of the parties to the contract may, by a reasonable' notice to the other party for that purpose, render the time of performance as of the essence of the contract and avail himself of forfeiture on default. (Myers v. De Mier, 52 N. Y. 647.) Time was not necessarily of the essence of the contract in question. But the trial court found that the plaintiff notified the defendants on the 12th of November, 1888, that the mortgage would mature on the 1st of November, 1889, and that he would not accept a deed of the premises unless the defendants procured for him at the time fixed for the passing of the title, a propel and sufficient extension of the mortgage until November, 1891, and upon that fact the court determined that such notice made time of the essence of the contract.

It is urged on the part of the plaintiff that the notice was insufficient for the purpose, in that the defendants were not by it given a reasonable time to procure the extension, and that it was not specific as to the time when the default would be treated by the plaintiff as a forfeiture of the right to tender performance. The plaintiff did not until the day the notice was given ascertain that the time of maturity of the mortgage was other than that stated in the contract. The mortgagee resided in Philadelphia, of which the plaintiff was advised at the meeting of the fifteenth of November, and whether the three days was a sufficient Or reasonable time to obtain from *114 him the extension before the stipulated time of performance of the contract if it"was obtainable, was a question of fact, as was also the question whether the defendants had used due diligence to procure it at that time. The court did not find that the defendants were or were not chargeable with laches in that respect. But there was evidence on the part of the plaintiff (contradicted by that on the part of the defendants) to the effect that the defendants had then made no effort and done nothing to procure the extension of the mortgage. And while the conflicting evidence on that subject cannot be referred to for the predication of error, it may here, so far as applicable, be considered in support of the conclusion of the trial •coiut. If it appeared by the record that it contained all the ■evidence of the trial it may be that the construction given to ■the finding before mentioned could be the subject of some criticism, as it does not distinctly appear by the evidence that the time when the extension should be produced was specified. The evidence of the plaintiff’s attorney, as there represented, in speaking of the notice given on November twelfth, is : “I told him (defendants’ attorney) we should insist on an extension of the time for the payment of the mortgage, else my client would not take title. He said it seemed ridiculous to now ask an extension,” as the mortgage then had a year to run. “ I said I would submit the matter to the plaintiff,” and added that he informed the defendants or one of them the evening of that or the following day that the plaintiff insisted upon extension of the mortgage to November 1, 1891; and that no purpose was expressed on their part to obtain it, but that on the contrary they said they did not expect to get it at that time. It cannot now and upon the record be held that there was not sufficient evidence to warrant the conclusion that the defendants were advised by the plaintiff that his completion of the purchase was dependant upon the production on the fifteenth of November, of an extension of the time of maturity of the mortgage. It may be that a different question would be presented if it had been found or conclusively established by the evidence that the plaintiff was advised that the *115 purpose or expectation of the defendants was to obtain it. But upon that subject the evidence on the part of the plaintiff (in conflict with that on the part of the defendants) was to the effect that it was then said by the defendants that they would not apply for an extension, and by their attorney that he had made no effort to get it, and that he had no reason' to believe he could obtain it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lashley v. BDL Real Estate Dev. Corp.
212 A.D.3d 800 (Appellate Division of the Supreme Court of New York, 2023)
Brum Realty, Inc. v. Takeda
205 A.D.2d 365 (Appellate Division of the Supreme Court of New York, 1994)
Mohen v. Mooney
162 A.D.2d 664 (Appellate Division of the Supreme Court of New York, 1990)
Sohayegh v. Oberlander
155 A.D.2d 436 (Appellate Division of the Supreme Court of New York, 1989)
Goldring v. Sletco Realty, Inc.
129 Misc. 2d 756 (New York Supreme Court, 1985)
GDJS Corp. v. 917 Properties Inc.
99 A.D.2d 998 (Appellate Division of the Supreme Court of New York, 1984)
Lusker v. Tannen
90 A.D.2d 118 (Appellate Division of the Supreme Court of New York, 1982)
Murphy v. Keil
71 Misc. 2d 844 (New York Supreme Court, 1972)
Drago v. Flewellin
33 A.D.2d 570 (Appellate Division of the Supreme Court of New York, 1969)
Oleg Cassini, Inc. v. Couture Coordinates, Inc.
297 F. Supp. 821 (S.D. New York, 1969)
Michaels v. Flapan
42 Misc. 2d 812 (New York Supreme Court, 1964)
Landow-Luzier Co. v. Grey
34 Misc. 2d 1061 (New York Supreme Court, 1962)
Stolper Steel Products Corp. v. Behrens Mfg. Co.
103 N.W.2d 683 (Wisconsin Supreme Court, 1960)
English Speaking Union (New York) Inc. v. Payson
11 Misc. 2d 669 (New York Supreme Court, 1958)
Green Point Savings Bank v. Central Gardens Unit No. 1, Inc.
279 A.D. 1078 (Appellate Division of the Supreme Court of New York, 1952)
Appleman v. Shorewood Realty Corp.
275 A.D.2d 1046 (Appellate Division of the Supreme Court of New York, 1949)
D'Onfro v. State
270 A.D. 9 (Appellate Division of the Supreme Court of New York, 1945)
In Re Utility Oil Corporation
10 F. Supp. 678 (S.D. New York, 1934)
Mahaney v. 580 Madison Ave., Inc.
135 Misc. 603 (New York Supreme Court, 1930)
McCutcheon v. Kimball
135 Misc. 299 (City of New York Municipal Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
30 N.E. 373, 132 N.Y. 108, 43 N.Y. St. Rep. 490, 87 Sickels 108, 1892 N.Y. LEXIS 1163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schmidt-v-reed-ny-1892.