Schenk v. HNA Holdings, Inc.

613 S.E.2d 503, 170 N.C. App. 555, 24 A.L.R. 6th 919, 2005 N.C. App. LEXIS 1067
CourtCourt of Appeals of North Carolina
DecidedJune 7, 2005
DocketCOA03-1094-2, COA03-1095-2
StatusPublished
Cited by10 cases

This text of 613 S.E.2d 503 (Schenk v. HNA Holdings, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schenk v. HNA Holdings, Inc., 613 S.E.2d 503, 170 N.C. App. 555, 24 A.L.R. 6th 919, 2005 N.C. App. LEXIS 1067 (N.C. Ct. App. 2005).

Opinion

MARTIN, Chief Judge.

Plaintiffs’ appeals in these cases present to this Court identical questions of law; therefore, we have consolidated the appeals pursuant to Rule 40 of the North Carolina Rules of Appellate Procedure. N.C. R. App. P. 40 (2005). The appeals arise from lawsuits in which plaintiffs sought compensatory and punitive damages from defendant, HNA Holdings, Inc., for alleged occupational exposure to asbestos dust and fibers at defendant’s polyester manufacturing plant.

Summarized only to the extent necessary for an understanding of the issues raised on appeal, the evidence at trial tended to show that defendant, HNA Holdings, Inc., or its predecessors in interest, owned the Celanese Fiber Plant (“Celanese”), located in Salisbury, North Carolina, since operations began in 1966. Like many industrial plants built in the 1960’s and 1970’s, the Celanese plant was constructed with insulation containing asbestos.

Daniel Construction Company built the Celanese plant and then provided maintenance for the company in specialty areas such as welding, pipe fitting, rigging and insulation. Daniel Construction Company and its successor in interest, Fluor Daniel (“Daniel”), employed plaintiff Schenk as a pipe fitter/welder beginning in 1975. Plaintiff Schenk worked for Daniel periodically until 1992, when Becon Construction Company (“Becon”) assumed Daniel’s maintenance contract. Plaintiff Schenk continued to work for Becon at Celanese until 1995. As a pipe fitter/welder, plaintiff Schenk was exposed to asbestos-containing insulation both through his work handling pipes and from being around people working with the insulation.

Daniel employed plaintiff Bell as an insulator for Celanese intermittently between 1973 and 1981, and then from 1988 until 1992. In 1992, when Daniel lost the overall maintenance contract to Becon, plaintiff Bell began working as an insulator for Becon and continued until 1995. At trial, plaintiff Bell testified he was exposed to asbestos dust in his work insulating pipes at Celanese while *558 cutting the insulation on a band saw, “rasping” or smoothing the rough edges of the insulation, and while removing asbestos “in every facet of the plant.”

Plaintiffs offered the testimony of James Whitlock (“Whitlock”), an asbestos handling and removal specialist who worked for SOS, a subsidiary of Daniel. Whitlock, who was hired to oversee the removal of asbestos material at Celanese, testified at trial that prior to his arrival in 1990, insulators for Daniel were removing asbestos from the Celanese plant. During his first walk-through of the plant after he was hired, Whitlock observed areas where the asbestos insulation was in a “dilapidated condition and was hanging from the pipes,” areas where insulation was on the floor, and areas where insulation was “in piles.” He also saw non-authorized individuals “handling and removing asbestos.”

Whitlock testified he informed by memorandum the plant industrial hygienist, Dave Smith, the resident engineer, John Winter (“Winter”), and others that “there was a lot of maintenance people that were doing removal of asbestos-containing insulation and that they were leaving the insulation lying around in the areas, and this' was cause for concern because it was causing exposure.” The next day, Winter asked Whitlock to “collect those letters and rip them up, take the letter out of [his] computer, off [his] hard drive, get it off floppy disk, and do away with it.”

For asbestos removal, Whitlock recommended Celanese use a “global abatement procedure.” In this procedure, a large area is contained and asbestos is totally removed from the entire area without other workers present. However, Whitlock’s recommendation was rejected in favor of a “glove bagging” technique, in which only a small area is contained for removal of a small bit or piece of pipe insulation, rather than abatement of the whole area. Other workers were often present during the glove-bagging method.

Prior to trial, the court denied defendant’s motion to strike the punitive damages claim but allowed an alternative motion to exclude any reference to punitive damages or defendant’s financial worth until the court determined that plaintiffs had presented sufficient evidence to submit an issue of punitive damages to the jury. At the close of plaintiffs’ evidence, after hearing arguments, the trial court granted defendant’s motion for directed verdict on the issue of punitive damages.

*559 The jury returned verdicts in favor of plaintiffs, finding the maintenance and construction work performed by plaintiffs was an inherently dangerous activity. The jury also found plaintiffs were injured as a direct result of defendant’s negligence. Plaintiffs were awarded compensatory damages for personal injuries. The trial court then conducted a “set-off’ hearing and reduced the awards by the amount each plaintiff had recovered as a result of prior settlements from other sources. Plaintiffs appeal.

I.

Plaintiffs first assign error to the trial court’s granting of defendant’s motion for directed verdict on the issue of punitive damages. They argue there was sufficient evidence that defendant acted recklessly, willfully or intentionally to withstand defendant’s motion. We do not agree.

“The standard of review of directed verdict is whether the evidence, taken in the light most favorable to the non-moving party, is sufficient as a matter of law to be submitted to the jury.” Davis v. Dennis Lilly Co., 330 N.C. 314, 322, 411 S.E.2d 133, 138 (1991). Our North Carolina statutes establish the requirements for punitive damages as follows:

Punitive damages may be awarded only if the claimant proves that the defendant is liable for compensatory damages and that one of the following aggravating factors was present and was related to the injury for which compensatory damages were awarded:
(1) Fraud.
(2) Malice.
(3) Willful or wanton conduct.

N.C. Gen. Stat. § 1D-I5(a) (2003). The existence of the aggravating factor must be proved by clear and convincing evidence. N.C. Gen. Stat. § 1D-I5(b) (2003). Willful and wanton conduct is defined by statute as “the conscious and intentional disregard of and indifference to the rights and safety of others, which the defendant knows or should know is reasonably likely to result in injury, damage, or other harm.” N.C. Gen. Stat. § lD-5(7) (2003). To award punitive damages against a corporation, “the officers, directors, or managers of the cor *560 poration [must have] participated in or condoned the conduct constituting the aggravating factor giving rise to punitive damages.” N.C. Gen. Stat. § 1D-I5(c) (2003). The jury awarded plaintiffs compensatory damages; therefore, the issue on appeal is whether there was sufficient evidence that the officers, directors, or managers of defendant, HNA Holdings, Inc., participated in or condoned willful or wanton conduct. See id.

Plaintiffs contend Winter’s order to destroy Whitlock’s memorandum constituted willful and wanton conduct by defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plyler v. Cox Brothers, Inc.
W.D. North Carolina, 2023
Dorothy Smith v. Schlage Lock Company, LLC
986 F.3d 482 (Fourth Circuit, 2021)
Hairston v. Harward
821 S.E.2d 384 (Supreme Court of North Carolina, 2018)
Jacokes v. APM Builders, Inc.
Court of Appeals of North Carolina, 2014
George v. Greyhound Lines, Inc.
708 S.E.2d 201 (Court of Appeals of North Carolina, 2011)
Everhart v. O'CHARLEY'S INC.
683 S.E.2d 728 (Court of Appeals of North Carolina, 2009)
Scarborough v. Dillard's Inc.
655 S.E.2d 875 (Court of Appeals of North Carolina, 2008)
Silver v. GMRI, Inc.
650 S.E.2d 676 (Court of Appeals of North Carolina, 2007)
Maurer v. Slickedit, Inc.
2006 NCBC 1 (North Carolina Business Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
613 S.E.2d 503, 170 N.C. App. 555, 24 A.L.R. 6th 919, 2005 N.C. App. LEXIS 1067, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schenk-v-hna-holdings-inc-ncctapp-2005.