Schaller, M. v. Excell Homes, Inc.

Superior Court of Pennsylvania·Decided December 23, 2014·No. 2926 EDA 2013·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

MICHELLE SCHALLER IN THE SUPERIOR COURT OF PENNSYLVANIA

Appellee

v.

EXCELL HOMES, INC.

Appellant No. 2926 EDA 2013

Appeal from the Judgment Entered September 30, 2013 In the Court of Common Pleas of Pike County Civil Division at No(s): 2011-00609

BEFORE: GANTMAN, P.J., PANELLA, J., and STABILE, J. MEMORANDUM BY PANELLA, J. FILED DECEMBER 23, 2014 Appellant, Excell Homes, Inc., appeals from the judgment entered in the Court of Common Pleas of Pike County, after an arbitration panel awarded Appellee, Michelle Schaller, $181,006.11 on her residential construction defect claim. After careful review, we affirm.

Excell contracted with Schaller to build and sell her a residence in Lackawaxen for the price of $299,712. The contract called for any disagreement, save for one involving a default in payment, to be submitted to binding arbitration. The contract further specified that Schaller would select one arbitrator and Excell would select another. These two arbitrators would then agree to the third arbitrator.

Excell built the home and Schaller subsequently filed a motion seeking to require Excell to exercise its authority to designate an arbitrator to

address a disagreement between the parties over the quality of the workmanship on the home. Schaller alleged that the defects in the home would require in excess of $140,000 to repair. Schaller named Charles Kannebecker, Esq., as her appointed arbitrator.

Excell filed an answer indicating that the only issue it had at the time was Schaller’s default in payment for the property. Excell indicated that it had filed a mechanic’s lien against the property, and denied that there were any defects in the workmanship. Excell further denied any responsibility to appoint an arbitrator.

The trial court ordered Excell to appoint an arbitrator. The trial court further held that, pursuant to the contract, Excell’s claims for payment were not subject to arbitration and would be resolved through the mechanic’s lien filed by Excell.

Excell appointed Jeffrey S. Treat, Esq., as an arbitrator, and Attorney Treat and Attorney Kannebecker appointed Mark E. Moulton, Esq., as the chairperson. The arbitration panel held a preliminary hearing in November, 2011, at which Schaller presented her case-in-chief. After this hearing, Excell requested an opportunity to bring a representative from the company that supplied the concrete for the home, as well as an engineer, to examine the concrete in place. Chairperson Moulton memorialized the board’s ruling in a letter to the parties:

There will be no home study or examination of the home by Excell’s engineer. The engineer may examine the concrete to

respond to the issues already raised. If Excell wishes to pursue claims against the concrete company that is outside the scope of this arbitration and no such pre-complaint discovery will be allowed this Friday. I prefer to rely on the professionalism of counsel to limit Friday’s time at the Schaller house to only a 20 to 30 minute examination of the basement concrete floor with core samples drawn if necessary, as a home study is specifically not authorized.

In a subsequent letter to the parties, Chairperson Moulton expanded on this ruling:

The ruling was to allow Excell to obtain a floor sample and not a home investigation. As for the balance of paragraph two, discovery should have been completed prior to the matter being listed for arbitration, and certainly any discovery issues should have been raised and resolved before the arbitration.

The additional request for an engineering inspection is outside the standard for these arbitrations. The panel discussed and ruled that this matter was a “bring it all at once and have the panel sort it out” affair. Aside from the issues of “metal design”

in the basement structure; 2X10 vs 2X12s and correction of the piers in back, I do not note any substantial scientific testimony.

Excell heard what Schaller was complaining of and had the opportunity to note same. Excell can certainly bring their own engineer to provide on the spot replies to the remaining testimony. In fairness, these matters are resolved by on-site presentation.

A second arbitration hearing was held in May 2012, approximately six months after the presentation of Schaller’s case-in-chief. The arbitration panel, in a letter dated May 25, 2012, ruled in favor of Schaller, and awarded her $181,006.11.

Attached to the letter is a document entitled “Accompanying Memo to Board of Arbitrators’ Decision,” dated June 13, 2012. In this memo, Attorney Treat, the arbitrator appointed by Excell, set forth his reasoning in

finding for Schaller. Attorney Treat’s memo highlights the condition of the concrete floor, concluding that “the concrete floor installed clearly fails to meet the requirements of good workmanship.” Attorney Treat further concluded that other defects in the home “resulted from the lack of proper coordination and oversight by the Project Manager …,” while noting that the project manager did not testify at the May hearing.

Schaller petitioned to have judgment entered upon the arbitrators’

award. Excell filed a counter-petition to vacate the arbitrators’ award. Schaller then filed preliminary objections to Excell’s counter-petition. Excell subsequently filed an answer to Schaller’s petition to confirm, and an amended counter-petition, to which Schaller again filed preliminary objections. The trial court granted Schaller’s preliminary objections.

The trial court held a hearing1 on Schaller’s petition to confirm, and later granted Schaller’s petition. Judgment was entered on September 30, 2013, and Excell filed this timely appeal.

1 Excell has included, in the reproduced record, selected portions of the transcript from this hearing. There is no transcript in the certified record. Ordinarily, we can only consider documents which are part of the certified record. Roth Cash Register Company, Inc. v. Micro Systems, Inc., 868 A.2d 1222, 1223 (Pa. Super. 2005). Furthermore, "[i]t is the obligation of the appellant to make sure that the record forwarded to an appellate court contains those documents necessary to allow a complete and judicious assessment of the issues raised on appeal." Everett Cash Mutual Insurance Company v. T.H.E. Insurance Company, 804 A.2d 31, 34 (Pa.Super. 2002)(quoting Hrinkevich v. Hrinkevich, 676 A.2d 237, 240 (Pa.Super. 1996)). However, since Schaller has not objected to the (Footnote Continued Next Page)

On appeal, Excell raises the following issues for our review:

[1.] Whether the trial court erred as a matter of law and abused its discretion in dismissing the appellant’s amended counter petition to vacate arbitration.

[2.] Whether the trial court erred as a matter of law and abused its discretion in dismissing the appellant’s amended counter petition to vacate arbitration award based upon preliminary objections filed pursuant to the Pennsylvania rules of civil procedure.

[3.] Whether the trial court erred as a matter of law and abused its discretion in confirming the arbitration award since the appellant did not receive a full and fair hearing and there was misconduct or irregularities in the proceedings on the part of the arbitrators.

Appellant’s Brief, at 4.

In its first two issues on appeal, Excell argues that the trial court erred in granting Schaller’s preliminary objections to Excell’s petition to vacate the arbitration award. In particular, Excell contends that a party cannot file preliminary objections to a petition. While we agree with Excell on this point of law, we conclude that the error is harmless under these circumstances.

Under the Uniform Arbitration Act, 42 Pa.C.S.A. §§ 7301-7362, a party wishing to have a court confirm or challenge an arbitration award is required to file a petition. See 42 Pa.C.S.A. § 7317.2 The rules governing these

(Footnote Continued)

Free access — add to your briefcase to read the full text and ask questions with AI

Schaller, M. v. Excell Homes, Inc., (Pa. Ct. App. 2014).

Schaller, M. v. Excell Homes, Inc. (Schaller, M. v. Excell Homes, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harleysville Mutual Casualty Co. v. Adair
218 A.2d 791 (Supreme Court of Pennsylvania, 1966)
McKenna v. Sosso
745 A.2d 1 (Superior Court of Pennsylvania, 1999)
Hrinkevich v. Hrinkevich
676 A.2d 237 (Superior Court of Pennsylvania, 1996)
Boyce v. St. Paul Property & Liability Insurance
618 A.2d 962 (Superior Court of Pennsylvania, 1992)
Fox v. Thompson
546 A.2d 1146 (Supreme Court of Pennsylvania, 1988)
Clark v. State Farm Automobile Insurance
599 A.2d 1001 (Superior Court of Pennsylvania, 1991)
Smaligo v. Fireman's Fund Insurance
247 A.2d 577 (Supreme Court of Pennsylvania, 1968)
Cargill v. Northwestern National Insurance
462 A.2d 833 (Supreme Court of Pennsylvania, 1983)
Roth Cash Register Co. v. Micro Systems, Inc.
868 A.2d 1222 (Superior Court of Pennsylvania, 2005)
Haegele v. Pennsylvania General Insurance
479 A.2d 1005 (Supreme Court of Pennsylvania, 1984)
Everett Cash Mutual Insurance v. T.H.E. Insurance
804 A.2d 31 (Superior Court of Pennsylvania, 2002)
Cid v. Erie Insurance Group
63 A.3d 787 (Superior Court of Pennsylvania, 2013)
Savage v. Commercial Union Insurance
473 A.2d 1052 (Superior Court of Pennsylvania, 1984)