Schaller, M. v. Excell Homes, Inc.

CourtSuperior Court of Pennsylvania
DecidedDecember 23, 2014
Docket2926 EDA 2013
StatusUnpublished

This text of Schaller, M. v. Excell Homes, Inc. (Schaller, M. v. Excell Homes, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schaller, M. v. Excell Homes, Inc., (Pa. Ct. App. 2014).

Opinion

J-A17024-14

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

MICHELLE SCHALLER IN THE SUPERIOR COURT OF PENNSYLVANIA Appellee

v.

EXCELL HOMES, INC.

Appellant No. 2926 EDA 2013

Appeal from the Judgment Entered September 30, 2013 In the Court of Common Pleas of Pike County Civil Division at No(s): 2011-00609

BEFORE: GANTMAN, P.J., PANELLA, J., and STABILE, J.

MEMORANDUM BY PANELLA, J. FILED DECEMBER 23, 2014

Appellant, Excell Homes, Inc., appeals from the judgment entered in

the Court of Common Pleas of Pike County, after an arbitration panel

awarded Appellee, Michelle Schaller, $181,006.11 on her residential

construction defect claim. After careful review, we affirm.

Excell contracted with Schaller to build and sell her a residence in

Lackawaxen for the price of $299,712. The contract called for any

disagreement, save for one involving a default in payment, to be submitted

to binding arbitration. The contract further specified that Schaller would

select one arbitrator and Excell would select another. These two arbitrators

would then agree to the third arbitrator.

Excell built the home and Schaller subsequently filed a motion seeking

to require Excell to exercise its authority to designate an arbitrator to J-A17024-14

address a disagreement between the parties over the quality of the

workmanship on the home. Schaller alleged that the defects in the home

would require in excess of $140,000 to repair. Schaller named Charles

Kannebecker, Esq., as her appointed arbitrator.

Excell filed an answer indicating that the only issue it had at the time

was Schaller’s default in payment for the property. Excell indicated that it

had filed a mechanic’s lien against the property, and denied that there were

any defects in the workmanship. Excell further denied any responsibility to

appoint an arbitrator.

The trial court ordered Excell to appoint an arbitrator. The trial court

further held that, pursuant to the contract, Excell’s claims for payment were

not subject to arbitration and would be resolved through the mechanic’s lien

filed by Excell.

Excell appointed Jeffrey S. Treat, Esq., as an arbitrator, and Attorney

Treat and Attorney Kannebecker appointed Mark E. Moulton, Esq., as the

chairperson. The arbitration panel held a preliminary hearing in November,

2011, at which Schaller presented her case-in-chief. After this hearing,

Excell requested an opportunity to bring a representative from the company

that supplied the concrete for the home, as well as an engineer, to examine

the concrete in place. Chairperson Moulton memorialized the board’s ruling

in a letter to the parties:

There will be no home study or examination of the home by Excell’s engineer. The engineer may examine the concrete to

-2- J-A17024-14

respond to the issues already raised. If Excell wishes to pursue claims against the concrete company that is outside the scope of this arbitration and no such pre-complaint discovery will be allowed this Friday. I prefer to rely on the professionalism of counsel to limit Friday’s time at the Schaller house to only a 20 to 30 minute examination of the basement concrete floor with core samples drawn if necessary, as a home study is specifically not authorized.

In a subsequent letter to the parties, Chairperson Moulton expanded on this

ruling:

The ruling was to allow Excell to obtain a floor sample and not a home investigation. As for the balance of paragraph two, discovery should have been completed prior to the matter being listed for arbitration, and certainly any discovery issues should have been raised and resolved before the arbitration.

The additional request for an engineering inspection is outside the standard for these arbitrations. The panel discussed and ruled that this matter was a “bring it all at once and have the panel sort it out” affair. Aside from the issues of “metal design” in the basement structure; 2X10 vs 2X12s and correction of the piers in back, I do not note any substantial scientific testimony. Excell heard what Schaller was complaining of and had the opportunity to note same. Excell can certainly bring their own engineer to provide on the spot replies to the remaining testimony. In fairness, these matters are resolved by on-site presentation.

A second arbitration hearing was held in May 2012, approximately six

months after the presentation of Schaller’s case-in-chief. The arbitration

panel, in a letter dated May 25, 2012, ruled in favor of Schaller, and

awarded her $181,006.11.

Attached to the letter is a document entitled “Accompanying Memo to

Board of Arbitrators’ Decision,” dated June 13, 2012. In this memo,

Attorney Treat, the arbitrator appointed by Excell, set forth his reasoning in

-3- J-A17024-14

finding for Schaller. Attorney Treat’s memo highlights the condition of the

concrete floor, concluding that “the concrete floor installed clearly fails to

meet the requirements of good workmanship.” Attorney Treat further

concluded that other defects in the home “resulted from the lack of proper

coordination and oversight by the Project Manager …,” while noting that the

project manager did not testify at the May hearing.

Schaller petitioned to have judgment entered upon the arbitrators’

award. Excell filed a counter-petition to vacate the arbitrators’ award.

Schaller then filed preliminary objections to Excell’s counter-petition. Excell

subsequently filed an answer to Schaller’s petition to confirm, and an

amended counter-petition, to which Schaller again filed preliminary

objections. The trial court granted Schaller’s preliminary objections.

The trial court held a hearing1 on Schaller’s petition to confirm, and

later granted Schaller’s petition. Judgment was entered on September 30,

2013, and Excell filed this timely appeal.

____________________________________________

1 Excell has included, in the reproduced record, selected portions of the transcript from this hearing. There is no transcript in the certified record. Ordinarily, we can only consider documents which are part of the certified record. Roth Cash Register Company, Inc. v. Micro Systems, Inc., 868 A.2d 1222, 1223 (Pa. Super. 2005). Furthermore, "[i]t is the obligation of the appellant to make sure that the record forwarded to an appellate court contains those documents necessary to allow a complete and judicious assessment of the issues raised on appeal." Everett Cash Mutual Insurance Company v. T.H.E. Insurance Company, 804 A.2d 31, 34 (Pa.Super. 2002)(quoting Hrinkevich v. Hrinkevich, 676 A.2d 237, 240 (Pa.Super. 1996)). However, since Schaller has not objected to the (Footnote Continued Next Page)

-4- J-A17024-14

On appeal, Excell raises the following issues for our review:

[1.] Whether the trial court erred as a matter of law and abused its discretion in dismissing the appellant’s amended counter petition to vacate arbitration.

[2.] Whether the trial court erred as a matter of law and abused its discretion in dismissing the appellant’s amended counter petition to vacate arbitration award based upon preliminary objections filed pursuant to the Pennsylvania rules of civil procedure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harleysville Mutual Casualty Co. v. Adair
218 A.2d 791 (Supreme Court of Pennsylvania, 1966)
McKenna v. Sosso
745 A.2d 1 (Superior Court of Pennsylvania, 1999)
Hrinkevich v. Hrinkevich
676 A.2d 237 (Superior Court of Pennsylvania, 1996)
Boyce v. St. Paul Property & Liability Insurance
618 A.2d 962 (Superior Court of Pennsylvania, 1992)
Fox v. Thompson
546 A.2d 1146 (Supreme Court of Pennsylvania, 1988)
Clark v. State Farm Automobile Insurance
599 A.2d 1001 (Superior Court of Pennsylvania, 1991)
Smaligo v. Fireman's Fund Insurance
247 A.2d 577 (Supreme Court of Pennsylvania, 1968)
Cargill v. Northwestern National Insurance
462 A.2d 833 (Supreme Court of Pennsylvania, 1983)
Roth Cash Register Co. v. Micro Systems, Inc.
868 A.2d 1222 (Superior Court of Pennsylvania, 2005)
Haegele v. Pennsylvania General Insurance
479 A.2d 1005 (Supreme Court of Pennsylvania, 1984)
Everett Cash Mutual Insurance v. T.H.E. Insurance
804 A.2d 31 (Superior Court of Pennsylvania, 2002)
Cid v. Erie Insurance Group
63 A.3d 787 (Superior Court of Pennsylvania, 2013)
Savage v. Commercial Union Insurance
473 A.2d 1052 (Superior Court of Pennsylvania, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Schaller, M. v. Excell Homes, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/schaller-m-v-excell-homes-inc-pasuperct-2014.