Scenic Hudson Preservation Conference v. Federal Power Commission

354 F.2d 608, 1 Envtl. L. Rep. (Envtl. Law Inst.) 20292, 1 ERC (BNA) 1084, 1965 U.S. App. LEXIS 3514
CourtCourt of Appeals for the Second Circuit
DecidedDecember 29, 1965
Docket29853_1
StatusPublished
Cited by12 cases

This text of 354 F.2d 608 (Scenic Hudson Preservation Conference v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scenic Hudson Preservation Conference v. Federal Power Commission, 354 F.2d 608, 1 Envtl. L. Rep. (Envtl. Law Inst.) 20292, 1 ERC (BNA) 1084, 1965 U.S. App. LEXIS 3514 (2d Cir. 1965).

Opinion

354 F.2d 608

1 ERC 1084, 62 P.U.R.3d 134, 1 Envtl.
L. Rep. 20,292

SCENIC HUDSON PRESERVATION CONFERENCE, Town of Cortlandt,
Town of Putnam Valley and Town of Yorktown, Petitioners,
v.
FEDERAL POWER COMMISSION, Respondent, and Consolidated
Edison Company of New York, Inc., Intervener.

No. 106, Docket 29853.

United States Court of Appeals, Second Circuit.

Argued Oct. 8, 1965.
Decided Dec. 29, 1965.

Samuel L. Slutsky, Putnam Valley, N.Y., for petitioner, Town of Putnam Valley.

John C. Tuttle, Peekskill, N.Y., of the brief, for petitioner, Town of Cortlandt.

John R. Kibbe and Raymond Margles, Yorktown Heights, N.Y., on the brief, for petitioner, Town of Yorktown.

Josephine H. Klein, Washington, D.C. (Richard A. Solomon, Gen. Counsel for Federal Power Commission, Howard E. Wahrenbrock, Sol., Melvin Spaeth, Asst. Gen. Counsel, Washington D.C., on the brief), for respondent.

Randall J. LeBoeuf, Jr., New York City (LeBoeuf, Lamb & Lieby, New York City, on the brief), for intervener.

Lloyd K. Garrison, New York City, (Simon H. Rifkind, Albert K. Butzel, Paul, Weiss, Rifkind, Wharton & Garrison, New York City, and Dale E. Doty, Washington, D.C., of counsel), for petitioner, Scenic Hudson Preservation Conference.

Before LUMBARD, Chief Judge and WATERMAN and HAYS, Circuit Judges.

HAYS, Circuit Judge:

In this proceeding the petitioners are the Scenic Hudson Preservation Conference, an unincorporated association consisting of a number of non-profit, conservationist organizations, and the Towns of Cortlandt, Putnam Valley and Yorktown. Petitioners ask us, pursuant to 313(b) of the Federal Power Act, 16 U.S.C. 825l(b), to set aside three orders of the respondent, the Federal Power Commission:1

(a) An order of March 9, 1965 granting a license to the intervener, the Consolidated Edison Company of New York, Inc., to construct a pumped storage hydroelectric project of the west side of the Hudson River at Storm King Mountain in Cornwall, New York;

(b) An order of May 6, 1965 denying petitioners' application for a rehearing of the March 9 order, and for the reopening of the proceeding to permit the introduction of additional evidence;

(c) An order of May 6, 1965 denying joint motions filed by the petitioners to expand the scope of supplemental hearings to include consideration of the practicality and cost of underground transmission lines, and of the feasibility of any type of fish protection device.

A pumped storage plant generates electric energy for use during peak load periods,2 using hydroelectric units driven by water from a headwater pool or reservoir. The contemplated Storm King project would be the largest of its kind in the world. Consolidated Edison has estimated its cost, including transmission facilities, at $162,000,000. The project would consist of three major components, a storage reservoir, a powerhouse, and transmission lines. The storage reservoir,3 located over a thousand feet above the powerhouse, is to be connected to the powerhouse, located on the river front, by a tunnel 40 feet in diameter. The powerhouse, which is both a pumping and generating station, would be 800 feet long and contain eight pump generators.4

Transmission lines would run under the Hudson to the east bank and then underground for 1.6 miles to a switching station which Consolidated Edison would build at Nelsonville in the Town of Philipstown. Thereafter, Overhead transmission lines would be placed on towers 100 to 150 feet high and these would require a path up to 125 feet wide5 through Westchester and Putnam Counties for a distance of some 25 miles until they reached Consolidated Edison's main connectins with New York Ciyt.6

During slack periods Consolidated Edison's conventional steam plants in New York Ciyt would provide electric power for the pumps at Storm King to force water up the mountain, through the tunnel, and into the upper reservoir. In peak periods water would be released to rush down the mountain and power the generators. Three kilowatts of power generated in New York City would be necessary to obtain two kilowatts from the Cornwall installation. When pumping the powerhouse would drawn approximately 1,080,000 cubic feet of water per minute from the Hudson, and when generating would discharge up to 1,620,000 cubic feet of water per minute into the river. The installation would have a capacity of 2,000,000 kilowatts, but would be so constructed as to be capable of enlargement to a total of 3,000,000 kilowatts. The water in the upper reservoir may be regarded as the equivalent of stored electric energy; in effect, Consolidated Edison wishes to create a huge storage battery at Cornwall. See Federal Power Commission, National Power Survey 120-21 (1964).

The Storm King project has aroused grave concern among conservationist groups, adversely affected municipalities and various state and federal legislative units and administrative agencies.7

To be licensed by the Commission a prospective project must meet the statutory test of being 'best adapted to a comprehensive plan for improving or developing a waterway,' Federal Power Act 10(a), 16 U.S.C. 803(a). In framing the issue before it, the Federal Power Commission properly noted:

'We must compare the Cornwall project with any alternatives that are available. If on this record Con Edison has available an alternative source for meeting its power needs which is better adapted to the development of the Hudson River for all beneficial uses, including scenic beauty, this application should be denied.'

If the Commission is properly to discharge its duty in this regard, the record on which it bases its determination must be complete. The petitioners and the public at large have a right to demand this completeness. It is our view, and we find, that the Commission has failed to compile a record which is sufficient to support its decision. The Commission has ignored certain relevant factors and failed to make a thorough study of possible alternatives to the Storm King project. While the courts have no authority to concern themselves with the policies of the Commission, it is their duty to see to it that the Commission's decisions receive that careful consideration which the statute contemplates. See Michigan Consolidated Gas Co. v. Federal Power Comm., 108 U.S.App.D.C. 409, 283 F.2d 204, 226, cert. denied, Panhandle Eastern Pipe Line Co. v. Michigan Consol. Gas Co., 364 U.S. 913, 81 S.Ct. 276, 5 L.Ed.2d 227 (1960). Petitioners' application, pursuant to 313(b), 16 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
354 F.2d 608, 1 Envtl. L. Rep. (Envtl. Law Inst.) 20292, 1 ERC (BNA) 1084, 1965 U.S. App. LEXIS 3514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scenic-hudson-preservation-conference-v-federal-power-commission-ca2-1965.