SC Energy Users Committee v. SCE&G

CourtSupreme Court of South Carolina
DecidedOctober 22, 2014
Docket27456
StatusPublished

This text of SC Energy Users Committee v. SCE&G (SC Energy Users Committee v. SCE&G) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SC Energy Users Committee v. SCE&G, (S.C. 2014).

Opinion

THE STATE OF SOUTH CAROLINA

In The Supreme Court

South Carolina Energy Users Committee, Appellant/Respondent,

v.

South Carolina Electric and Gas, South Carolina Office

of Regulatory Staff and Pamela Greenlaw, Respondents,

and Sierra Club, is Respondent/Appellant.

Appellate Case No. 2013-000529

Appeal From The Public Service Commission

Opinion No. 27456

Heard April 16, 2014 – Filed October 22, 2014

AFFIRMED

Scott Elliott, of Elliott & Elliott, P.A., of Columbia, for Appellant/Respondent.

Robert Guild, of Columbia, for Respondent/Appellant.

Belton Townsend Zeigler, of Pope Zeigler, LLC, and James B. Richardson, Jr., both of Columbia, K. Chad Burgess and Matthew W. Gissendanner, of Cayce, Florence P. Belser, Nanette S. Edwards, Jeffrey M. Nelson, and Shannon Bowyer Hudson, all of Columbia, for Respondents. CHIEF JUSTICE TOAL: The South Carolina Energy Users Committee (the SCEUC) and the Sierra Club (collectively, Appellants) appeal orders of the Public Service Commission (the Commission) approving Respondent South Carolina Electric & Gas's (SCE&G) application for updated capital cost and construction schedules, pursuant to the Base Load Review Act, S.C. Ann. §§ 58-33-210 to -298 (Supp. 2013) (the BLRA).1 In essence, this appeal presents the questions of whether the Commission applied the correct section of the BLRA, and whether the Commission must also consider the prudence of project completion at the update stage. We affirm.

FACTS/PROCEDURAL BACKGROUND

On March 2, 2009, SCE&G obtained an initial base load review order2 authorizing it to complete a project involving the construction of two 1,117 net megawatt nuclear units in connection with the construction of a nuclear power plant at the V.C. Summer Nuclear Station located near Jenkinsville, South Carolina.

On May 15, 2012, SCE&G petitioned the Commission for a base load review order approving updates to the capital cost and construction schedules for the project. SCE&G sought approximately $283 million in capital costs to be recouped from its customers in rates pursuant to the BLRA. The application comprised the following changes to the costs enumerated in the initial base load review order: (1) an Engineering, Procurement, and Construction Contract (EPC) change order resulting from a settlement agreement for schedule changes and additional costs related to the time frame in which the Combined Operating License was received from the Nuclear Regulatory Commission, the redesign and construction of certain components, and certain Unit 2 site conditions ($137.5

1 The South Carolina Office of Regulatory Staff (ORS) is also a respondent, made party pursuant to section 58-4-10 of the South Carolina Code. See S.C. Code Ann. § 58-4-10 (Supp. 2013). 2 A base load review order is "an order issued by the [C]ommission pursuant to Section 58-33-270 establishing that if a plant is constructed in accordance with an approved construction schedule, approved capital costs estimates, and approved projections of in-service expenses, as defined herein, the plant is considered to be used and useful for utility purposes such that its capital costs are prudent utility costs and are properly included in rates." S.C. Code Ann. § 58-33-220(4). million); (2) owner's costs ($131.6 million); (3) transmission costs ($7.9 million); and (4) additional EPC change orders for cyber security ($5.9 million), healthcare costs ($139,573), and wastewater piping ($8,250). With respect to updates to the construction schedules, SCE&G sought to delay the completion date of Unit 2 by eleven months, which would advance the date for completion of the entire project by seven and one-half months.

The Commission received timely notices to intervene by the Sierra Club,3 the SCEUC, an organization consisting of industrial customers of SCE&G, and Pamela Greenlaw, a residential customer.4

A hearing was convened before the Commission to assess the application on October 2–3, 2012. By order dated November 15, 2012, the Commission approved $278.05 million of the $283 million in cost increases to the previously approved capital cost budget and approved the updated construction schedule, finding the cost increases resulted from "the normal evolution and refinement of construction plans and budgets for the Units and not the result of imprudence on the part of SCE&G."

Appellants filed petitions for reconsideration. In their petitions, along with specific errors, Appellants averred that the Commission erred generally in permitting the modifications after SCE&G did not anticipate the cost adjustments when it originally filed for an initial base load review order; that SCE&G was required to present a full evaluation of the prudence of the decision to continue to construct the nuclear units; and that the evidence in the Record was insufficient to meet that burden. By order dated February 14, 2013, the Commission denied Appellants' petitions for rehearing, finding they lacked merit. This appeal of the Commission's base load review order and decision to deny the petitions for reconsideration followed.

ISSUES

3 The Sierra Club is a non-profit organization dedicated to "protect[ing] the wild places of the earth" and to "promot[ing] the responsible use of the earth's ecosystems and resources." The Sierra Club's South Carolina Chapter consists of nine local groups and more than 5,000 members, some of whom are ratepayers of SCE&G and neighbors to the site of the proposed nuclear plant. 4 Pamela Greenlaw is not party to this appeal. I. Whether the Commission erred by applying the wrong section, and therefore the wrong standard, of the BLRA?

II. Whether the Commission erred in holding that a prudency evaluation of the need for the continued construction of the units is not required under the BLRA?

III. Whether the evidence supports the Commission's finding that the additional capital costs were prudent under the BLRA?

STANDARD OF REVIEW

"This Court employs a deferential standard of review when reviewing a decision from the Commission and will affirm the Commission's decision if it is supported by substantial evidence." S.C. Energy Users Comm. v. Pub. Serv. Comm'n of S.C., 388 S.C. 486, 490, 697 S.E.2d 587, 589–90 (2010) (citing Duke Power Co. v. Pub. Serv. Comm'n of S.C., 343 S.C. 554, 558, 541 S.E.2d 250, 252 (2001)). "The Commission is considered the expert designated by the legislature to make policy determinations regarding utility rates." Id. at 490, 697 S.E.2d at 590 (citing Kiawah Prop. Owners Grp. v. Pub. Serv. Comm'n of S.C., 359 S.C. 105, 109, 597 S.E.2d 145, 147 (2004)); see also Hamm v. Pub. Serv. Comm'n of S.C., 289 S.C. 22, 25, 344 S.E.2d 600, 601 (1986) (stating that because the Commission is an "expert" in utility rates, "the role of a court reviewing such decisions is very limited" (quoting Patton v. Pub. Serv. Comm'n of S.C., 280 S.C. 288, 291, 312 S.E.2d 257, 259 (1984))). "The construction of a statute by the agency charged with its administration will be accorded the most respectful consideration and will not be overruled absent compelling reasons." Dunton v. S.C. Bd. of Exam'rs in Optometry, 291 S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kiawah Property Owners Group v. Public Service Commission
597 S.E.2d 145 (Supreme Court of South Carolina, 2004)
Patton v. South Carolina Public Service Commission
312 S.E.2d 257 (Supreme Court of South Carolina, 1984)
Hodges v. Rainey
533 S.E.2d 578 (Supreme Court of South Carolina, 2000)
Sloan v. South Carolina Board of Physical Therapy Examiners
636 S.E.2d 598 (Supreme Court of South Carolina, 2006)
Nucor Steel v. South Carolina Public Service Commission
426 S.E.2d 319 (Supreme Court of South Carolina, 1992)
South Carolina Energy Users Committee v. South Carolina Public Service Commission
697 S.E.2d 587 (Supreme Court of South Carolina, 2010)
Duke Power Co. v. Public Service Commission
541 S.E.2d 250 (Supreme Court of South Carolina, 2001)
Hamm v. South Carolina Public Service Commission
344 S.E.2d 600 (Supreme Court of South Carolina, 1986)
Dunton v. South Carolina Board of Examiners
353 S.E.2d 132 (Supreme Court of South Carolina, 1987)
Friends of the Earth v. Public Service Commission
692 S.E.2d 910 (Supreme Court of South Carolina, 2010)
Beaufort County v. South Carolina State Election Commission
718 S.E.2d 432 (Supreme Court of South Carolina, 2011)
Waters v. South Carolina Land Resources Conservation Commission
467 S.E.2d 913 (Supreme Court of South Carolina, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
SC Energy Users Committee v. SCE&G, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sc-energy-users-committee-v-sceg-sc-2014.