SBH Services & CORE Construction, JV II

CourtArmed Services Board of Contract Appeals
DecidedJanuary 27, 2020
DocketASBCA No. 61714
StatusPublished

This text of SBH Services & CORE Construction, JV II (SBH Services & CORE Construction, JV II) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SBH Services & CORE Construction, JV II, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) SBH Services & CORE Construction, JV II ) ASBCANo. 61714 ) Under Contract No. W912QR-14-C-0001 )

APPEARANCES FOR THE APPELLANT: Ms. Sharon Athas Cote Managing Partner

Derrick Haddox, Esq. Swanson, Martin & Bell, LLP Chicago, IL

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney R. Lauren Homer, Esq. Engineer Trial Attorney U.S. Army Engineer District, Louisville

OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD ON THE GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION

The government moves to dismiss this appeal for lack of subject matter jurisdiction, alleging that appellant failed to properly certify its claim in accordance with the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109. The government also asserts that the underlying claim was brought as a pass-through claim by a second-tier subcontractor that lacks privity with the government. For the reasons set forth below, the government's motion is denied.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On November 27, 2013, the United States Army Corps of Engineers (government) awarded Contract No. W912QR-14-C-0001 to SBH Services & CORE Construction, JV II . (SBH or appellant) for the construction of Barkley Elementary School, Fort Campbell, KY at a base price of $38,670,097.00, with the opportunity for future options to be awarded at a later date (R4, tab 2 at 6).

2. SBH executed a subcontract agreement with MPS Geothermal (MPS) on May 21, 2014, for the furnishing of all labor, materials, equipment, and other necessary construction services required for a complete "turnkey" construction of Barkley Elementary School at Fort Campbell, KY (R4, tab 11 at 3370). 3. Sometime thereafter, MPS entered into a subcontract with Jackson & Sons Drilling & Pump, Inc. (Jackson or second-tier subcontractor) (compl. il 11; answer i-111).

4. By serial letter S-0089, dated December 5, 2016, 1 SBH submitted to the government a request for equitable adjustment (REA) for "Geothermal Different [sic] Site Conditions" in the total amount of $1,899,636.00 and for a 63-day time extension. The total amount sought included amounts for MPS, Byrd Survey, Charles Dewesee Construction, S&:ME and SBH. (R4, tab 446 at 4939-40) Included as part of the REA transmitted with S-0089 was a two-page letter from Jackson, the second-tier subcontractor, addressed to the contracting officer (CO) and purporting to be a claim for its portion of the REA ($1,008,547.49). That letter was dated November 4, 2016 and was submitted and certified by James D. Jackson, President of second-tier subcontractor Jackson. While that certification included all of the assertions required for a claim certification under the CDA, 41 U.S.C. § 7103 (b), including that he was "authorized to certify the claim on behalf of the Contractor," he also made clear that he signed in his capacity as President of Jackson & Sons Drilling & Pump, Inc. (Id. at 4942-43)

5. By letter dated December 15, 2016, the CO requested clarification on whether SBH's December 5, 2016 letter was an REA, or whether appellant was seeking "a Final Contracting Officer's Decision in accordance with 41 U.S.C. § 7103" (R4, tab 447).

6. By letter dated December 22, 2016 to the Louisville, KY District Corps office, and not to Fort Campbell as other correspondence was addressed, SBH seemed to affirm that the December 5, 2016 package submission "was meant to be a REA" (R4, tab 448). Later, a letter dated April 4, 2017 advised that the December 5, 2016 correspondence was intended for another REA, not the one for Geothermal differing site conditions (R4, tab 450). Because it was not addressed to Fort Campbell, but to another Corps office, we find that the December 5, 2016 letter was, in fact, meant for a separate REA.

7. By serial letter S-0095, dated March 10, 2017, SBH stated:

This letter is sent in reference to SBH I CORE letter S-0095[ 2] and documentation submitted with that letter, which USACE acknowledged they were in receipt on January 4th, 2017. We want to bring to your attention that all the documentation

1 Serial letter S-0089 is undated; however, the government asserts it received a package containing S-0089 that was dated December 5, 2016 (R4, tab 447). Appellant does not contest this date. 2 Appellant twice incorrectly referenced S-0095. The correct letter of reference is S-0089, v which included the documentation SBH asserts was submitted as a claim. Appellant corrects this error in S-0098. (R4, tab 450)

2 turned in with S-0095 was submitted as a Claim, and not as an REA.

(R4, tab 449)

8. By serial letter S-0098, dated April 4, 2017, and headed: "Subject Matter: Claim for Geothermal Different [sic] Site Conditions", SBH stated:

This letter is sent to provide clarification about Different [sic] Site Conditions for Geothermal which was submitted as a Claim under SBH \ CORE letter S-0089, and USACE acknowledged that they were in receipt of the letter and package on January 4th, 2017. The Claim was put together by the attorney representing Jackson Geothermal (2nd tier subcontractor) to SBH I CORE. The claimant has certified the Claim and it was included in the packet submitted under S-0089. All the documentation supporting this Geothermal Claim were submitted under SBH I CORE letters S-0089 and S-0095.

(R4, tab 450 at 5173) Serial letter S-0098 was on SBH letterhead, included a CDA claim certification making all of the required assertions, and was certified by Saravanan Sathya, the SBH Project Manager (id) . .We find as fact that the claim was perfected upon submission of the Project Manager's CDA certification on April 4, 2017.

9. On April 24, 2018, the CO issued a final decision (COFD). The CO notified SBH that for the purposes of this decision, he would treat serial letters S-0089 and S-0095 as a "claim." (R4, tab 1 at 1)

10. The COFD stated that SBH had shown some entitlement warranting some sort of compensation for differing site conditions, but no additional time. However, the CO ultimately concluded that, although some merit to the claim was found, the government was "unable to fix an amount for a contract modification and must leave that for further negotiation and/or adjudication." (Id. at 5)

11. By letter dated July 20, 2018, appellant timely filed a notice of appeal to the Board, which the Board docketed as ASBCANo. 61714.

DECISION

The government contends that the Board lacks jurisdiction over this appeal because appellant failed to properly certify its claim in accordance with the CDA (gov't mot. at 1). The government's motion asserts that serial letter S-0098 fell short of the necessary

3. requirements to convert appellant's REA into a claim in two different aspects: . '

1) appellant named Jackson as the claimant; and 2) appellant discussed two different matters in the claim but failed to clarify which issue was being certified ( id. at 10-11). Additionally, the government contends that SBH's claim is a "pass-through claim" from a subcontractor that lacks privity with the government (id. at 1). Firstly, Jackson is not the only subcontractor with a claim; moreover, the prime contractor, SBH, also has a part of the claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
SBH Services & CORE Construction, JV II, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sbh-services-core-construction-jv-ii-asbca-2020.