Save the St. Johns River v. WATER MGT. DIST.

623 So. 2d 1193, 1993 Fla. App. LEXIS 8650, 1993 WL 317075
CourtDistrict Court of Appeal of Florida
DecidedAugust 23, 1993
Docket92-305
StatusPublished
Cited by2 cases

This text of 623 So. 2d 1193 (Save the St. Johns River v. WATER MGT. DIST.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Save the St. Johns River v. WATER MGT. DIST., 623 So. 2d 1193, 1993 Fla. App. LEXIS 8650, 1993 WL 317075 (Fla. Ct. App. 1993).

Opinion

623 So.2d 1193 (1993)

SAVE THE ST. JOHNS RIVER, Appellant,
v.
ST. JOHNS RIVER WATER MANAGEMENT DISTRICT and David A. Smith, Appellees.

No. 92-305.

District Court of Appeal of Florida, First District.

August 23, 1993.

*1194 Thomas G. Tomasello, Oertel, Hoffman, Fernandez & Cole, P.A., Tallahassee, for appellant.

Wayne E. Flowers, Gen. Counsel, St. Johns River Water Management Dist., Palatka, for appellee St. Johns River Water Management Dist.

Bram D.E. Canter and Darren A. Schwartz, Haben, Culpepper, Dunbar & French, P.A., Tallahassee, for appellee David A. Smith.

*1195 ZEHMER, Chief Judge.

We review by appeal, pursuant to section 120.68, Florida Statutes (1991), a final order of the Florida Land and Water Adjudicatory Commission. The Commission, consisting of the Governor and Cabinet exercising their powers of appellate review pursuant to section 373.114, Florida Statutes (1991), affirmed the final order of the St. Johns River Water Management District granting David A. Smith's application for a management and storage of surface waters (MSSW) permit in connection with a proposed residential and golf development situated adjacent to Lake Poinsett. Appellant, SAVE The St. Johns River Association, Inc.,[1] challenged the District's notice of intent to issue the MSSW permit in a timely filed petition. The matter was referred to the Division of Administrative Hearings, a formal evidentiary hearing was held, and the hearing officer recommended approval of the permit application on specified conditions (these conditions are not disputed on appeal). The District's final order adopted the hearing officer's recommended order in its entirety, granted the permit on the conditions stated therein, and dismissed SAVE's petition. The Commission affirmed the District's decision on a closely divided vote, concluding that on the record made before the hearing officer and the District there were no inconsistencies between the District's final order and the purposes, objectives, and provisions of chapter 373, Florida Statutes. The Commission rejected each of the contentions made by SAVE in a thorough and well reasoned order, which we now affirm.

I.

The District is empowered by law to review applications and to issue MSSW permits for projects within its boundaries.[2] Smith applied for an MSSW permit to construct a stormwater management system to serve a proposed residential and golf development to be known as Sabal Hammocks. The proposed project is to be located on land that has been used since the 1950's for agricultural purposes that included cattle grazing and cultivation of crops such as rye and oats. The proposed site is adjacent to Lake Poinsett and related marsh land, and lies within the St. Johns River Water Management District. The receiving waters for stormwater discharge from the proposed development will be Lake Poinsett and its adjacent marshes.

Currently, a dike system exists along the southern boundary of the proposed development property and separates the internal grazing lands from the lower marsh and flood areas external to the dike. The dike system has been in place since it was originally constructed in 1973. A series of ditches cross the parcel and drain the areas within the dike system. Pursuant to a consent order previously approved by the District, two agricultural discharge pumps currently are in use at the site and discharge waters into the marshes adjacent to Lake Poinsett. When the dike was constructed in 1973, employees of the Department of Natural Resources and the Florida Marine Patrol inspected the construction for the specific purpose of determining whether it was being constructed in accordance with the requirements of existing law. They informed Smith that the construction did not require a permit from the state agency. At that time, the District did not have permissive permitting authority over *1196 the construction of this dike system. Although detailed specifications for the original construction are not shown by the record, it was established that the majority of the dike structure has remained in place over the ensuing period and was sufficient to indicate the original dimensions of the dike system.

In 1978, the Department of Environmental Regulation (DER) issued Smith a permit to construct a new dike landward of the 1973 dike and authorized 21 breaches to be made in the old dike. Only 12 breaches were actually cut in the old dike, and none of these were brought down to ground level (the record indicates they remained some 3 to 4 feet higher than the ground on which the dike was constructed). Construction of the new dike was later abandoned and never completed. The 1973 dike remained intact throughout its entire length and continued to impede water movement from the marsh into the agricultural areas. In 1986, Smith informed the District, DER, and the U.S. Army Corps of Engineers that he had abandoned construction of the new dike and planned to restore the old dike to its original condition and dimensions by filling in the 12 breaches. All three agencies allowed this work to be completed without objection and did not require Smith to obtain a permit for this restorative work. Although no written engineering plans existed for the 1973 dike system, it was established that the dike had been constructed to an elevation of 22 feet and a width of 10-12 feet at the top. As the construction of the 12 breaches left the majority of the original dike in place, written design specifications were not required for the District to determine that the restorative work did not extend beyond the original construction specifications of the dike system.

The stormwater management and treatment system authorized under the MSSW permit will treat stormwater from the site prior to any discharge off-site in a manner that sufficiently meets or exceeds all state water quality standards. Wetland impacts associated with the proposed project are minor and will be offset by the plan for creation and enhancement of wetlands on site. The two existing agricultural pumps will be replaced by a single pump station having a total pump capacity no greater than the two existing pumps. After development, the peak rate of discharge from the site will not exceed the pre-development rate, and the volume of discharge from the site will be less after development than before development.

The District accepted the recommended findings of fact and conclusions of law in the hearing officer's recommended order and directed that the permit be issued on the recommended conditions. SAVE then appealed to the Commission, urging that the matter be remanded to the District or the hearing officer for further findings on the legality of the original dike construction and the restorative work. SAVE argued that the record failed to contain competent, substantial evidence to support a finding that the land involved should be excluded from the St. Johns River floodplain, as the District had done by recognizing the presence of the dike system as the pre-development condition of the property. DER gave the Commission its recommendation on this matter pursuant to section 373.114, Florida Statutes (1991). It urged that the matter be remanded for further findings because: 1) whether the original dike was legally constructed had not been properly adjudicated in this proceeding, and this prevented DER from accurately determining whether the District was correct in its assertion that the pre-development condition was that of a diked parcel; and 2) the District has been actively acquiring floodplain in the upper St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ST. JOHNS RIVER WATER MANAG. DIST. v. Modern, Inc.
784 So. 2d 464 (District Court of Appeal of Florida, 2001)
Department of Revenue v. Bank of America
752 So. 2d 637 (District Court of Appeal of Florida, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
623 So. 2d 1193, 1993 Fla. App. LEXIS 8650, 1993 WL 317075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/save-the-st-johns-river-v-water-mgt-dist-fladistctapp-1993.