Save Our Wetlands, Inc. v. Witherspoon

638 F. Supp. 1158, 24 ERC 1961, 16 Envtl. L. Rep. (Envtl. Law Inst.) 20972, 24 ERC (BNA) 1961, 1986 U.S. Dist. LEXIS 22966
CourtDistrict Court, E.D. Louisiana
DecidedJuly 10, 1986
DocketCiv. A. 86-2554
StatusPublished

This text of 638 F. Supp. 1158 (Save Our Wetlands, Inc. v. Witherspoon) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Save Our Wetlands, Inc. v. Witherspoon, 638 F. Supp. 1158, 24 ERC 1961, 16 Envtl. L. Rep. (Envtl. Law Inst.) 20972, 24 ERC (BNA) 1961, 1986 U.S. Dist. LEXIS 22966 (E.D. La. 1986).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

PATRICK E. CARR, District Judge.

Plaintiff, Save Our Wetlands, Inc. (SOWL), a non-profit group of conservationists, hunting and wildlife enthusiasts, commercial fisherman and trappers, and others, brought suit against Eugene S. Witherspoon in his capacity as District Engineer of the New Orleans District Corps of Engineers, Department of the Army (Corps) and ARTRA Resources Corporation seeking declaratory and injunctive relief in regard to the issuance of three (3) dredging permits sought by ARTRA. The matter came on for hearing on the motion for preliminary injunction on July 1, 1986. After two and one half days of testimony and evidence, by express agreement, the parties submitted the case on the merits. Now, upon consideration of the pleadings, the testimony of the witnesses, the documentary evidence, post-trial memoranda and the law applicable to this case, the Court renders its findings of fact and conclusions of law in accordance with Rule 52 of the Federal Rules of Civil Procedure.

The Court has jurisdiction pursuant to 28 U.S.C. §§ 1331, 1346 and under the Clean Water Act, 33 U.S.C. § 1251, et seq.

This controversy arises out of the issuance of dredging permits by the Corps to ARTRA Resources Corporation, the lessee of oil and gas mineral exploration rights from Lutcher Moore Cypress Lumber Company. The Lutcher Moore tract comprises 64,500 acres of cypress swamp land located in the Maurepas/Ponchartrain/Borgne Basin, north of Mt. Airy and Reserve, Louisiana. Three permits are at issue, affecting a total of 54 wetland acres.

PERMIT NO. 1: LMNOD-SE (RESERVE RELIEF CANAL) 7

ARTRA applied for a permit to perform work in the vicinity of the Reserve Relief Canal located approximately 7.9 miles northwest of Laplace, Louisiana in St. John the Baptist Parish, affecting 21 acres of wetlands. ARTRA proposed to dredge and maintain one 3849 foot by 60 foot access canal and a 368 foot by 160 foot slip area, for the purpose of gaining access to oil and gas drilling exploration and production operations. The proposal required the excavation of approximately 85,884 cubic yards of forested wetland and marsh material (spoil), which would be placed as a continuous levee around the slip. Approximately 1,333 cubic yards of waterbottom at the mouth of the Reserve Relief Canal would also be excavated and placed in open water with the resultant decrease in water depth of no more than 0.5 foot.

The proposal also called for the placement of a pollution boom across the mouth of the slip area during drilling and completion operations. If the well was producible, the pollution boom would encircle the wellhead and production equipment. If the well was not producible, the mouth of the access canal would be plugged and the spoil bank gapped. Mitigation also included revegetation of the spoil banks at the project site.

Of primary concern was the fact that there were two active and one abandoned bald eagle nests in the vicinity of this proposed activity. In order to protect the public interests regarding this endangered species, the United States Fish and Wildlife Service (USFWS) recommended that three restrictions be incorporated into the permit. ARTRA voluntarily agreed and requested the Corps to so incorporate these restrictions. The Corps did so as follows:

1. Dredging and drilling activities shall be limited to the period May 15 through October 1 of any year.
*1160 2. No work requiring the utilization of heavy equipment shall be conducted during October 1 through May 15 of any year (the only exception will be emergency work coordinated with the U.S. Fish and Wildlife Service).
3. All drilling equipment shall be removed from the area by October 1 during the year of drilling.

See Exhibit P-1, pp 60, 33 and 95.

A fourth restriction was not incorporated by the Corps into the permit, but rather supported by the Corps and voluntarily agreed to by ARTRA. This restriction involved performance of off-site mitigation measures to “compensate for unavoidable habitat losses.” See Exhibit P-1, pp 60 and 95.

Based upon a short form Environmental Assessment (EA), a finding of no significant impact, and a finding that no Environmental Impact Study (EIS) was required, the permit for the Reserve Relief Canal issued on June 6, 1986. Suit was filed on June 18, 1986. The work under the permit was completed on June 25, 1986, prior to the commencement of trial. At the conclusion of trial on the merits, defendant ARTRA notified the Court that it would voluntarily suspend all operations in the area pending the final decision on the merits. PERMIT NO. 2: LMNOD-SE (ST. JAMES PARISH WETLANDS) 39

This permit application involved work located approximately 6 miles north of Mt. Airy, Louisiana in St. James Parish, affecting 14 acres. ARTRA proposed the cleaning out of approximately 2,000 feet of the existing Bourgeois Canal with the 9,800 cubic yards of spoil to be placed onto the existing spoil bank. Further, ARTRA proposed to construct a 2,300 foot canal and slip area by dredging approximately 53,793 cubic yards of swamp material for the purpose of accessing a proposed oil and gas well site. The proposal called for the spoil to be placed as a continuous levee around the slip and a levee along the canal with 50 foot breaks or gaps every 500 feet. It would also be gapped at existing streams, sloughs and bayous.

A pollution boom would be required to be placed across the mouth of the slip during drilling and production operations. The mouth of the canal would be plugged in the case of a dry well or upon abandonment. Again, on-site mitigation included revegetation of the spoil banks. Off-site mitigation was again agreed to by ARTRA.

At the time suit was filed, the Court was informed that permit issuance was imminent. On the final day of the hearing, the permit was issued by the Corps and received by ARTRA. The same day, the Corps suspended the permit indefinitely pending the final decision on the merits. PERMIT NO. 3: LMNOD-SE (MISSISSIPPI BAYOU) 1

As to this third project ARTRA proposed to dredge a 60 foot by 800 foot channel in Lake Maurepas to access Dutch Bayou. Further, ARTRA proposed sweeping the existing Dutch and Mississippi Bayous as necessary to access a proposed canal and slip. ARTRA sought to dredge and maintain a 3,475 foot by 60 foot access canal and a 350 foot by 160 foot slip area. The site of the proposed location is approximately 7.3 miles northwest of Reserve, Louisiana affecting 20 acres of wetlands.

The new construction called for the excavation of 81,052 cubic yards of swamp material for the proposed canal to be placed as a continuous levee around the canal and slip areas. A pollution boom would be placed across the mouth of the slip during drilling and production operations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
638 F. Supp. 1158, 24 ERC 1961, 16 Envtl. L. Rep. (Envtl. Law Inst.) 20972, 24 ERC (BNA) 1961, 1986 U.S. Dist. LEXIS 22966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/save-our-wetlands-inc-v-witherspoon-laed-1986.