Save Long Beach Island, Inc. v. U.S. Department of Commerce

CourtDistrict Court, District of Columbia
DecidedOctober 24, 2025
DocketCivil Action No. 2025-2214
StatusPublished

This text of Save Long Beach Island, Inc. v. U.S. Department of Commerce (Save Long Beach Island, Inc. v. U.S. Department of Commerce) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Save Long Beach Island, Inc. v. U.S. Department of Commerce, (D.D.C. 2025).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

SAVE LONG BEACH ISLAND, INC., et al.,

Plaintiffs,

v. Civil Action No. 1:25-cv-02214 (CJN)

UNITED STATES DEPARTMENT OF COMMERCE, et al.,

Defendants,

&

EMPIRE OFFSHORE WIND LLC, et al.,

Defendant-Intervenors.

MEMORANDUM OPINION

Opponents of an offshore wind farm already under construction off the coast of New York

and New Jersey move to enjoin further work on the ground that governmental authorizations for

the project violate the Marine Mammal Protection Act. See ECF 17; 16 U.S.C. § 1371(a)(5)(A).

For the reasons that follow, the Court denies their motion.

I. BACKGROUND

A. Factual Background

In early 2017, the Bureau of Ocean Energy Management (BOEM) issued a lease permitting

the construction of an offshore wind farm near Brooklyn, New York. ECF 19-1 at 3. Equinor

Wind US LLC initially won the rights to the lease and then later assigned those rights to its

subsidiaries Empire Offshore Wind LLC and Empire Leaseholder LLC (collectively, Empire

Wind). Id. The project covers nearly 80,000 acres and is projected to generate 2,076 megawatts

1 of electricity. ECF 21 at 5. Construction is proceeding in two phases: Empire Wind 1 and Empire

Wind 2. ECF 19-1 at 3.

Leading up to the start of construction, Empire Wind applied for and received several

permits at the federal and state level. In January 2020, Empire Wind submitted a Construction and

Operations Plan to BOEM. Id. at 5. Its proposal included hundreds of mitigation and monitoring

measures intended to minimize disruptions to the environment and animals caused by the project.

Id. at 6. In February 2024, BOEM approved the Plan after several rounds of modifications and an

environmental review. Id. at 5–6. In December 2024, BOEM reissued its approval of the Plan as

two separate approvals: one for Empire Wind 1 and one for Empire Wind 2. Id. at 6.

In December 2021, Empire Wind requested a five-year Letter of Authorization from the

National Marine Fisheries Service (NMFS) to “take” various marine mammals incidental to

construction of the project in compliance with the Marine Mammal Protection Act. Id. at 4. That

Act permits NMFS to authorize the taking of “small numbers of marine mammals of a species or

population stock if the Secretary, after notice . . . and opportunity for public comment . . . finds

that the total of such taking during each five-year (or less) period concerned will have a negligible

impact on such species or stock and will not have an unmitigable adverse impact on the availability

of such species or stock for taking for subsistence uses.” 16 U.S.C. § 1371(a)(5)(A)(i). “The term

‘take’ means to harass, hunt, capture, or kill, or attempt to harass, hunt, capture, or kill any marine

mammal,” id. at § 1362(13), and the Marine Mammal Protection Act distinguishes between two

levels of harassment takings. Level A harassment encompasses “any act of pursuit, torment, or

annoyance which . . . has the potential to injure a marine mammal or marine mammal stock in the

wild.” Id. § 1362(18)(A)(i), (C). Level B harassment covers “any act of pursuit, torment, or

2 annoyance which . . . has the potential to disturb a marine mammal or marine mammal stock in

the wild by causing disruption of behavioral patterns.” Id. § 1362(18)(A)(ii), (D).

Following a round of notice and comment and an environmental review, in February 2024,

NMFS issued a Letter of Authorization for the project that permits the incidental taking of marine

mammals from February 2024 through February 2029. ECF 19-1 at 5. Of particular relevance

here, the Letter authorizes annual Level B harassment of up to 31.9 percent of Northern Migratory

Coastal Bottlenose Dolphins. See Taking Marine Mammals Incidental to the Empire Wind Project,

Offshore New York, 89 Fed. Reg. 11342, 11416 (Feb. 14, 2024). Among other mitigation

measures, the Letter of Authorization imposes a seasonal moratorium on impact pile driving,

requires the use of species observers and sound attenuation devices during pile driving, and calls

for shutdowns of pile driving if marine mammals were observed nearby. ECF 19-1 at 4–5. In

January 2025, NMFS reissued the Letter with minor changes, including updating the relevant

subsidiary that had permission to build the project. Id. at 5.

Active construction of Empire Wind 1 has been underway for more than a year. ECF 19-

2 at 3. Construction of the onshore portion began in April 2024. Id. In-water installation of export

cables to transfer electricity commenced in July 2024. Id. at 4. Building of monopile foundations

for the wind turbines started in June 2025 and is scheduled to finish by the end of October 2025.

Id. All construction for Empire Wind 1 is set to conclude by the end of 2026. Id. at 6.

On April 16, 2025, BOEM issued a suspension order that paused construction as part of

the Department of Interior’s general review of offshore wind projects, and on May 19, 2025,

3 BOEM lifted the suspension order. ECF 17-1 at 3. Empire Wind resumed construction the next

day. Id. at 1.

B. Procedural History

On April 4, 2023, Save Long Beach Island and Dr. Robert Stern filed a lawsuit in the

District of New Jersey challenging authorizations issued by NMFS that permitted the incidental

takings of marine mammals for several offshore wind projects. Complaint at 1–4, Save Long

Beach Island v. U.S. Dep’t of Com., No. 3:23-cv-01886 (D.N.J. Apr. 4, 2023). On February 29,

2024, the district court dismissed the suit without prejudice for mootness and lack of standing. See

Save Long Beach Island v. U.S. Dep’t of Com., 721 F. Supp. 3d 317, 335, 340 (D.N.J. 2024). Save

Long Beach Island and Stern then filed an amended complaint on March 29, 2024, that explicitly

challenged the Letter of Authorization for both Empire Wind 1 and 2. Amended Complaint at 15,

Save Long Beach Island v. U.S. Dep’t of Com., No. 3:23-cv-01886 (D.N.J. Mar. 29, 2024). But,

on June 11, 2025, the district court granted summary judgment to Empire Wind and the

government regarding the Letter of Authorization. See Save Long Beach Island v. U.S. Dep’t of

Com., No. 3:23-cv-01886, 2025 WL 1829543, at *31 (D.N.J. July 2, 2025).

On July 11, 2025, Save Long Beach Island and Stern—along with new Plaintiffs Save the

East Coast, Inc., Protect Our Coast – LINY, Captain Alan Shinn, and Borough of Seaside Park—

filed this suit against various government defendants, alleging that both the Letter of Authorization

and the Construction and Operations Plan for Empire Wind 1 and 2 violate the Marine Mammal

Protection Act, as well as the National Environmental Policy Act and the Outer Continental Shelf

4 Lands Act. ECF 1 at 2–3. Empire Wind intervened as a defendant. See Min. Order of Aug. 8,

2025.

On August 21, 2025, Plaintiffs moved for the Court to stay the effect of the Letter of

Authorization and Construction and Operations Plan or, in the alternative, to enter a preliminary

injunction to halt all Empire Wind 1 construction. ECF 17. In their motion, they raise only their

claim under the Marine Mammal Protection Act, arguing that the government’s approval of work

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amoco Production Co. v. Village of Gambell
480 U.S. 531 (Supreme Court, 1987)
Cobell, Elouise v. Norton, Gale
391 F.3d 251 (D.C. Circuit, 2004)
Chaplaincy of Full Gospel Churches v. England
454 F.3d 290 (D.C. Circuit, 2006)
Mylan Pharmaceuticals, Inc. v. Shalala
81 F. Supp. 2d 30 (District of Columbia, 2000)
Newdow v. Bush
355 F. Supp. 2d 265 (District of Columbia, 2005)
Natural Resources Defense Council, Inc. v. Evans
232 F. Supp. 2d 1003 (N.D. California, 2002)
Friends of Animals v. United States Bureau of Land Management
232 F. Supp. 3d 53 (District of Columbia, 2017)
AARP v. United States Equal Employment Opportunity Commission
226 F. Supp. 3d 7 (District of Columbia, 2016)
Cal. Ass'n of Private Postsecondary Sch. v. DeVos
344 F. Supp. 3d 158 (D.C. Circuit, 2018)
Chazz Clevinger v. Advocacy Holdings, Inc.
134 F.4th 1230 (D.C. Circuit, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
Save Long Beach Island, Inc. v. U.S. Department of Commerce, Counsel Stack Legal Research, https://law.counselstack.com/opinion/save-long-beach-island-inc-v-us-department-of-commerce-dcd-2025.