Saturn Constr. v. U.S. Concrete Sys., No. Cv91 070 22 38 (Jan. 6, 1992)

1992 Conn. Super. Ct. 6
CourtConnecticut Superior Court
DecidedJanuary 6, 1992
DocketNo. CV91 070 22 38
StatusUnpublished

This text of 1992 Conn. Super. Ct. 6 (Saturn Constr. v. U.S. Concrete Sys., No. Cv91 070 22 38 (Jan. 6, 1992)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saturn Constr. v. U.S. Concrete Sys., No. Cv91 070 22 38 (Jan. 6, 1992), 1992 Conn. Super. Ct. 6 (Colo. Ct. App. 1992).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION ON APPLICATION FOR TEMPORARY INJUNCTION This case is before the court on an application for a temporary injunction. The applicant, Saturn Construction Company, Inc. is seeking to enjoin a pending demand for arbitration filed by the defendant, U.S. Concrete Systems Corp. on the ground that there is no written agreement to arbitrate. A hearing was held on October 9, 1991 before the court.

The relevant facts are not in dispute. The Saturn Construction Company ("Saturn"), a general contractor, entered into a contract with the State of Connecticut, acting through CT Page 7 the Department of Public Works, for the construction of the concrete foundation and building "shell" portion of a project known as the Western Connecticut Correctional facility. On August 1, 1990, Saturn, acting through its vice president, William Burns, engaged U.S. Connecticut Systems Corp. ("U.S. Concrete") as a subcontractor by transmitting to U.S. Concrete a purchase order for the supply of precast concrete panels. The purchase order contains twenty-six numbered contract term, a "Hold harmless clause," and a schedule of insurance requirements. Paragraph 26(B) of this document contains the following term, the interpretation or which is at issue:

This firm is responsible to Saturn Construction Co. in the same manner and requirements as Saturn is responsible to the Owner and Architect.

Also at issue is paragraph 11 of the Notice to Bidders sent by the state and executed by Saturn. This clause states that any dispute arising out of the contract "shall be submitted to arbitration under the rules of the American Arbitration Association."

On August 28, 1990, U.S. Concrete, acting through its president, Nancy N. Sarda, executed and returned the purchase order to Saturn. The returned purchase order contains some minor modifications of the terms of the original purchase order, a five-page letter "summarizing" the agreement and adding additional terms, and a provision stating that. "[a]ny conflict whatsoever shall be governed and/or superseded by the provisions of this letter." The instant dispute does not concern any conflict between the terms of the two document.

On September 10, 1990, Saturn, again acting through Burns, responded to the returned purchase order by stating that "I have no problem with your minor quotation corrections." but objecting that "the final note [containing the provision that conflicts shall be governed by the purchase order returned by U.S. Concrete and its accompanying letter] is totally unacceptable and will not be acknowledged by this Company as a part of this Purchase Order. By letter dated September 17, 1990, Sarda responded by stating that the payment terms were non-negotiable and that U.S. Concrete would not continue work if its payment terms were not accepted.

Despite the conflicting memoranda, the parties commenced performance. During the course of the project, disputes arose over the quality of the panels delivered by U.S. Concrete and the terms of payment. By letter dated October 30, 1990, Luca Cappelli, Jr., Chairman of the Board of Saturn, terminated the CT Page 8 purchase order, ordered that no further work be done, and stopped a previously tendered payment check.

On January 28, 1991, U.S. Concrete initiated abritration proceedings before the American Arbitration Association ("AAA") in Hartford, Connecticut. From the record, it appears that the parties participated in the proceedings only to the point of selecting an arbitrator. Thereafter, on April 8, 1991, Saturn notified the AAA and counsel for U.S. Concrete by letter that it would not continue to participate in the arbitration proceedings, stating that it had never agreed to arbitrate disputes with U.S. Concrete.

Subsequently, on July 13, 1991, Saturn filed an Application for Temporary injunction and Order to Show Cause with the Superior Court for the Judicial District of Hartford/New Britain at Hartford.

A. Parties' Arguments

The plaintiff argues that it is entitled to a temporary injunction enjoining the defendant from proceeding with the above-described claim for arbitration before the AAA because; 1) arbitration can be compelled only by contract, and there exists no valid written agreement; 2) if there exists a valid written agreement, this agreement does not include a valid arbitration clause; and 3) the plaintiff by its limited appearance in the arbitration proceedings, did not waive its right to contest arbitrability. The defendant challenges each of these assertions, arguing that; 1) a valid and enforceable contract exists; 2) the terms of the contract include an agreement to arbitrate disputes; and 3) that, in any event, the plaintiff has waived its right to contest arbitrability.

B. Legal Analysis

1. The Application for Temporary Injunction.

The Superior Court has jurisdiction to hear claims for injunctive relief, see General Statutes 52-471, the issuance of which always rests in the sound discretion of the trial court. Pet v. Department of Health Services, 207 Conn. 346,370, 542 A.2d 672 (1988). A party seeking injunctive relief has the burden of alleging and proving irreparable harm and the lack of an adequate remedy at law. Id., 370. In addition, a party seeking a temporary injunction must "show a reasonable degree of probability of success before a temporary injunction. . . may be granted." Griffin Hospital v. Commission on Hospitals and Health Care, 196 Conn. 451, 457, 493 A.2d 229 (1985). CT Page 9

2. The Likelihood of Success on the Merits.

It is well, settled that, under Connecticut law, only written agreements to arbitrate are valid. Bennett v. Header,208 Conn. 352, 359, 545 A.2d 553 (1988). The plaintiff argues that "the contract negotiations and the multiple exchanges of offers and counteroffers show that Saturn and U.S. Concrete never had a `meeting of the minds' sufficient to formulate a contract." Plaintiff's Memorandum at 6, citing Bridgeport Pipe Engineering Co. v. Dellatteo Construction Co., 159 Conn. 242,268 A.2d 391 (1970). The defendant argues that the parties have entered into an enforceable agreement under 2-207 of the Uniform Commercial Code. General Statutes 42a-2-207.

a) The Existence of a Written Agreement Article 2 of the U.C.C. applies to "transactions in goods."

General Statutes 42-2-102. The instant case involves the provision of raw materials by the defendant for incorporation by the plaintiff into its building project. Because this transaction is one in goods, this case is governed by the provisions of Article 2 of the U.C.C. General Statutes 42a-2-191 et seq., where applicable.

Section 2-204 of the U.C.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E & F CONSTRUCTION CO. v. Rissil Construction Associates, Inc.
435 A.2d 343 (Supreme Court of Connecticut, 1980)
Bridgeport Pipe Engineering Co. v. DeMatteo Construction Co.
268 A.2d 391 (Supreme Court of Connecticut, 1970)
Sturman v. Socha
463 A.2d 527 (Supreme Court of Connecticut, 1983)
Griswold v. Union Labor Life Insurance
442 A.2d 920 (Supreme Court of Connecticut, 1982)
Griffin Hospital v. Commission on Hospitals & Health Care
493 A.2d 229 (Supreme Court of Connecticut, 1985)
Pet v. Department of Health Services
542 A.2d 672 (Supreme Court of Connecticut, 1988)
Bennett v. Meader
545 A.2d 553 (Supreme Court of Connecticut, 1988)
Ryiz v. Federal Insurance Co.
497 A.2d 1001 (Connecticut Appellate Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
1992 Conn. Super. Ct. 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saturn-constr-v-us-concrete-sys-no-cv91-070-22-38-jan-6-1992-connsuperct-1992.