Sargent v. Johnson

601 F.2d 964, 1979 U.S. App. LEXIS 13212
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 13, 1979
DocketNos. 79-1078, 79-1121
StatusPublished
Cited by3 cases

This text of 601 F.2d 964 (Sargent v. Johnson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sargent v. Johnson, 601 F.2d 964, 1979 U.S. App. LEXIS 13212 (8th Cir. 1979).

Opinion

HEANEY, Circuit Judge.

. This matter is before us for the third time.1 The sole issue raised on this appeal is whether, under a contractual indemnity clause, a negligent indemnitee can recover attorney’s fees from his indemnitor. The District Court denied recovery. We affirm.

Paul F. Sargent was employed on a construction project in Minneapolis, Minnesota, on July 14, 1969. On that date, he fell down an elevator shaft and was severely injured. He subsequently brought an action in the District Court alleging negligence on the part of Axel H. Ohman, Inc. (Ohman), a subcontractor on the project, and Roger T. Johnson, architect on the project. These defendants joined Preston Haglin Company (Haglin), the general contractor, as a third-party defendant.2 At trial, the court directed a verdict against Johnson, Ohman and Haglin and referred the remaining issues to the jury. It returned a special verdict of $1.6 million in favor of Sargent and apportioned fault as follows:

Ohman — 55 percent;
Johnson — 15 percent;
Haglin — 30 percent.

After judgment was entered according to this special verdict, all of the parties filed post-trial motions. Before the District Court ruled on these motions, Sargent, Oh-man and Haglin entered into a settlement agreement under which Ohman and Haglin agreed to pay the full amount of the judgment, with Ohman paying 55 percent and Haglin, 45 percent. Johnson, who was not á party to the agreement, was relieved of any liability to Sargent. On November 14, 1974, the District Court modified its earlier judgment to reflect this settlement agreement. Thereafter, Johnson renewed that part of his post-trial motion which sought an award of his attorney’s fees from Haglin and Ohman.3

[966]*966Johnson rests his claim for indemnification from Haglin on the indemnity provisions of the contract between the Housing and Redevelopment Authority (Johnson’s employer and the owner of the building site) and Haglin.4 Section 21.1 of the supplemental conditions to that contract reads as follows:

The Contractors shall defend, indemnify and hold harmless the Local Authority, its Architects, Engineers and all its officers, commissioners, employees and agents from any and all claims, suits, lawsuits, damages or expenses on account of bodily injury, sickness, disease, death and property damage as a result of or alleged to be the result of the Contractors’ operation in connection with this Contract.

By virtue of the pledge to “defend * * * [the Local Authority’s] Architects * * * from any and all claims, suits, lawsuits, damages and expenses * * * ”, Johnson contends that Haglin (and through him, Oh-man) is liable for the attorney’s fees Johnson incurred in defense of Sargent’s negligence action. The validity of this contention turns on the interpretation of the contract and, as jurisdiction in this case rests on diversity of citizenship, Minnesota law governs. After the submission of briefs and oral argument on the issue, the District Court, without discussion, applied Minnesota law to deny Johnson’s motion. It is from this denial that Johnson appeals.

After the District Court’s denial of Johnson’s motion and before this appeal was heard, the Minnesota Supreme Court decided Farmington Plumbing and Heating Company v. Fisher Sand and Aggregate, Inc., Minn., 281 N.W.2d 838 (1979).5 There, in denying a partially negligent indemnitee’s claims against a partially negligent indemnitor, the Court stated:

Indemnity agreements are to be strictly construed when the indemnitee * * * seeks to be indemnified for its own negligence. There must be an express provision in the contract to indemnify the in-demnitee for liability occasioned by its own negligence; such an obligation will not be found by implication. Webster v. Klug & Smith, 81 Wis.2d 334, 340, 260 N.W.2d 686, 690 (1978).

Id. at 842.

Under this standard, Johnson’s claim for indemnity fails as the contract between Haglin and Johnson’s employer is devoid of any express provision which would indemnify Johnson for damages and expenses arising from his own negligence.

On appeal, however, Johnson argues that Farmington Plumbing is not controlling because the contract upon which he relies is different than that construed in the Farm-ington Plumbing case. Although the contractual provisions in the instant case are indeed broader than those construed by the Minnesota Supreme Court in Farmington Plumbing,6 the rule there announced does [967]*967not concern itself with the subtleties of determining, inferentially, the intent of the parties. Instead, it requires an express provision to effectuate the parties’ intention to allow for the indemnification of a negligent indemnitee.

Nevertheless, Johnson characterizes the operative language in Farmington Plumbing as mere dicta which, in light of a number of other Minnesota cases, should not be taken as an authoritative statement of Minnesota law. In particular, Johnson cites to Northern Pac. Ry. Co. v. Thorton Bros. Co., 206 Minn. 193, 288 N.W. 226 (1939), and the more recent cases of Anstine v. Lake Darling Ranch, 305 Minn. 243, 233 N.W.2d 723 (1975); Jacobson v. Rauenhorst Corporation, 301 Minn. 202, 221 N.W.2d 703 (1974); and Christy v. Menasha, 297 Minn. 334, 211 N.W.2d 773 (1973). These cases, he argues, stand for the proposition that indemnity contracts are to be fairly, not strictly, construed and that negligent indemnitees can recover from even innocent indemnitors if such is a fair construction of the intent of their contract. Johnson argues that the court in Farmington Plumbing couldn’t have intended to overrule, sub silentio, this line of cases and that, thus, the reasoning of these cases is still valid law and should be applied in the instant case.

However, a reading of the more recent cases cited by Johnson reveals no factual inconsistency with the result reached in Farmington Plumbing. Anstine, Jacobson and Christy all involved interpretations of the indemnity clause of the standard Minnesota Associated General Contractors (AGC) subcontract agreement. In Anstine, the Minnesota Supreme Court noted that the probable intent of the clause was to expressly provide that a subcontractor indemnify the contractor even if the latter was himself partially negligent. See An-stine v. Lake Darling Ranch, supra at 305 Minn. 249-250, 233 N.W.2d at 728. Thus, the Minnesota Supreme Court, although not required to do so under the standard in use in the Jacobson and Christy cases, has acknowledged that the indemnity clauses there construed probably did include the express provision which, after Farmington Plumbing, is required for recovery by a negligent indemnitee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
601 F.2d 964, 1979 U.S. App. LEXIS 13212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sargent-v-johnson-ca8-1979.