Opinion

Baker, J.

Suit by appellant against William Rankin, [237]*237treasurer of Marshall county, to enjoin the collection of a drainage assessment and to have the lien declared void. Appellees Pollard, Goff and Poohey, owners of the lien, on their application, were made parties defendant. Separate demurrers to each of the eight specifications of the complaint were sustained, except to the fourth. Answer in general denial and two affirmative paragraphs. Demurrer to second overruled, sustained to the third. Reply in general denial. Trial and finding for the defendants. Motion for a new trial overruled. Judgment for defendants. Exceptions by each party to each adverse ruling.

The errors assigned are: Sustaining the demurrers to each of the seven specifications of the complaint; overruling the demurrer to the second paragraph of answer to the fourth specification; overruling the motion for a new trial.

The ditch in question has its source in Kosciusko and its outlet in Marshall county. The complaint, after averring the filing of the petition in Kosciusko county and the appointment of viewers, the filing of the transcript before the commissioners of Marshall county and the appointment of viewers, the application of the joint viewers for extensions of time for filing report and the granting of the extensions, the filing of the report of the viewers, the hearing of the petition and rqport before the commissioners, the setting aside of the report and notice given, the making of an ■amended report by the viewers showing the assessment of plaintiff’s land and the impracticability of allotting portions of the work to the several persons assessed, the hearing of the petition and the finding that the drain was of public utility and that notice had been given, the making of the final report, the notices of and the letting of the contract for construction to Pollard, Goff and Eoohey, the assessment of plaintiff’s land in Marshall county, the examination and acceptance of the drain by the surveyor of Kosciusko county, the issuance of certificates by the surveyor of Kosciusko county that the work had been completed and that the [238]*238assessments were due and if not paid were to be collected as other taxes are collected, the delivery of the certificate to Pollard, Goff and Foohey, the refusal of plaintiff to pay the certificates, the issuance of duplicate certificates by the surveyor of Kosciusko county and the filing thereof with the auditor of Marshall county to be extended on the-tax duplicate, the placing of the tax duplicate in the hands of Rankin, treasurer of Marshall county, who is threatening and intending to enforce collection, — and alleging that the sums so extended purport to be a lien and constitute a cloud upon plaintiff’s title, — proceeds in eight specifications to state the reasons why the plaintiff should not be compelled to pay the assessments, and why they should be declared null and void.

Each specification, in connection with the general allegations preceding and following it, must be complete in itself as a separate paragraph of complaint. No specification can derive aid from another. Mustard v. Hoppess, 69 Ind. 324; Hilton v. Mason, 92 Ind. 157; Scott v. Hansheer, 94 Ind. 1; Hill v. Probst, 120 Ind. 528; Jones v. Cullen, 142 Ind. 335; Raymond v. Wathen, 142 Ind. 367.

The first and seventh specifications in substance allege that the proceedings are void for the reason that no allotments were made to plaintiff, but the contract for constructing plaintiff’s portion of the drain was let to Pollard, Goff and' Foohey, without giving plaintiff an opportunity to do the work. Appellant contends that the proceeding was governed by §4286 R. S. 1881, as the petition had been filed prior to the date of the amendment of the statute. Acts 1893, p. 329, §5656 Burns 1894, §4286 Horner 1897. The petition was filed in the commissioners’ court of Kosciusko county on February 23, 1893. The amendatory act took effect March 4, 1893, before any action had been taken on the petition. After it took effect, this cause was governed by the provisions of the amendatory act. Steele v. Empsom, 142 Ind. 397. These specifications, taken in connection with the preceding allegation that the viewers reported that it was [239]*239impracticable to make an allotment, show that the law was strictly followed and that the proceeding was. regular in this regard.

In the second and third specifications it is averred in substance that the proceedings were void for the reason that the viewers had asked for and obtained two extensions of time in which to make and file their report. The commissioners had authority to grant the extensions, and if the viewers found it impossible to complete their work within the time first fixed, they did exactly what the law required them to do. Bondurant v. Armey, 152 Ind. 244.

The fifth specification is based on the theory that the collection of the assessment should be restrained because the surveyor of Kosciusko county alone accepted the work and issued the certificate. The statute relating to drains in two counties (§§5677-5680 Burns 1891, §§4308-1311 R. S. 1881 and Horner 1897) makes no provision for the acceptance of work by the surveyors of the two counties acting jointly or by either alone; but requires that the proceedings be begun in the county containing the head of the proposed ditch and be governed so far 'as applicable by the provisions in reference to drains in one county. In Denton v. Thompson, 136 Ind. 146, it was held that appeals by remonstrators must be taken, irrespective of their residence, to the circuit court of the county whose commissioners had original jurisdiction of the proceedings. The statute relating to drains in two counties contains no reference to appeals. Similarly, the part of this statute directing that such drain be repaired by the joint action of the proper officers of the two counties having been declared inoperative, other parts of the drainage acts were looked to, and it was held that the repairs should be made throughout the entire ditch by the surveyor of the county in which the proceedings originated. Watkins v. State, 151 Ind. 123. Analogously, it might well be decided that the surveyor of Kosciusko county, that being the county containing the head of the ditch, was the proper [240]*240officer to accept the work in both counties. But it is unnecessary to pass upon the question, for this specification fails to show any equities that should entitle appellant to an injunction. It discloses, if anything, a mere irregularity of an officer in carrying out the judgment. It fails to show that appellant has not received all the benefits .he would have received if the work had been accepted in what he claims was the proper manner. This ground for injunctive relief is therefore insufficient. Montgomery v. Wasem, 116 Ind. 343; Fletcher v. White, 151 Ind. 401.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. Clark
172 N.E. 124 (Indiana Supreme Court, 1930)
Dyer v. Woods
76 N.E. 624 (Indiana Supreme Court, 1906)
Strayer v. Taylor
69 N.E. 145 (Indiana Supreme Court, 1903)
Studabaker v. Board of Commissioners
60 N.E. 453 (Indiana Supreme Court, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
56 N.E. 225, 154 Ind. 236, 1900 Ind. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sarber-v-rankin-ind-1900.