Sanford Hous. Auth. v. Perkins Propane, Inc.

CourtSuperior Court of Maine
DecidedSeptember 14, 2004
DocketYORcv-03-216
StatusUnpublished

This text of Sanford Hous. Auth. v. Perkins Propane, Inc. (Sanford Hous. Auth. v. Perkins Propane, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanford Hous. Auth. v. Perkins Propane, Inc., (Me. Super. Ct. 2004).

Opinion

STATE OF MAINE SUPERIOR COURT

CIVIL ACTION YORK, ss. DOCKET NO. CV-03-216 CS SANFORD HOUSING AUTHORITY, Plaintiff Vv. ~ ORDER CRN OEL! Le PERKINS PROPANE, INC,, é 24 FM Defendant Str

This case comes before the court on Plaintiff Sanford Housing Authority’s

Motion for Summary Judgment. Following hearing, the Motion is Denied. FACTS

Plaintiff Sanford Housing Authority (SHA) owns and manages East Side Acres and Sunset Towers apartments. In 1987, SHA entered into a three-year contract with Defendant Perkins Propane (Perkins) to supply those units with propane gas. The contract required the supplier to provide all equipment necessary for propane storage and delivery to the apartments. As the successful bidder, Perkins paid for the equipment currently on site, installed by SHA’s previous contractor, Eastern Propane Gas. Eventually Perkins replaced that equipment with its Own, at a cost of over $34,000.

SHA did not seek new bids on the propane contract after the first three years expired, and continued to use Perkins as its supplier until 2003. In 2003, SHA once again invited bids on the propane contract for the apartments. The new invitation to bid specified upgraded equipment different from that installed by Perkins. Perkins notified

SHA it would not be submitting a bid, and asked SHA whether it would be exercising its option, under Paragraph (3) of the 1987 contract, to purchase the equipment Perkins had installed. SHA notified Perkins it would not be exercising that option. In putting the contract out to bid, SHA did not provide prospective bidders with the cost of purchasing Perkins’ equipment and did not tell bidders that the purchase was required, A successful bidder was eventually identified who did not purchase Perkins’ equipment.

Perkins maintains that, under the terms of the 1987 contract, SHA was required to provide the purchase price of Perkins’ equipment to prospective bidders, who were obliged to include the purchase price in their bids. Perkins locates these requirements

in paragraph (3) of the contract, which reads:

(3) The parties hereby agree that the AUTHORITY shall have the option to purchase from PERKINS PROPANE all of the equipment installed by PERKINS PROPANE in connection with this Contract at a price to be negotiated between the parties at that time, .. . PERKINS PROPANE further agrees that the AUTHORITY shall be allowed to submit to bid in three (3) years this account and that PERKINS PROPANE will provide the purchase price to the AUTHORITY for the equipment so that any prospective bidder can include in its bid the cost of purchasing this equipment from PERKINS PROPANE.

SHA disputes Perkins’ reading of these terms, and sued for declaratory judgment

on the issue of its obligations to Perkins, if any, under the 1987 contract. On April 6, 2004 SHA filed this motion for summary judgment. DISCUSSION

In a motion for summary judgment, the moving party asserts that no genuine

issue of material fact exists and the judgment may be rendered as a matter of law.

Darling’s v. Ford Motor Co., 2003 ME 21, { 4, 817 A.2d 877, 879.

SHA contends it is undisputed that the 1987 contract between the parties has expired, or alternatively, that the express terms of Paragraph (3) in the 1987 contract in no way

obligate SHA to pass on the cost of Perkins’ equipment to a new supplier. Perkins argues that the relationship between the parties was governed by the terms of their 1987

contract, and that the express language of Paragraph (3) favors Perkins, or alternatively,

is ambiguous.

A. The Parties’ Three-Year Contract.

The law of contract recognizes that parties who have made an express contract for a stated period of time frequently proceed with performance after expiration of that time “without making any new express agreement, of extension or otherwise.” Corbin, A. L., Corbin on Contracts, § 1.19 (Rev. ed. 1993). “From such continued action a court may infer that the parties have agreed in fact to renew the . . . contract for another similar period.” Id. A number of jurisdictions have held that:

Where after the expiration of a contract fixing the reciprocal rights and

obligations of the parties, they continue doing business together, the conduct of

the parties may at times permit, or even constrain a finding that the parties impliedly agree that their rights and obligations in connection with such business

should continue to be measured as provided in the old contract.

Twitchell v. Pittsford, 106 A.D.2d 903, 905 (N.Y. App. Div., December 14, 1984). See, e.g.,

Steed v. Busby, 593 S.W.2d 34 (Ark. 1980); Steranko v. Inforex, 362 N.E.2d 222 (Ma.

1977); Town of Webster v. Village of Webster, 720 N.Y.S.2d 664 (App. Div.

2001)(holding an important kind of implied-in-fact contract may arise when parties continue performance after an express contract has expired).

In Maine, the Law Court recognizes that “the facts and circumstances surrounding the conduct between the parties can form a binding, implied-in-fact

contract.” Nightingale v. Leach, 2004 ME 22, { 4, 842 A.2d 1277, 1279 (citations

omitted)’. “Whatever may be said for the difference between an express contract and

an implied-in-fact contract, ‘[t]he distinction involves no difference in legal effect.’” Id.

See, e.g. Terrio v. Millinocket Cmty. Hosp, 379 A.2d 135, 138 (Me. 1977); Lawson v. McLeod, 152 Me. 67, 69 123 A.2d 199, 200 (1956). (citing Restatement (Second) of Contracts § 4 cmt. a ( 1981)(emphasis omitted)). An implied-in-fact contract contains all the necessary elements of a binding agreement, but its terms are inferred from “circumstances, including course of dealing, or usage of

trade or course of performance.” Restatement (Second) of Contracts § 5 cmt. a. (cited in

Taliento v. Portland West Plan. Council, 1997 ME 194, I 15, 705 A.2d 696, 700 (Lipez, J., dissenting)). Thus, the Law Court found an implied-in-fact contract when both Patties to an apartment management dispute “believed and intended that they were still Operating under a contractual relationship based on the terms of [an inapplicable] written document.” Nightingale, 2004 ME 22, | 4, 842 A.2d at 1279,

The parties do not dispute that the 1987 contract stipulated a term of three years. The parties disagree about whether the 1987 contract continued to govern their relationship after 1991. Here, it is undisputed that SHA and Perkins chose to continue their arrangement, whereby Perkins stored, delivered and supplied all propane requirements to the two SHA properties for some twelve years beyond the three-year term of their 1987 contract. Neither party maintains that the 1987 contract was expressly extended for an additional term, altered, revoked, or that a new contract replaced it. The parties adjusted the Price term of the 1987 contract to accommodate the changing price of propane, but otherwise did not change their understanding of their reciprocal responsibilities or alter their course of conduct. There is no evidence that the express terms of the 1987 agreement were treated by either party as having expired. In 2003, after deciding not to bid on the contract, Perkins inquired about and received responses from SHA that expressly referred to SHA’s option to purchase the equipment under Paragraph (3) of the 1987 contract. Only when Perkins expressed its expectation concerning reimbursement from new bidders, did the parties’ differing interpretations

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Terrio v. Millinocket Community Hospital
379 A.2d 135 (Supreme Judicial Court of Maine, 1977)
Steed v. Busby
593 S.W.2d 34 (Supreme Court of Arkansas, 1980)
Darling's v. Ford Motor Co.
2003 ME 21 (Supreme Judicial Court of Maine, 2003)
Acadia Insurance Co. v. Buck Construction Co.
2000 ME 154 (Supreme Judicial Court of Maine, 2000)
Benton Falls Associates v. Central Maine Power Co.
2003 ME 99 (Supreme Judicial Court of Maine, 2003)
Lawson v. McLeod
123 A.2d 199 (Supreme Judicial Court of Maine, 1956)
Steranko v. Inforex, Inc.
362 N.E.2d 222 (Massachusetts Appeals Court, 1977)
American Protection Insurance v. Acadia Insurance Co.
2003 ME 6 (Supreme Judicial Court of Maine, 2003)
Taliento v. Portland West Neighborhood Planning Council
1997 ME 194 (Supreme Judicial Court of Maine, 1997)
Portland Valve, Inc. v. Rockwood Systems Corp.
460 A.2d 1383 (Supreme Judicial Court of Maine, 1983)
Nightingale v. Leach
2004 ME 22 (Supreme Judicial Court of Maine, 2004)
Twitchell v. Town of Pittsford
106 A.D.2d 903 (Appellate Division of the Supreme Court of New York, 1984)
Town of Webster v. Village of Webster
280 A.D.2d 931 (Appellate Division of the Supreme Court of New York, 2001)
Stephan v. Pennsylvania General Insurance
621 A.2d 258 (Supreme Court of Connecticut, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Sanford Hous. Auth. v. Perkins Propane, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanford-hous-auth-v-perkins-propane-inc-mesuperct-2004.