Benton Falls Associates v. Central Maine Power Co.

2003 ME 99, 828 A.2d 759, 2003 Me. LEXIS 110
CourtSupreme Judicial Court of Maine
DecidedAugust 1, 2003
StatusPublished
Cited by14 cases

This text of 2003 ME 99 (Benton Falls Associates v. Central Maine Power Co.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benton Falls Associates v. Central Maine Power Co., 2003 ME 99, 828 A.2d 759, 2003 Me. LEXIS 110 (Me. 2003).

Opinion

LEVY, J.

[¶ 1] Central Maine Power Company (CMP) appeals from a summary judgment entered in the Superior Court (Cumberland County, Cole, J.) in favor of Benton Falls Associates (Benton Falls) in a contract dispute concerning the prices for electrical power indexed to cost calculations established by the Public Utilities Commission (PUC). CMP argues that the court erred when it (1) determined as a matter of law that the parties’ 1989 amended contract indexed prices to “avoided costs” which had been approved by the PUC in 1989, and (2) awarded Benton Falls its costs, including attorney fees, for opposing CMP’s motion for reconsideration. We conclude that a summary judgment should not have been entered because the parties’ 1989 contract is ambiguous and the material facts necessary to interpret it are disputed. We therefore vacate the judgment.

I. BACKGROUND

[¶ 2] Benton Falls owns and operates a 4.3 megawatt hydroelectric generating facility in Benton. Under federal and state laws, Benton Falls is a “qualifying facility” (QF) which entitles it to sell electrical power to a utility at rates that reflect the utility’s “avoided costs.” 1 At the time Benton Falls first contracted to sell power, “avoided costs” were defined as “the incremental costs to an electric utility of electric energy or capacity or both which, but for the purchase from the qualifying facility ... such utility would generate itself or purchase from another source.” Me. P.U.C. Reg. 36 § 1(A)(2) (May 13, 1981) (current version at 360 § 1(A)(3) (March *761 22, 1998)). The PUC establishes avoided costs based on estimates that utilities must submit annually. To calculate avoided costs, 50 megawatt increments of electricity, known as decrements, are subtracted from the utility’s hypothetical plan to meet its own anticipated electricity needs, known as its “base case resource plan.”

[¶ 3] In October 1984 Benton Falls entered into a contract to sell electrical power to CMP from late 1987 through 2007. The contract set prices for the years 1988 through 2000, and indexed prices from 2001 through 2007 to avoided costs that would be established by the PUC in the future. The contract described these rates as 75% of the “ ‘standard long-term avoided cost rates’ established by the ... PUC for the second 50 megawatt decrement, or the decrement which includes the second 50 megawatts if a second 50 megawatt decrement is not used.” Prior to 1986, the PUC held several avoided cost proceedings in which it established avoided costs for the first decrement through 1997, and for the second, third, and fourth decrements through 1998. In 1986 the PUC established avoided costs for the first decrement for 1998 through 2000, for the second, third, and fourth decrements for the period 1999 through 2000, and for four new decrements, identified as the fifth, sixth, seventh, and eighth decrements, for the period 1986 through 2000.

[¶ 4] Effective March 1987, the PUC required utilities to file avoided cost estimates for at least two decrements of capacity over a 30-year period, instead of the 15-year period previously required. Me. P.U.C. Reg. 36 § (3)(C)(5) (March 28, 1987). To conform with this new requirement, CMP filed avoided cost estimates in October 1987 for 1988 through 2017 based on four new 30-year decrements, labeled 87-A, 87-B, 87-C, and 87-D. CMP explained the change in its proposed decrement scheme as follows:

In past avoided cost filings, decrements were numbered 1 through 8 and calculated for 15 years. The year and letter designations now reflect the fact that new 30-year decrements do not build upon prior avoided cost estimates, but upon the actual contracts that resulted from those calculations. The base case resource plan includes all existing contracts, including cogeneration and small power production from prior decrements. Therefore, the next four decrements are the next four 50 MW blocks calculated from this base case and are related to prior decrements only to the extent that contracts based on previously calculated avoided costs now are included in the base case resource plan.

[¶ 5] In its filing, CMP stated that “Decrements 87-A and 87-B correspond to the two decrements previously designated as Decrements 7 and 8.” CMP also requested that the PUC approve the Decrement 87-A avoided costs as the avoided costs for the extended years of Decrement 1, Decrement 2, and Decrement 3.

[¶ 6] In spring 1989, before the PUC approved any avoided costs in Docket No. 87-261, the parties entered into an amended power purchase agreement (the amended contract). It provided that for the period beginning January 1, 1999, and ending December 31, 2007, certain rates be paid by CMP:

shall equal 75% of the so-called “standard long-term avoided costs” established by the [PUC] for the decrement which includes the second 50 megawatts and expressed in cents per kilowatt-hour, established for each of the years through December 31, 2007.

(Emphasis added). This provision differs from the corresponding provision in the original contract, which indexed the rate to *762 ‘standard long-term avoided cost rates’ established by the ... PUC for the second 50 megawatt decrement, or the decrement which includes the second 50 megawatts if a second 50 megawatt decrement is not used.” Elsewhere in the amended contract, the parties referred to the seventh decrement of avoided costs as “now known as Decrement 87-A.”

[¶ 7] In July 1989 the PUC approved CMP’s avoided costs through 2017 for Decrements 87-A, 87-B, 87-C, and 87-D. The PUC’s order closing the case for Docket No. 87-261, however, stated the following:

In this avoided cost proceeding, the only unresolved issue is whether the Commission, in this case, should establish avoided cost rates for decrements established in previous Commission avoided cost proceedings for certain years beyond the 15 years that had been set by the Commission. These years have commonly been called the “out years.” All parties addressing this issue agree that these rates should be set at some time. They disagree as to whether they should be set in this case or in some subsequent case. The reason they must be set is that nine contracts in the First, Second and Third Decrement have incorporated Commission-established avoided cost rates for these out years, even though they had not yet been set.

In March 1990, the PUC closed the proceeding and instructed CMP to submit data for avoided costs for extended decrements at the outset of its next avoided cost case.

[¶8] In January 2001, after CMP refused to pay prices indexed to Decrement 87-B established in Docket No. 87-261, Benton Falls filed a complaint in the Superior Court requesting a declaratory judgment setting forth CMP’s obligations under the amended contract and seeking money damages for breach of contract. CMP answered and counterclaimed, seeking a declaratory judgment that the PUC did not establish long term avoided costs for the “decrement which includes the second 50 megawatts” in Docket No. 87-261, and that the avoided costs set by the PUC in a more recent proceeding, Docket No. 2000-10, established the rate which applies under the amended contract. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knowlton v. Anderson
Maine Superior, 2011
Bath Sav. Inst. v. Ruffner
Maine Superior, 2009
Castiglia v. Bailey
Maine Superior, 2007
Tibbetts v. Worcester
Maine Superior, 2007
Topliff v. El-Hajj
Maine Superior, 2006
Perron v. Cowan
Maine Superior, 2006
Audette v. Brown
Maine Superior, 2005
Anchorage Realty Trust v. Donovan
2004 ME 137 (Supreme Judicial Court of Maine, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2003 ME 99, 828 A.2d 759, 2003 Me. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benton-falls-associates-v-central-maine-power-co-me-2003.