Sanford & Brooks Co. v. United States

47 Ct. Cl. 383, 1912 U.S. Ct. Cl. LEXIS 64, 1911 WL 1370
CourtUnited States Court of Claims
DecidedMay 6, 1912
DocketNo. 30607
StatusPublished

This text of 47 Ct. Cl. 383 (Sanford & Brooks Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanford & Brooks Co. v. United States, 47 Ct. Cl. 383, 1912 U.S. Ct. Cl. LEXIS 64, 1911 WL 1370 (cc 1912).

Opinion

Barney, J.,

delivered the opinion of the court.

This is a suit for a balance claimed to be due upon a contract between the plaintiff and the Government for the construction of certain timber revetments and also for the erection of certain earth embankments against the same at Fort Du Pont and Fort Delaware, Del.

The material portions of the specifications belonging to said contract, in so far as they bear upon the consideration and decision of this case, are as follows:

“27. The work to be done. — The work to be done under the specifications is about as follows:
“ The construction of about 4,500 linear feet of revetment, of which not more than 1,200 linear feet is to be two-row and the remainder one-row construction; the construction in place of two or four waste weirs as may be needed; the construction in place of one trunk sluice; the construction of about 5,600 linear feet of trestle to support 12" discharge pipe; the raising and repairing of about 10,000 linear feet of retaining embankment; and the probable repair of some of the present waste weirs at Forts Du Pont and Delaware; all as shown on attached plans, which form a part of these specifications.
“28. Timber revetment.■ — The timber revetment will be of one or two row construction as may be found necessary and [386]*386will be built in accordance with the plans for this work and backed up or filled in with an earth bank as shown on said plans.
“ It is estimated that not more than 1,200 feet will be rwo-row construction.
“30. Raising and ref airing banks. — The bank behind revetment along river front at Fort Du Pont will have a width on top of 4 feet. All other banks will be brought to a height of 14 feet above mean lew water, and will be of such dimensions as may be directed by the Engineer officer in charge. All earth placed in banks must be shaped up and tamped, and all work done to the satisfaction of the Engineer officer in charge.
37. The work will be done at such times and places as directed by the Engineer officer in charge.
“41. In canvassing bids, the following quantities will be assumed as approximately correct:
“ 40,000 cubic yards of material in banks and revetments.
“ 100 cubic yards stone in riprap of weirs and sluices.
“ 460,000 feet b. m. yellow pine.
“ 4,950 linear feet yellow pine piles.
“ 36,000 lbs. iron.
“ 3,100 lbs. spikes and wire nails.
“The above amounts will be increased or diminished in any amount that may be found necessary, and such increase or diminution shall not be made the basis of any claim by the contractor.”

The contract further provided:

“Provided., that the approximate quantities of materials as set forth in paragraph 41 of the said specifications may be diminished by the party of the first part to the extent of 25 per cent (25).”

The claim of the plaintiff relates exclusively to and grows out of that portion of the work which involved the building of the earth embankment.

The contract provided as to payment for this character of work as follows:

“ Raising and repairing retaining banks at Forts Du Pont and Delaware, and backing up and filling in revetment.
“For material in place, tamped and shaped up, twenty-seven (27) cents per cubic yard.”

The findings show that with the exception of the 80 feet two-row construction (and that was all of that kind of [387]*387construction ordered) the foundation for the revetment was marshy and swampy and furnished no solid foundation to support the material necessary to rest upon it. The timbers for the revetment were merely driven into this marshy and soft-mud bottom without penetrating into any solid material. The plaintiff was required to deposit the dredged material against this one-row revetment as thus constructed, and as a result of these two conditions the dredged material thus deposited settled and spread until of itself it created a foundation upon which the embankment when completed could stand.

As a resultant the plaintiff was compelled to deposit upon said embankment a total of 57,000 cubic yards of dredged material in order to complete an embankment as directed under its contract, which measured above the plane of the original proposed line only 18,244J cubic yards. The plaintiff was paid for the latter amount of yardage only, and this suit is brought to recover for the difference between the sum thus allowed and an allowance for the 57,000 cubic yards of material necessarily and actually deposited.

The decision in this controversy depends upon the construction of the provisions of the contract relating to the payment for this work, which is f

“For material in place, tamped and shaped up, twenty-seven (27) cents per cubic yard.”

. It is contended by the plaintiff that under this provision as to payment the plaintiff should be paid the agreed price per cubic yard for all of the dredged material actually deposited in the construction of the embankment, which would, of course, include such material as sank below the plane of the original proposed line for such embankment, while on the part of the defendants it is contended that the allowance was properly made only for such material as remained after completion, in the embankment above said plane.

We have not been cited by either party to any authority deciding as to the technical meaning to be given to the phrase “ measured in place ” as used in contracts of this kind. The problem in this case resolves itself into the question whether the plaintiff, under the contract, is to be paid at the [388]*388agreed price per cubic yard for all of the dredged material “placed” against the revetment in order to complete an embankment of the agreed dimensions, or whether it was only to receive pay for the yardage which, to use a common expression, remained above ground.

We think much light is thrown upon this question by other provisions of the contract. Paragraph 41 of the specifications above quoted provides:

“ 41. In canvassing bids, the following quantities will be assumed as approximately correct: 40,000 cubic yards of material in banks and revetments.”

Article I of the contract has the following statement:

“Provided, that the approximate quantities of materials as set forth in paragraph 41 of the said specifications may be diminished by the party of the first part to the extent of 25 per cent.”

Thus we find that when the contract was executed the Government made an estimate therein of 40,000 cubic yards as the probable quantity of dredged material which would he necessary for the completion of the work, and further hound itself not to diminish"’this quantity more than 25 per cent, which would make 30,000 cubic yards as the minimum quantity of dredged material which the plaintiff would be ■called upon to furnish.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. United States
73 U.S. 543 (Supreme Court, 1868)
Clark v. United States
3 Ct. Cl. 451 (Supreme Court, 1867)
Clark v. United States
4 Ct. Cl. 148 (Court of Claims, 1868)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 383, 1912 U.S. Ct. Cl. LEXIS 64, 1911 WL 1370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanford-brooks-co-v-united-states-cc-1912.