Clark v. United States

4 Ct. Cl. 148
CourtUnited States Court of Claims
DecidedDecember 15, 1868
StatusPublished
Cited by1 cases

This text of 4 Ct. Cl. 148 (Clark v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark v. United States, 4 Ct. Cl. 148 (cc 1868).

Opinions

Nott, J.,

delivered tbe opinion of tbe court:

Tbe cause of action in this case accrued in 1848. For twenty years tbe claim has been vigorously pressed upon tbe executive departments, upon Congress, and in this court. . Tbe case has been three times tried — twice before this court as formerly constituted, and once since its reorganization in 1863. In the two former trials tbe three judges came to three different conclusions and no judicial result was reached. In tbe trial before tbe present court judgment was given against tbe claimant, and that judgment tbe Supreme Court, on appeal, lias reversed. (1C. Cls.B., p.246; 3 id., p. 451.)

In tbe history of tbe case appear two vexed questions. Tbe contract of tbe claimant bound him u to furnish all tbe material and make 221,000 cubic yards of embankment at the navy yard, Memphis, Tennessee;” which was to be made uin such manner mid place as shall he directed” by tbe government’s engineer, and to be finished “on or before the 15th July, 1847.” And ufor the materials and emhmihment made, approved of,, and received,” tbe contract further provides, tbe claimant should receive 18 cents per cubic yard as bis bills therefor were presented, but 10 per cent, was to be “ withheld from the amount of all payments on account thereof” until tbe contract should be fully performed. Out of these provisions of tbe contract tbe two vexed questions arose: tbe first was, whether tbe contractor should be paid for tbe yards of earth ■ contained in tbe embankment after it bad been accepted by tbe defendants, and not for tbe number of yards delivered; tbe second, whether tbe intermediate measurements and payments by tbe defendants [151]*151were not each, an acceptance of so much of tie embankment, leaving tie subsequent losses by waste, shrinkage, and tie washing of tie river, to be borne by them and not by tie claimant.

To these two questions might be added a third, relative to tie admissibility of certain ex parte affidavits used to support tie claim before Congress, and which we ruled were incompetent and inadmissible, These three questions were the only questions at law discussed or considered on the last trial, and the first two were the questions on which the three judges of the former Court of Claims were so strongly divided. Yet, as very often happens, the questions so much discussed below were not deemed important or difficult when the appeal was heard in the court above; and it only impliedly, though very clearly, appears that our rulings upon the former two stand approved and affirmed, while the third does not seem to have been brought before the appellate court. That court, however, went beyond these three questions, and reversed the judgment upon other grounds.

The first of these grounds of reversal is that the Court of Claims erred in having placed “ the right of the agents of the government to use the embankment as a roadway, and to compel him (the claimant) to dump loose earth into the current, by which it was carried away,” “upon the simple fact that those injuries were inflicted after the day at which his contract should have been completed.” And the Supreme Court then points out that “the contract declares no penalty for not completing the work by the 15th of July,” and that “ it does not even authorize the government to forfeit the contract or to terminate it.”

It certainly never .was the intention .of this court to hold, or to be understood as holding, that an ordinary contract to do certain work or build a certain structure by a certain day, containing no clause of forfeiture, could be forfeited merely because the work was not completed at the appointed time. In this case the contract was founded upon an advertisement for sealed proposals for building the embankment, and “ for constructing the foundations for nine buildings,” for furnishing the lumber therefor, &c. These buildings were to be erected on and near the embankment, and the obstructions complained of, as .we understand the evidence, arose from the work for and upon these nine buildings. It would seem to us that the want of a forfeiture [152]*152clause in tbe contract could not exclude tbe defendants from tbe use of tbeir own property beyond tbe prescribed time. And this was precisely wbat we intended to bold. Tbe contract was not forfeited. Up to a day certain tbe claimant was entitled to tbe full use of tbe premises. Beyond that day be might continue bis work subject to tbe use which tbe defendants might make of them own premises. In this we thought we preserved tbe rights of both parties, leaving tbe one free to erect tbeir buildings and tbe other free to carry on bis work by necessarily circuitous routes and such other disadvantages as bis own delay might have caused. But, unfortunately, this view of tbe case, and, indeed, these facts in tbe case, never reached tbe Supreme Court. When this case was last tried tbe right of appeal did not exist, and tbe rules of tbe Supreme Court bad not been promulgated. When tbe right of appeal subsequently came, tbe findings for tbe appeal bad to be framed in a manner different from tbe present one, and not so well adapted for a clear statement of tbe reasons for tbe decision in tbe court below. Added to these disadvantages, tbe right of appeal came suddenly, and this court was compelled to-prepare tbe findings for all tbe cases which bad accumulated since its reorganization. It is therefore not to be wondered at that tbe case may have gone up in such a form as to mislead tbe tribunal by which tbe decision was to be reviewed.

A second ground of reversal was in tbe supposed ruling of this court that, tbe loss caused by the settling of tbe batture, on which tbe embankment is built, was to be borne by tbe claimant. “We take it for granted,” says tbe opinion, “that tbe word {settling’ in this finding of tbe law is used for tbe settling of tbe batture.” Such was not'our meaning'. In tbe opinion read at the time this judgment was rendered it was expressly said of tbe “ settling” of tbe batture: “The fact of its sinking rests on the opinion of witnesses. The extent to which it did sink is not shown hy a particle of evidence. No computation of damages can he made from such a failure of proof P

We certainly thought that if tbe claimant bad proved this part of bis case, be should assuredly recover. But, unfortunately for him, bis evidence went to tbe whole of bis case or none. It showed tbe number of yards of earth deposited and tbe number remaining, and there it stopped. It was satisfactory and sufficient, upon bis legal theory, that be should [153]*153recover for all of tbe missing yards; but when tbis court beld that he should not recover for any one part of his alleged damages, there was nothing in the evidence to show what amount of damage was suffered elsewhere. We were therefore compelled to dismiss that part of the case for want of proof.

Tet there is still another ground of reversal. In view of the facts that the embankment was to be made, according to the contract, in the Memphis navy yard, and that it actually was made there, this court regarded the contract precisely as if (in the language of the Supreme Court) “ this embankment had been built on dry land.” We thought that, as the claimant did “contract and engage” to “furnish all the material and make 221,000 cubic yards of embankment at the navy yard,” he was bound to do so; and that, as “ no other charge” was to be admitted, nor allowance to be made by the United States on account of this contract, the risks were to be assumed by the contractor, and the losses to be borne by him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanford & Brooks Co. v. United States
47 Ct. Cl. 383 (Court of Claims, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
4 Ct. Cl. 148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-v-united-states-cc-1868.