Sanduski v. Charles Schwab & Co., Inc.

CourtDistrict Court, D. Nevada
DecidedAugust 20, 2020
Docket2:19-cv-01340
StatusUnknown

This text of Sanduski v. Charles Schwab & Co., Inc. (Sanduski v. Charles Schwab & Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanduski v. Charles Schwab & Co., Inc., (D. Nev. 2020).

Opinion

1 UNITED STATES DISTRICT COURT 2 DISTRICT OF NEVADA 3 Thomas J. Sanduski, Case No.: 2:19-cv-01340-JAD-BNW

4 Plaintiff Order Confirming Arbitration Award 5 v. [ECF Nos. 8, 14] 6 Charles Schwab & Co., Inc.,

7 Defendant

8 Thomas Sanduski petitions to vacate a Financial Industry Regulatory Authority (FINRA) 9 arbitration award finding him liable to Charles Schwab & Co., Inc. for failing to pay his 10 unsecured debit balance. Sanduski raises two issues for vacatur: (1) one of the arbitrators was 11 partial to Charles Schwab and (2) the panel was guilty of misconduct, and potentially exceeded 12 its authority, for refusing Sanduski’s request to postpone the hearing.1 Charles Schwab 13 countermoves to enforce the award.2 Sanduski has not met his heavy burden of proving that the 14 two limited contacts between one of his arbitrators and Charles Schwab’s experts demonstrated 15 actual bias or prejudicial non-disclosure sufficient to justify vacatur under 9 U.S.C. § 10(a)(2). 16 Nor has Sanduski shown that the panel’s reasonable rejection of his mid-hearing postponement 17 request was arbitrary or showed manifest disregard of the law, as required under §§ 10(a)(3) and 18 10(a)(4). So, I deny Sanduski’s petition and grant Charles Schwab’s countermotion, confirming 19 the award in its entirety. 20 21 22

23 1 ECF No. 14 (motion to vacate arbitration award). 2 ECF Nos. 7 (opposition to motion to vacate); 8 (motion to confirm arbitration award). 1 Background 2 Charles Schwab sought $418,518.14 from Sanduski in a FINRA arbitration proceeding, 3 claiming that Sanduski breached the terms of his Schwab One Account Agreement by failing to 4 pay his unsecured debit balance.3 The parties do not appear to contest the underlying substance 5 of their dispute or that the FINRA rules of arbitration apply,4 but instead focus on irregularities

6 at the hearing and impropriety after its conclusion. Because the dispute involved more than 7 $100,000, FINRA Rule 12401 required arbitration by a panel “of three arbitrators, unless the 8 parties agree in writing to one arbitrator.”5 Rule 12601 governs postponements and provides that 9 postponement requests made within ten days of the hearing date will only be granted if the panel 10 “determines that good cause exists.”6 Rule 12210 cautions the parties against “ex parte 11 communications,” noting that “no party . . . may communicate with any arbitrator outside of a 12 scheduled hearing or conference regarding an arbitration unless all parties or their representatives 13 are present.”7 Finally, the FINRA Chairperson Training Manual advises arbitrators to be 14 cognizant of Rule 12208 and Canon IV C of the Code of Ethics, noting that Rule 12208 states

15 that “arbitrators should not deny any party the opportunity to representation.”8 16 The two-day hearing was initially scheduled to begin January 31, 2019, but was 17 postponed by two months at Sanduski’s request because his counsel had withdrawn.9 Sanduski 18 19 3 ECF No. 14 at 10 (arbitration order). 20 4 ECF Nos. 7-1 at ¶ 4; 8-1 at 18; 14 at ¶¶ 4–5. 21 5 ECF No. 21-1, Ex. 14 at 1, Ex. 16 at 2. 6 ECF Nos. 7-1, Ex. 4 at 1; 8-1, Ex. 4 at 1. 22 7 ECF Nos 7-1, Ex. 8 at 1; 8-1, Ex. 8 at 1. 23 8 ECF No. 14 at 22. 9 ECF Nos. 7-1 at ¶ 5; 8-1 at ¶ 5. 1 did not secure new counsel and appeared without representation at the March 27th hearing.10 2 During the first day of the hearing, Arbitrator Geddes discovered that he would be unable to 3 physically attend the hearing on the second day because of a “family emergency.”11 The panel 4 offered the parties the option to postpone the hearing, proceed with only two panelists, or permit 5 Geddes to participate by phone on the second day.12 Both parties selected the third option and

6 Geddes chose to attend the hearing remotely.13 7 But when that day arrived, Sanduski expressed reservations about Geddes’s virtual 8 attendance and asked to postpone the hearing a second time so that he could secure 9 representation.14 Chairperson Edmonson reviewed the training manual and cited rules, and he 10 determined that good cause did not exist for the postponement.15 He interpreted Rule 12208 and 11 the training manual materials as counseling postponements where parties had never been 12 represented; because Sanduski’s counsel had withdrawn, and Sanduski had not secured new 13 counsel in the intervening two months, Edmonson believed further postponement was 14 “inappropriate” and “delay[ed] the process unduly.”16 Based on the record before me, Sanduski

15 did not raise with the panel that Geddes’s virtual attendance violated any FINRA Rules. 16 The specter of impropriety surfaced at the hearing’s close. After argument ceased and 17 the parties filed out, one of Charles Schwab’s experts said “see you next week” to Arbitrator 18 19 10 ECF Nos. 14 at 11; 17 at 15–16. 20 11 ECF No. 14 at ¶ 6. 21 12 Id. at ¶ 7. 13 Id. at ¶ 9. 22 14 Id. at ¶ 11. 23 15 ECF No. 17 at 47; see also ECF No. 14 at ¶¶ 11–13. 16 ECF No. 17 at 48. 1 Grinnell.17 Though Grinnell did not respond to or acknowledge the statement, the parties agree 2 this was likely a reference to Grinnell’s empanelment on a second Charles Schwab arbitration, 3 which would involve that same expert witness.18 After Grinnell made her decision and learned 4 that she would not be involved in writing the order, Grinnell left the arbitration and called a car 5 for the airport.19 Noticing that a different Charles Schwab expert witness was also going to the

6 airport, Grinnell chose to share a ride.20 Grinnell warned the expert that she could not discuss 7 the preceding arbitration and they chatted exclusively about living in Phoenix.21 In May 2019, 8 the panel issued its order, awarding Charles Schwab $418,518.14 in damages.22 9 Discussion 10 A. Standard for reviewing an arbitration award 11 The Federal Arbitration Act (FAA) permits any party to apply to the court to confirm, 12 vacate, modify, or correct an arbitration award.23 “[F]ederal court review of arbitration awards is 13 extremely limited,”24 and an award must be confirmed unless it is vacated, modified, or 14 corrected on the grounds described in the FAA.25 An award may be vacated if: (1) it was

15 procured by corruption, fraud, or undue means; (2) “there was evident partiality or corruption in 16 the arbitrators;” (3) “the arbitrators were guilty of misconduct in refusing to postpone the 17 17 ECF No. 14 at ¶ 15, Ex. A at 3; see also ECF No. 7 at 12. 18 18 ECF No. 14 at ¶ 15; see also id. at 12. 19 19 Id.; see also id. at 29–30. 20 Id. at 29–30. 20 21 Id. 21 22 Id. at 11. 22 23 9 U.S.C. §§ 9, 10, 11. 24 A.G. Edwards & Sons, Inc. v. McCollough, 967 F.2d 1401, 1403 (9th Cir. 1992) (citation and 23 quotations omitted). 25 Hall St. Assocs., L.L.C. v. Mattel, Inc., 552 U.S. 576, 582 (2008) (citing 9 U.S.C. § 9). 1 hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to 2 the controversy; or of any other misbehavior by which the rights of any party have been 3 prejudiced;” or (4) “the arbitrators exceeded their powers, or so imperfectly executed them that a 4 mutual, final, and definite award upon the subject matter submitted was not made.”26 5 Sanduski marshals two of these theories against the arbitrator’s award in this case:

6 (1) one arbitrator on the panel was “impartial” and (2) the arbitrators committed misconduct by 7 refusing to postpone his hearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Lagstein v. CERTAIN UNDERWRITERS, LLOYD'S, LONDON
607 F.3d 634 (Ninth Circuit, 2010)
Johnson v. Gruma Corp.
614 F.3d 1062 (Ninth Circuit, 2010)
Biller v. Toyota Motor Corp.
668 F.3d 655 (Ninth Circuit, 2012)
Fairchild & Co. v. Richmond, Fredericksburg & Potomac Railroad
516 F. Supp. 1305 (District of Columbia, 1981)
The Sunrise Trust v. Morgan Stanley & Co.
552 F. App'x 685 (Ninth Circuit, 2014)
Jon Sanchez v. Robert Elizondo
878 F.3d 1216 (Ninth Circuit, 2018)
Monster Energy Company v. City Beverages, LLC
940 F.3d 1130 (Ninth Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Sanduski v. Charles Schwab & Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanduski-v-charles-schwab-co-inc-nvd-2020.