Sand Point Water & Light Co. v. Panhandle Development Co.

83 P. 347, 11 Idaho 405, 1905 Ida. LEXIS 72
CourtIdaho Supreme Court
DecidedNovember 10, 1905
StatusPublished
Cited by24 cases

This text of 83 P. 347 (Sand Point Water & Light Co. v. Panhandle Development Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sand Point Water & Light Co. v. Panhandle Development Co., 83 P. 347, 11 Idaho 405, 1905 Ida. LEXIS 72 (Idaho 1905).

Opinion

AILSHIE, J.

— Prior to hearing this case on its merits, the respondent filed and presented a motion to dismiss the appeal and also a motion to strike from the transcript the appellant’s statement on motion for a new trial. We have carefully examined the record and affidavits used on the hearing of these motions and have concluded that both motions should be overruled, and it is so ordered.

This action was commenced by the respondent corporation to restrain the appellant corporation from diverting and appropriating the waters of Sand creek and Switzer creek in Kootenai county, and to restrain and enjoin the defendants from interfering with or diverting the waters of those streams in any way or manner that would interfere with the rights and appropriation of the plaintiff. The case went to trial upon complaint and answer and resulted in a judgment for the plaintiff, from which judgment and an order denying a motion for a new trial, the defendant has appealed. The substance of the trial court’s findings of fact is that the plaintiff’s grantor was the prior appropriator of the waters of Switzer creek and the west branch of Sand creek, situated in Kootenai county, and that such appropriation dates from September 26, 1903, the-date on which respondent’s grantor made his application to the state engineer for a permit to divert, appropriate and use the waters of those streams to the extent of twenty cubic feet per second. The court finds-that plaintiff and its grantor had performed all the acts and requirements necessary or imposed by the statute for the protection of its appropriation, and had diverted the waters and applied them to a beneficial use in supplying the village of Sand Point and its inhabitants with water for domestic uses and fire purposes. The court also finds that the respondent’s appropriation was and is prior to that of the appellant and so ordered and decreed. The appellant contends that the undisputed facts as disclosed by the evidence and appearing upon the record show clearly and beyond question that the court’s findings are unsupported by the evidence, and that he should have found that appellant’s water right from these streams is prior and su[411]*411perior to the rights of respondent, and that the findings of the court in this respect are wholly unsupported. The facts as they appear from the record upon this point are substantially as follows:

On December 16, 1902, appellant’s grantors located a water right on West Sand or Mill creek in Kootenai county, and the location notice thereof was posted and duly filed and recorded in the office of the county recorder of Kootenai county, and thereafter, in due time, was filed in the office of the state engineer at Boise city. Within a few days thereafter the same parties duly and regularly made two additional locations on these streams. On the fourteenth day of January, 1903, and about twenty-nine days after making the first location, work was commenced which consisted in cutting out a trail up the canyon and makng a survey for flumes and ditches. Work was continuously prosecuted from that time until the date of the trial of this cause, with at least one man on the ground all the time engaged in building a road, and a flume and ditch through which to carry the waters of these streams, and the general work incident to the construction of the diverting work for carrying out the purposes for which the appropriation was being made. An itemized statement of expenditures made in carrying on this work appears to have been presented upon the trial showing an expenditure of $714 for wages, groceries, tools and supplies, between the fourteenth day of January, 1903, and the first day of September, 1903. It was also shown that an expenditure of more than $1,700 was made on these works between the fourteenth day of January, 1903, and the eighth day of February, 1904. At the time of the trial in this case it appeared that the appellant had built about one mile of road up the canvyn for the purpose of reaching the point of diversion on the stream and conveying material and supplies, and had also erected ans constructed a flume three thousand four hundred feet in length. None of these facts are directly disputed by the respondent, but. at the trial the respondent placed witnesses upon tne stand who testified that in passing through this country in the neisrhoor[412]*412hood of this work they had noticed some work had been done, but the witnesses estimated the value thereof as very small — something like $200 or $300, perhaps. But it does not appear that these witnesses had made very much examination or pretended to have seen all the works or were at all accurate or positive as to their estimates. It remains, nevertheless, a fact, that they admit that work had been done there, and, in fact, one of plaintiff’s witnesses was one of the first men employed by the defendant’s grantor, and had made the original survey for the defendant’s diverting works. The fact stands upon the record practically undisputed, that on the twenty-ninth day of September, 1903, the date on which respondent’s grantor obtained his permit from the state engineer to divert and appropriate the waters of these streams, the appellant was actively engaged in the construction of its diverting works, and had at that time expended from $700 to $800 in the prosecution of the work. It should be observed that appellant’s location and the prosecution of its work was made under the act of February 25, 1899 (Sess. Laws 1899, p. 380), while the respondent’s right was initiated under the act approved March 11, 1903 (Sess. Laws 1903, p. 223). By the latter act a permit is obtained from the state engineer to divert and appropriate the waters of any of the public streams of the state, while under the act of 1899, notice was required to be posted and a copy thereof filed and recorded with the county recorder, and a duplicate thereof filed with the state engineer. By section 6 of the act of 1899, under which appellant initiated its right, it is provided: “Within sixty days after the notice is posted, the claimant must commence the excavation or construction of the works by which he intends to divert the water, and must prosecute the work diligently and uninterruptedly to completion, unless temporarily interrupted by snow, rain or cold weather.” Bespondent claims that the appellant failed to show that it had prosecuted the construction of its diverting works with the diligence required by section 6, supra, and for that reason, if for none other, the judgment was properly entered against [413]*413appellant. It seems to us, however, when we consider that this work was being prosecuted in a mountainous section of the state where there is a heavy snowfall and a long winter season, with much rough and stormy weather, which would interrupt and delay the character of work that was being carried on, that the amount and kind of work which is shown to have been done evidences good faith, reasonable diligence and a purpose to complete the work and apply the waters to the beneficial use designated. Saying nothing of the record notice which the respondent had, the work upon the ground and its continued prosecution was ample actual notice to respondent, or any other subsequent claimant to these waters, as to the nature of the claim asserted by appellant. It seems to us that the real difficulty in this case has arisen from a wrong construction and misapplication of the word “appropriate” as used in our statutes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joyce Livestock Co. v. United States
156 P.3d 502 (Idaho Supreme Court, 2007)
State v. United States
996 P.2d 806 (Idaho Supreme Court, 2000)
R.T. Nahas Co. v. Hulet
674 P.2d 1036 (Idaho Court of Appeals, 1983)
State, Dept. of Parks v. IDAHO DEPT, WATER ADMIN.
530 P.2d 924 (Idaho Supreme Court, 1974)
Glenn Dale Ranches, Inc. v. Shaub
494 P.2d 1029 (Idaho Supreme Court, 1972)
Cantlin v. Carter
397 P.2d 761 (Idaho Supreme Court, 1964)
Jones v. McIntire
91 P.2d 373 (Idaho Supreme Court, 1939)
Pioneer Irrigation District v. American Ditch Ass'n
1 P.2d 196 (Idaho Supreme Court, 1931)
Keiler v. McDonald
218 P. 365 (Idaho Supreme Court, 1923)
Re Determination of Water Rights of Hood River.
227 P. 1065 (Oregon Supreme Court, 1923)
Short v. Praisewater
208 P. 844 (Idaho Supreme Court, 1922)
Reno v. Richards
178 P. 81 (Idaho Supreme Court, 1918)
Basinger v. Taylor
164 P. 522 (Idaho Supreme Court, 1917)
State ex rel. Ham, Yearsley & Ryrie v. Superior Court
126 P. 945 (Washington Supreme Court, 1912)
Furey v. Taylor
127 P. 676 (Idaho Supreme Court, 1912)
Schodde v. Twin Falls Land & Water Co.
224 U.S. 107 (Supreme Court, 1912)
Nielson v. Parker
115 P. 488 (Idaho Supreme Court, 1911)
Speer v. Stephenson
102 P. 365 (Idaho Supreme Court, 1909)
Brown v. Newell
85 P. 388 (Idaho Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
83 P. 347, 11 Idaho 405, 1905 Ida. LEXIS 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sand-point-water-light-co-v-panhandle-development-co-idaho-1905.