San Francisco Planning & Urban Renewal Ass'n v. Central Permit Bureau

30 Cal. App. 3d 920, 106 Cal. Rptr. 670, 1973 Cal. App. LEXIS 1263
CourtCalifornia Court of Appeal
DecidedFebruary 28, 1973
DocketCiv. 31380
StatusPublished
Cited by5 cases

This text of 30 Cal. App. 3d 920 (San Francisco Planning & Urban Renewal Ass'n v. Central Permit Bureau) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Francisco Planning & Urban Renewal Ass'n v. Central Permit Bureau, 30 Cal. App. 3d 920, 106 Cal. Rptr. 670, 1973 Cal. App. LEXIS 1263 (Cal. Ct. App. 1973).

Opinions

[923]*923Opinion

CALDECOTT, J.

This is an appeal from a judgment of the Superior Court of the City and County of San Francisco denying appellants San Francisco Planning and Urban Renewal Association and individual petitioners (hereinafter referred to as SPUR), a writ of mandate. Appellants sought an order revoking a permit the City and County of San Francisco had granted to the real party in interest San Francisco Chatmar Associates (Chatmar), for the construction of a highrise hotel.

On November 26, 1971, a petition for writ of mandate was filed in the Superior Court of the City and County of San Francisco by SPUR. The petitioner requested that the respondents City and County of San Francisco Central Permit Bureau, Planning Commission and Board of Permit Appeals (hereinafter Agencies) revoke a site permit granted to Chatmar Associates for construction of a Holiday Inn Hotel. The writ was requested on the ground that the proposed building violated the height and bulk limitation of the “Urban Design Plan.” The petition was denied and judgment entered on December 13, 1971. The appeal is from the judgment.

On August 26, 1971, the city planning commission, by resolution, adopted, as an amendment to the Master Plan of the City and County of San Francisco, the “Urban Design Plan” which had been under study for several years. The plan was first published in May of 1971; public presentation had been made in May; and hearings held in July. On August 26, 1971, the city planning commission also adopted a resolution which declared its intention to reclassify property in accordance with the bulk and height limitation of the Urban Design Plan. Recognizing that additional study of the plan was necessary, the commission adopted for its guidance, until the board of supervisors enacted the proposed plan, an “outline of interim, height and bulk controls.” Approximately one year later, on July 31, 1972, the board of supervisors adopted the Urban Design Plan, and the ordinance was signed into law by the mayor on August 18,1972.

On June 21, 1971, Chatmar filed a site permit application for a Holiday Inn at the corner of Pine Street and Van Ness Avenue in San Francisco. Chatmar had first informally approached the San Francisco Planning Department in the middle of 1969 with a proposed highrise hotel for that location. Chatmar purchased the land in November 1969 and in May 1970. [924]*924In July 1970, the planning department staff advised the developers that, although their amended proposal did not violate the existing zoning laws, it would not be in accord with the height and bulk restrictions of the forthcoming Urban Design Plan. The developers did not apply for a permit at that time and had no further contact with the planning department until one year later when they filed their application for a site permit. The developers stated that they had been engaged in obtaining financing during this period.

The site permit was not issued by the central permit bureau at the time the application was made, because the preliminary plans disclosed the building would greatly exceed the height and bulk guidelines of the Urban Design Plan. The application was then called up for a decision by the planning commission.1

At its regular meeting on September 16, 1971, the planning commission considered reports on the project, the effect of section 302(e) of the city Planning Code and the Urban Design Plan.

The record is clear that the plans submitted by Chatmar complied with the existing zoning laws. It is also clear that the plan differed substantially from the provisions of the Urban Design Plan, particularly as to the height and bulk of the building. At the hearing it was the director of planning’s interpretation that the interim controls of August 26, 1971 did not apply to the Chatmar project.

At the hearing, witnesses, both for and against approval of the application for the permit, appeared. Those favoring the granting of the permit pointed out the economic benefits to the city to be derived from the project and those opposed spoke of the undesirable effects of the project on the residential character of the neighborhood and the unfortunate effect on the city because of its height and bulk. The planning commission approved the application. The permit was issued on October 14, 1971.

Appellants appealed to the permit appeals board which, in a de novo hearing on November 8, 1971, concurred in the planning commission’s [925]*925decision. No additional evidence was taken at this hearing. A request for rehearing was denied on November 22, 1971. On November 26, 1971, the petition for writ of mandate was filed in the superior court commencing the judicial procedures upon which this appeal is based.

The following are the issues raised, on this appeal.

I. Are the respondent zoning Agencies bound to apply the interim zoning controls in existence at the time of their respective hearings on the site permit application?

II. Did the board of permit appeals fail to follow the procedures, prescribed by the Charter of the City and County of San Francisco for obtaining a variance from the zoning ordinance?

III. Does the “Due Process” clause require that the board of permit appeals make findings of fact when exercising its appellate powers?

IV. Are amendments to the Planning Code adopted subsequent to the final administrative agency’s action binding upon the appellate court?

V. Was an environmental impact report required in this case?

I

Are the respondent zoning Agencies bound to apply the interim zoning controls in existence at the time of their respective hearings on the site permit application?

Section 302(e) of the Planning Code of the City and County of San Francisco cited by appellants provides in part: “302(e) Effect upon permit applications. No application for a building permit ... or for any other permit ... for a new use of property, filed subsequent to the day that ... a resolution of intention has been adopted for the reclassification of such property . . . shall be approved by the Department of City Planning while proceedings are pending on such reclassification . . . unless the construction and use proposed . . . would conform both to the existing classification of such property . . . and also to the different classification . . . under consideration in those proceedings; . . .” (Italics added.)

The basic contention of the appellants is that the respondent Agencies were required under section 302(e) to apply the interim zoning controls in effect at the time of their action and that the Agencies did not have discretion to disregard these controls merely because a site permit application was filed before the controls were enacted. This contention is repeated, in [926]*926various forms, throughout the appellants’ argument as though the mere repetition of a false premise will endow it with credence.

We are unable to agree with appellants’ interpretation of section 302(e). The wording of the section is clear. The section provides that no application for a building permit filed subsequent to the resolution of intention shall be approved. It is undisputed that the proposed building of Chatmar complied with the requirements of the existing zoning laws and in fact the plans were modified so that they would comply.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guinnane v. San Francisco City Planning Commission
209 Cal. App. 3d 732 (California Court of Appeal, 1989)
McDonald's Systems of California, Inc. v. Board of Permit Appeals
44 Cal. App. 3d 525 (California Court of Appeal, 1975)
Plan for Arcadia, Inc. v. City Council of Arcadia
42 Cal. App. 3d 712 (California Court of Appeal, 1974)
People v. County of Kern
39 Cal. App. 3d 830 (California Court of Appeal, 1974)
San Francisco Planning & Urban Renewal Ass'n v. Central Permit Bureau
30 Cal. App. 3d 920 (California Court of Appeal, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
30 Cal. App. 3d 920, 106 Cal. Rptr. 670, 1973 Cal. App. LEXIS 1263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/san-francisco-planning-urban-renewal-assn-v-central-permit-bureau-calctapp-1973.