Sampson Motors, Inc. v. Roland

263 P.2d 445, 121 Cal. App. 2d 491, 1953 Cal. App. LEXIS 1380
CourtCalifornia Court of Appeal
DecidedNovember 24, 1953
DocketCiv. 19629
StatusPublished
Cited by8 cases

This text of 263 P.2d 445 (Sampson Motors, Inc. v. Roland) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sampson Motors, Inc. v. Roland, 263 P.2d 445, 121 Cal. App. 2d 491, 1953 Cal. App. LEXIS 1380 (Cal. Ct. App. 1953).

Opinion

MOORE, P. J.

Appellant contracted with respondent July 3, 1951, for the construction of a machine shop according to plans and specifications. The total contract price was $14,876 which included “relocating garage and pouring necessary slab for same and for chip bins.” Neither painting, plumbing nor electrical work was included in the work to be done. The contract required completion of the structure within 90 days and contained a clause for the settlement by arbitration of “all questions as to the rights and obligations arising under the terms of the contract, the plans and specifications.” Also, it authorized the arbitrators to fix their own compensation.

*493 A dispute having arisen concerning asserted violations of the contract arbitrators were appointed, hearings were held and an award was made. The findings were that respondent substantially completed performance on October 8, 1951, in a good and workmanlike manner “except as hereinafter found”; that the contractor was entitled to $1,332.85 less a credit of $50 for respondent’s failure to perform certain work, and for extras and various items he should be paid $2,323.49, including his work on the storage shed for $900 and removal of the west wall for $361.91. Other items claimed by respondent were disallowed; appellant was awarded $500 as damages due to unleveled concrete floor, but its claims for damages for delay and certain defects and other errors in construction were likewise rejected. Respondent was ordered to perform some nine specific items within 20 days. By their award the arbitrators fixed their own total compensation at $1,020, each party to pay one half thereof. Subsequently, an amended and supplemental award was filed by the arbitrators, making minor changes in the original award and assessing all the additional costs against appellant. After a motion by appellant to vacate, modify and correct the award had been denied by the superior court, a petition by respondent for confirmation of the amended and supplemental award was granted. This appeal is from the judgment, the order confirming the award and the order denying the motion to modify the award.

Appellant contends that the lower court should have granted the motion to vacate, modify and correct the award because (1) the arbitrators were guilty of misbehavior by which the rights of appellant were prejudiced (Code Civ. Proc., § 1288(c)), and (2) the arbitrators so exceeded their powers and so imperfectly executed them that a mutual, final and definite award was not made. (Code Civ. Proc., § 1288(d).)

To dwell upon the numerous arguments made to the arbitrators by the parties would add no factual content of value to this discussion. Neither is there anything of value in the contentions made to the court below. Suffice it to say that on February 29, 1952, respondent moved for a confirmation of the final award of the arbitrators which was done by judgment in March, 1952. More arguments, motions and modifications followed and final judgment was entered, ordering appellant to pay the balance fixed by the award, costs and fees of the arbitrators.

*494 Every reasonable intendment will be indulged to give effect to arbitration proceedings. An award made upon an unqualified submission will not be set aside on the ground that it is contrary to law unless the error appears on the face of the award and causes substantial injustice. (Utah Const. Co. v. Western Pac. R. Co., 174 Cal. 156, 159 [162 P. 631]; Popcorn Equipment Co. v. Page, 92 Cal.App.2d 448, 451 [207 P.2d 647].) The award of the arbitrators is sufficient if it is clear and precise and gives the result of the accounts between the parties without detailing the process by which the result was reached. (Carsley v. Lindsay, 14 Cal. 390, 394; Popcorn Equipment Co. v. Page, supra.) The merits of the controversy between the parties, the nature and sufficiency of the evidence, and the credibility and good faith of the parties, in the absence of corruption, fraud or undue means in obtaining an award are not matter for judicial review. (Pacific Vegetable Oil Corp. v. C. S. T., Ltd., 29 Cal.2d 228, 233, 238 [174 P.2d 441].)

Appellant contends that by reason of the fact that “the award as made by the arbitrators is on its face inconsistent with the facts found and contrary to all the evidence, the action of the arbitrators becomes arbitrary and oppressive and constitutes ‘misbehavior,’ ‘excess of powers,’ or an imperfect execution of such powers.” In support of this contention, appellant enumerates six specific items, despite the fact that no record was made of the arbitration proceedings.

(1) The arbitrators found that the factory floor was not constructed according to the specifications and awarded $500 as damages to appellant. Appellant insists that it presented evidence of damages to the extent of $2,000 and argues that the failure of the arbitrators to find such to be a fact is misbehavior. The measure of damages is a question of fact for the arbitrators in the absence of a contractual provision therefor. In determining the measure and extent of the damage they are not restricted to a consideration of the evidence presented to them, but may inform themselves further from private investigation and personal experience. (Sapp v. Barenfeld, 34 Cal.2d 515, 521 [212 P.2d 233].)

(2) Under the terms of the contract, respondent was to furnish receipted bills covering work done and materials furnished. Appellant argues that an award to the builder by the arbitrators without the production of all the bills is an act in excess of their authority. Such is not the fact. In the absence of a record or detailed findings, it must be presumed *495 that the arbitrators included in their award any damage to appellant resulting from respondent’s breach of this portion of the contract.

(3) The work to be done, as detailed in the contract, included “relocating garage and building necessary slab for same.” The arbitrators awarded to respondent as an extra for “work performed on storage shed after relocating same, $900. ’ ’ Appellant insists that the storage shed and the garage were the same structure and that therefore this work was included in the contract price. Also, it designates such award an act in excess of authority and misbehavior for failure to follow the contract. But it should be noted that the award is for extra work performed after the relocation referred to in the contract was completed.

(4) Appellant claimed damages for delay in the completion of the building, resulting from the fact that appellant removed and replaced the floor of the building. The award specifically disallowed this claim. Presumptively the arbitrators found that the delay was not caused by respondent, and this conclusion is not open for consideration on appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Puerto Rico Housing Authority v. Superior Court
82 P.R. 333 (Supreme Court of Puerto Rico, 1961)
Autoridad Sobre Hogares v. Tribunal Superior de Puerto Rico
82 P.R. Dec. 344 (Supreme Court of Puerto Rico, 1961)
William B. Logan & Associates v. Monogram Precision Industries, Inc.
184 Cal. App. 2d 12 (California Court of Appeal, 1960)
Lauria v. Soriano
180 Cal. App. 2d 163 (California Court of Appeal, 1960)
Ulene v. Murray Millman of California, Inc.
346 P.2d 494 (California Court of Appeal, 1959)
Straus v. North Hollywood Hospital, Inc.
309 P.2d 541 (California Court of Appeal, 1957)
Griffith Co. v. San Diego College for Women
289 P.2d 476 (California Supreme Court, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
263 P.2d 445, 121 Cal. App. 2d 491, 1953 Cal. App. LEXIS 1380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sampson-motors-inc-v-roland-calctapp-1953.