Samoa Development, Inc. v. American Samoa Power Authority

5 Am. Samoa 3d 172
CourtHigh Court of American Samoa
DecidedAugust 24, 2001
DocketCA No. 146-95
StatusPublished

This text of 5 Am. Samoa 3d 172 (Samoa Development, Inc. v. American Samoa Power Authority) is published on Counsel Stack Legal Research, covering High Court of American Samoa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Samoa Development, Inc. v. American Samoa Power Authority, 5 Am. Samoa 3d 172 (amsamoa 2001).

Opinion

OPINION AND ORDER

Plaintiff Samoa Development Inc. (“Samoa Development”) brings this suit for damages against defendants American Samoa Power Authority (“ASPA”) and Fred Pele (“Pele”) for wrongfully cancelling an award of procurement. ASPA and Pele contend their act was justified by the explicit terms governing the award, specifically those applicable to contractors’ bonds. The case proceeded to trial on November 28, 2000. Both counsel were present.

Facts

On June 8, 1995, the Office of Procurement of the American Samoa Government issued an Invitation for Bids for Project #AS-NH-001(29), regarding striping, signing and delineation of portions of the Territorial Route 1 highway of American Samoa (“the striping project”). ASPA was, at the time, engaged in public highway construction and maintenance. ASPA’s Executive Director Abe Malae (“Malae”) was, as ASPA’s chief procurement officer, ultimately responsible for the selection of outside contractors procured for highway projects. Pele, the [175]*175general manager of ASPA’s Civil/Highway Division, had been delegated authority for administration of the performance of contracts for such projects, including the contract in question. He also had at least apparent authority to conduct the procurement process for the striping project.

The specifications governing the striping project, made available to all bidders, incorporated the Hawaii Standard Specifications for Road and Bridge Construction and explicitly substituted terms. Haw. Dep’t of Transp., Highways Div., Haw. Standard Specifications. Three provisions, in particular, are relevant in this case. Section 103.04 of the specifications governs cancellation of the award, and reserves for the ASG’s Department of Public Works “the right to cancel the award of any contract at any time before the execution of said contract by all parties without any liability to the awarded and to any other bidder.” Id. at § 103.04 (emphasis added). Section 103.06 requires contractor’s bonds. It states, specifically, “[a]t the time of the execution of the contract, the successful bidder shall file a ‘Performance Bond’ and a ‘Payment Bond.’” Id. at § 103.06. Finally, Section 103.08 provides that failure to execute the contract and file acceptable bonds within 10 days after the award of the contract, or within such further time as the Director may allow, shall be cause for the cancellation of the award.” Id. at § 103.08. Such specifications are authorized by A.S.C.A. § 15.0102 (12).2

On July 11, 1995, the Source Evaluation Board (“SEB”) for this procurement met, opened the bids, and found Samoa Development to be, at $182,951.00, the lowest responsive bidder.3 In second place was Island Builders, Inc. (“Island Builders”), at $193,034.69. The U.S. Department of Transportation, Federal Highway Administration (“FHWA”), which provided funding for the striping project, was notified of the SEB’s findings by ASPA’s letter of July 21, 1995, signed by Pele. FHWA concurred in the award to Samoa Development on August 1, 1995. A notice of award was issued to Samoa Development on August 9, 1995, in a letter from ASPA, signed by Malae and Pele, and addressed to Samoa Development’s president Falema'o Pili (“Pili”). The letter requests that Samoa Development “provide originals of the Performance [176]*176Bond for 100% of the contract amount, Labor and Material Payment Bond for 100% of the contract amount and proof of insurance coverage” ■within 14 days upon receipt of the notice. The notice was marked received on August 11, 1995.

On August 23, 1995, two days before the deadline to acquire the bonds, Samoa Development sent a letter, signed by Pili, to ASPA acknowledging the “conditional awarding” of the striping contract to it, and asking for an extension of 15 days to acquire the bonds. ASPA granted to Samoa Development an extension within which to provide performance and payment bonds. There is, however,' no express evidence as to the actual number of days given in the extension itself, ASPA’s notice to Samoa Development of its withdrawal of the striping project award, dated September 13, 1995, signed by Pele for Malae and ASPA, confirms an extension of 19 days. The relevant portion states, “You have been extended nineteen (19) more calendar days, in addition to the addition to the original fourteen (14) calendar days to post the bonds but to no avail.” However, a ASPA’s later letter of October 6, 1995, again signed by Pele for Malae and ASPA, written with the purpose of asking Samoa Development to pick up the original bonds, states: “It is very unfortunate that your company had failed to submit all necessary bonds in time even after extending the period for further [sic] 14 days. ASPA has been awaiting [sic] 5 days more than the deadline to inform you the withdrawal [sic] of this project.”

We find that an extension of 14 days was given. However, we also find that ASPA and Pele unofficially postponed termination of the contract award for another five days and thus afforded Samoa Development further time to provide the required bonds. This action was consistent with ASPA’s customary practice. In 1995, ASPA was flexible in its deadlines regarding the accepting and filing of bonds as a matter of practical necessity in the procurement of local contractors to perform public construction projects that required bonding. As small businesses, local contracting firms were unaccustomed to bonding requirements for federally-funded projects and often encountered financial and logistical problems in routinely acquiring contractors’ bonds.

Samoa Development did, in good faith, acquire the appropriate bonds. On September 8, 1995, ASPA received from Kalilimoku Hunt, a general agent of the American National Insurance Co., a letter stating that “all of the requirements to consummate the bond” for the striping project were received by the Hunt/Linden Agency, and were then submitted to the National Casualty Insurance Co. It further stated: “[w]e have indications from the Insurance Company that the bond should be issued by Wednesday 13, 1995 [sic].” Samoa Development received further confirmation of the processing of its bond on September 11, 1995, in a [177]*177letter from Robert Style, Regional Director of Broker’s Network, stating, “we are in the process of procuring bond(s) in the amount $182,951.00.”

On September 12, 1995, Samoa Development received a hand-scrawled fax from an “Anita” at Specialty Bonds and Insurance, Co. to a “Kauli,” with the subject line “Re: Samoa Development,” the body of which states:

WE HAVE APPROVAL TO ISSUE BOND FOR CAPTIONED. PLZ [sic] HAVE 61A EXECUTED AND FAX’D [sic] BACK. RATE WILL BE 390, SO WE WILL NEED FAX’D [sic] COPY OF CHECK IN AMOUNT OF $5,489.00. THX! [sic],

Samoa Development apprised Pele of the authorization that day, and on September 13, 1995, sent to ASPA what Pili described in a cover letter to be “the documents which indicates [sic] the issuing of our Bond. The Underwriter is sending our Bond in the overnight pouch on Friday’s flight.”

Despite these communications, in a letter dated and faxed on September 13, 1995, signed by Pele only, without a signature above the signature line for Malae, ASPA withdrew the contract from Samoa Development “because of failure to post the required performance and the payment bonds.” Pili immediately responded with a letter asking for reconsideration “on the grounds that a letter of intent was included to ensure the forthcoming issuance of the Bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Robertson
266 U.S. 243 (Supreme Court, 1924)
Hunt Ltd. v. Lifschultz Fast Freight, Inc.
889 F.2d 1274 (Second Circuit, 1989)
State v. Johnson
779 P.2d 778 (Alaska Supreme Court, 1989)
Schull Construction Co. v. Board of Regents of Education
113 N.W.2d 663 (South Dakota Supreme Court, 1962)
McRae v. Farquhar Albright Company
269 S.W. 375 (Supreme Court of Arkansas, 1925)
Atlantic Sea-Con. Ltd. v. Robert Dann Co.
560 A.2d 592 (Court of Special Appeals of Maryland, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
5 Am. Samoa 3d 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/samoa-development-inc-v-american-samoa-power-authority-amsamoa-2001.