Sam Parish Construction Co. v. Cities Service Pipeline Co.

254 So. 2d 73, 1971 La. App. LEXIS 5500
CourtLouisiana Court of Appeal
DecidedOctober 22, 1971
DocketNo. 3576
StatusPublished
Cited by4 cases

This text of 254 So. 2d 73 (Sam Parish Construction Co. v. Cities Service Pipeline Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sam Parish Construction Co. v. Cities Service Pipeline Co., 254 So. 2d 73, 1971 La. App. LEXIS 5500 (La. Ct. App. 1971).

Opinion

MILLER, Judge.

Plaintiff, Sam Parish Construction Company sued Cities Service Pipeline Company to recover the sum of $118,328.16 allegedly due plaintiff under a contract for the construction of a tank car repair shop on defendant’s premises in Calcasieu Parish. Defendant denied it owed plaintiff any sum whatsoever and filed a reconventional demand for damages alleging plaintiff failed to complete its contract. Judgment was rendered for plaintiff in the sum of $113,670.94 and defendant’s reconventional demand was rejected. Defendant has appealed. We affirm.

The primary issue to be decided is whether the parties entered into a straight cost-plus contract or a cost-plus contract with a stipulated maximum price. Plaintiff contends the parties entered into a cost-plus contract and that defendant has failed to pay the sum of $118,328.16, representing the balance owed on the contract upon which defendant has already paid the sum of $229,314.69. Defendant denies it owes plaintiff any amount and contends that the parties agreed to a cost-plus contract with a maximum cost figure of $225,313.00 and that it has paid plaintiff sums in excess of the maximum price. Defendant also filed a reconventional demand for damages in the total sum of $55,584.40, representing payment in excess of the alleged maximum contract price, the cost for completing the work covered by the contract, and the cost of stand-by salaries paid to Cities Service personnel employed to operate the tank car repair shop.

During February and March of 1968, representatives of defendant Cities Service and Sam Parish, president of the plaintiff corporation, began negotiations on the tank car repair shop. On March 15, 1968 plain[75]*75tiff submitted an estimate of costs for doing the work in the sum of $206,624.00. Apparently no further move was made by either party on this bid. By letter dated May 3, 1968 defendant sent a set of specifications to plaintiff and requested that plaintiff furnish a “turn key proposal” for the work based on the enclosed specifications. The letter stated that defendant desired to begin construction on May 13, 1968 with an expected completion date of August 30, 1968. On May 11, 1968 plaintiff wrote to Cities Service proposing to build a tank car repair shop on a time and materials basis, “per our conference, telephone conversations, and preliminary drawings at an outside figure of two hundred twenty-five thousand three hundred fifty-nine and no one hundred ($225,359.00) dollars.” After the letter was received by Cities Service, plaintiff was contacted by telephone by Larry Moore, Cities Service Engineer, who informed plaintiff to begin work on the site on May 16, 1968.

On May 29, 1968 defendant sent a purchase order to plaintiff wherein it stated:

“Furnish all labor, tools, equipment, supervision, vehicles, and material (except material being furnished by Cities Service) to build a tank car repair shop in West Lake Charles, Louisiana, as per Cities Service specifications. On a time and material basis, per letter outlining terms of cost-plus work dated 5/20/68, per labor rates dated 5/21/68, and per letter stating maximum contract price dated 5/11/68. Contract payments are not to exceed $225,359.00.”

The purchase order was received by plaintiff on May 31, 1968. On June 4, 1968 Sam Parish sent a letter to defendant taking exceptions to the purchase order wherein he stated:

“There are many things mentioned in the specifications such as painting, piping, electrical work, etc., which we do not know and still do not know the quantity of work to be done.
“For the above reasons we do not feel that it would be fair to either party to tie our purchase order down to this set of specifications.
“2. Contract payments are not to exceed Two Hundred Twenty-Five Thousand Three Hundred Fifty-Nine and No/100 ($225,359.00) Dollars — this estimate is based on the quantity of work as we understood it from our conference, telephone conversations and preliminary drawings at the time our quotation was made.
“Any extra work that was not contemplated at the time the above quotation was made, such as the extra clearing, extra excavation, extra fill to be placed in the railroad bed and the cost of disposing of the three thousand yards of dirt, trees, stumps, etc., which was excavated out of the railroad bed (original plan was to reuse this dirt as fill in the railroad bed) will not be figured in the $225,359.00, which is our outside figure to build a Tank Car Repair Shop in West Lake Charles, Louisiana.”

Defendant did not reply to this letter.

In accordance with the arrangement of the parties, plaintiff rendered weekly progress reports to defendant on the construction and submitted itemized billings for payment every two weeks. As of October 18, 1968 plaintiff had rendered ten itemized billings to defendant which totaled $214,563.60, all of which were paid by the defendant. On November 4, 1968 plaintiff rendered its eleventh itemized billing for $75,311.01. The defendant refused to pay this bill and the subsequent bills of plaintiff except for the sum of $15,621.72 paid directly to two subcontractors for the benefit of plaintiff. At that point defendant had paid directly to plaintiff or for the account of plaintiff the sum of $230,185.32. Based upon its contention that the maximum fee on the job was $225,359.00 defendant refused to pay any further sums. Defendant then informed plaintiff to cease work on the job effective November 12, [76]*761968 which resulted in plaintiff moving from the job site a day or two later.

The trial judge concluded that the parties entered into a straight cost-plus contract. In his opinion, the negotiations reflected that the parties never consummated any agreement as to an outside or maximum figure. In a thorough analysis of the problem, the trial court reasoned as follows :

“It is noted that the proposal of May 11, 1968, was not addressed to the defendant, but to an address, marked for attention of Mr. Zieba, and serves only to emphasize the sketchy basis of the agreement between the parties. The proposal to build the repair shop at an ‘outside figure’ of $225,359.00 is stated to be on a ‘time and materials basis, per our conference, telephone conversations and preliminary drawings.’ There is no evidence as to what was developed at ‘our conference’ or in ‘telephone conversations’, and the parties are in disagreement as to the nature of the ‘preliminary drawings’ on which the proposal was made. The purchase order, dated May 29, 1968, and received by the plaintiff May 31, 1968, to which certain exceptions were taken in a letter dated June 4, 1968, referred to ‘Cities Service specifications’, which were not mentioned in the proposal of plaintiff referred to above. The letter of plaintiff dated May 11, 1968, was incorporated in the purchase order by reference, as were other letters annexed thereto. It appears that the defendant found it necessary to deliver its purchase order, purporting to set forth more fully the terms of the agreement between the parties and, accordingly, it would seem that the verbal telephone notice of Larry Moore to Mr. Parish to proceed with the work after his proposal of May 11, 1968, was not to be considered as a firm acceptance of the May 11th letter as setting forth the contract between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ceco Corp. v. Mid-Gulf Construction, Inc.
396 So. 2d 474 (Louisiana Court of Appeal, 1981)
Planning Systems Corp. v. Murrell
374 So. 2d 719 (Louisiana Court of Appeal, 1979)
Duet v. Kiffe
269 So. 2d 534 (Louisiana Court of Appeal, 1972)
Sam Parish Construction Co. v. Cities Service Pipeline Co.
255 So. 2d 773 (Supreme Court of Louisiana, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
254 So. 2d 73, 1971 La. App. LEXIS 5500, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sam-parish-construction-co-v-cities-service-pipeline-co-lactapp-1971.