Ceco Corp. v. Mid-Gulf Construction, Inc.

396 So. 2d 474, 1981 La. App. LEXIS 3680
CourtLouisiana Court of Appeal
DecidedMarch 10, 1981
DocketNo. 11721
StatusPublished
Cited by1 cases

This text of 396 So. 2d 474 (Ceco Corp. v. Mid-Gulf Construction, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ceco Corp. v. Mid-Gulf Construction, Inc., 396 So. 2d 474, 1981 La. App. LEXIS 3680 (La. Ct. App. 1981).

Opinion

GULOTTA, Judge.

In this construction contract case, plaintiff, a steel supplier, claims entitlement to $24,158.61, the amount of escalated costs of reinforcing steel, welded wire fabric and other steel materials furnished and delivered by plaintiff to defendant for the construction of a courthouse and jail facility in St. Charles Parish, in accordance with a contract entered into between the parties on April 19, 1974.

The trial judge in the judgment dismissing plaintiff’s suit stated that Ceco “... has failed to carry the burden of proof required . . .. ” Plaintiff appeals. We reverse.

In response to Mid-Gulf Construction, Inc.’s April 19, 1974 purchase order, Ceco Corporation agreed to deliver to Mid-Gulf certain steel materials in connection with the construction job at a cost of $194,883.52. The agreement provided that all materials would be shipped to arrive at the job by August 1, 1974. Conditions attached to the agreement and around which this dispute revolved, are as follows:

“All reinforcing steel prices listed herein are firm until August 12,1974, prices for materials shipped after that date will be increased a maximum of $25.00/ton for each 6-month period after August 12, 1974.
In the event that Ceco’s suppliers for Mesh and Rebar accessories increase their price to Ceco after February 12, 1974, material prices shall be increased by the actual amount of the increase.”

Also included in the purchase order is a recitation that:

“All materials will be delivered to the Job Site by the Seller’s Truck in the sequence and quantities required.”

Steel was first delivered on June 13 and 14, 1974, and then periodically as requested [476]*476by Mid-Gulf and required on the construction job. Invoices were sent to Mid-Gulf in connection with each delivery. On September 9, 1974, defendant was notified by the district manager of Ceco that in accordance with the terms of the contract the escalation clause had become effective and the remaining steel shipment would be increased by the sum of $25.00 per ton.

In accordance with that letter, a September 27, 1974 invoice reflected the escalation increase. This increase was also reflected in subsequent invoices dated October 22, 1974, November 12, 1974, December 4, 1974, February 24, 1975, two invoices dated February 25,1975, March 3,1975, May 28,1975, June 16, 1975, June 19, 1975, and June 27, 1975. These escalation costs as reflected in the invoices were paid without any protest from Mid-Gulf. However, the sum of $24,-158.61, the total amount of the accumulated escalation costs charged to Mid-Gulf and now the subject of this suit, was withheld by Mid-Gulf from final payment, to Ceco under the contract.

According to plaintiff, although the purchase order specified that all materials were to be shipped for arrival at the job by August 1, 1974, the delivery dates were modified by Mid-Gulf as is customary in construction contracts involving large shipments. Plaintiff claims that requests for delivery were made by the Mid-Gulf superintendent on the job as required for use in the construction. Supportive of this position was a letter dated December 4, 1974 and addressed to Mid-Gulf by Ceco which states that confirmation was being made of a telephone conversation with Mid-Gulf’s assistant job superintendent rescheduling reinforcing steel shipments as per the job superintendent’s request.

Plaintiff also contends that Mid-Gulf’s silence and inaction to the invoice escalation charges and indeed payment of the invoice amount including the specific escalation charges is an implied assent to the contract modification and assessment of those charges. Plaintiff relies in support of this contention on LSA-C.C. arts. 1811 and 1816.1 We agree.

Robert Krejcu, Ceco’s district manager at the time the contract was entered into with defendant, testified that reinforcement steel is normally scheduled for shipment to the job site between the job superintendent of the construction contractor and Ceco’s chief draftsman who handles the details and scheduling. These shipments are usually scheduled when required in different phases of construction. When and where steel is delivered, according to Krejcu, are controlled by the general contractor’s general superintendent on the job, in this case, Mid-Gulf’s superintendent. Krejcu pointed out the first requested delivery by Mid-Gulf was on June 15, 1974 and the next request was made on August 30, 1974. The steel deliveries were made as requested by Mid-Gulf. Krejcu further supported Ceco’s claim that Mid-Gulf was notified after August 12, 1974 that the escalation clause in the contract was triggered by the later delivery and no exception was taken or [477]*477objection made to that communication. Krejcu also pointed out that the invoices including the escalation clauses were paid by Mid-Gulf without objection. The shipments were not made prior to August 1, or August 12, according to Krejcu because they had not been requested. Delivery could have been made at any time that delivery had been requested. As late as June 6,1975, Ceco was still ordering steel to be fabricated in Houston for use on the job.

Eric Berger, Ceco’s superintendent and chief draftsman on the job in 1974 who handled the scheduling of shipments of steel, stated that the steel deliveries were made when requested by Mid-Gulf’s job superintendent, Al Schreffner. This witness, to a large extent, corroborated Krejcu’s testimony. He additionally testified that he had no recollection of any request for a delay in delivery made by Mid-Gulf prior to August 12, 1974.

Thomas B. Sellers, the president of the sub-contractor responsible for placement of the delivered steel on the courthouse and jail facility, testified that other than the initial delivery at no time was there an insufficiency of steel on the job site, but rather “more than enough steel to do the work.” He emphasized that there was a plentiful supply of steel on hand. On occasions he indicated that steel was being delivered to the site in amounts more than could be used at the time. No delays, according to this witness, were caused in delivery by Ceco. Sellers at first testified that if all of the steel required in the entire construction had been delivered prior to August 1 it could have been stacked on the job site in such a way as to permit its use as required in the development of the construction job. He later stated, however, that there was not enough space on the job site to store all of the steel required in the entire job. This sub-contractor testified that he was on the job site just about every day of construction and that it was not customaiy in construction jobs such as this one that all steel would be delivered to the job site at one time.

J. Michael Dixon, the department manager for Mid-Gulf at the time the construction job was in progress, testified that he had participated only “peripherally” in the original purchase order between Mid-Gulf and Ceco in April, 1974. His predecessor at Mid-Gulf, Cory Pittman, had handled the job until December 15,1974 and it had been Pittman’s original responsibility for the scheduling of delivery of the materials to the job site. Dixon testified that he had commenced work on the job in November, 1974. Made aware in November of the escalation charges being made, Dixon instructed that those charges would not be paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taita Chemical Co. v. Westlake Styrene Corp.
246 F.3d 377 (Fifth Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
396 So. 2d 474, 1981 La. App. LEXIS 3680, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ceco-corp-v-mid-gulf-construction-inc-lactapp-1981.