Safeway, Inc. v. Nordic PCL Construction, Inc.

312 P.3d 1224, 130 Haw. 517, 2013 WL 5823693, 2013 Haw. App. LEXIS 626
Hawaii Intermediate Court of Appeals·Decided October 30, 2013·No. No. CAAP-10-0000046·Published·Cited by 5 cases

Opinion

Opinion of the Court by

REIFURTH, J.

Defendant-Appellant Nordic PCL Construction, Inc. (“Nordic”) seeks to enforce a contractual provision requiring arbitration of disputes relating to performance of three construction contracts entered into between Nordic and Plaintiff-Appellee Safeway Inc. (“Safeway”) for the construction of a Safeway Store and retail shops on Kapahulu Avenue. Safeway contends that a set of supplemental conditions formed part of the contract for the project, and that those conditions expressly deleted the arbitration clause. The Circuit Court of the First Circuit (“Circuit Court”)1 declined to enforce the arbitration provision, concluding that “the agreement itself is ambiguous[.]”

Nordic appeals from the July 1, 2010 order denying its application to compel arbitration, and the September 23, 2010 order denying its motion to clarify, amend, or reconsider the order denying the application to compel arbitration. Nordic alleges that the Circuit Court erred by (1) concluding in those orders that the supplementary conditions were part of the construction contract, and (2) denying Nordic’s request for an evidentiary hearing.

We concur with the Circuit Court that there were genuine issues of material fact pertaining to the existence of an agreement to arbitrate, but conclude that the court should have held, and must now hold, an evidentiary hearing to promptly determine those issues.

I. BACKGROUND

In 2006, Safeway engaged Nordic as the prime general contractor for the construction of the Safeway Store #2747, retail shops, and related site improvements on Kapahulu Avenue, in Honolulu, Hawai'i (the “Project”). Shortly after the store opened, a waterproofing membrane installed on the parking deck, situated above the store, began to fail and water leaked into the store. Eventually, the parties to this appeal, as well as several others, sought to litigate responsibility for the failure as well as claims to monies withheld by Safeway.

A. Nordic Receives the Bid and Contract Documents

In early 2006, Safeway, in the course of soliciting general contractors for the Project’s construction, had its architect, Benner Stange Associates Architects, Inc. (“Ben-ner”), assemble a project manual (“Project Manual”), consisting of standard forms prepared by Safeway and including a list of supplementary conditions (“Supplementary Conditions”), for distribution to prospective general contractors.2 On or about February [521]*5216, 2006, Benner sent a copy of the Project Manual to Glen Kaneshige, then-President of Nordic.

Mr. Kaneshige described the section of the Project Manual entitled Bid Form and Supplements as including, among other things, “an unsigned eight-page document named ‘Construction Contract,’” (“Initial Construction Contract”), “a nine-page document named ‘General Conditions,’ ” (“General Conditions”), and the Supplementary Conditions. According to Mr. Kaneshige, “Nordic and Safeway never negotiated the terms of any of these documents, and they never became a part of the Parties’ Contracts.”

On April 10, 2006, Safeway notified Nordic that Nordic had been selected as the Project’s general contractor. Safeway then provided Nordic with a set of documents, including a modified version of the Initial Construction Contract (“Modified Initial Construction Contract”) and a document titled AIA Document A201-1997: General Conditions of the Contract for Construction with many edits, either by strike-through text (apparently deletions) or underlined text (apparently additions) (“A201 Document”). Safeway provided further copies of the Project Manual to Nordic in May and June 2006.

Final drafts of three contract documents, each entitled AIA Document A101-1997: Standard Form of Agreement Between Owner and Contractor were sent to Nordic by Safeway on or about October 2, 2006. Each contract corresponded to one of three Project components — construction of the store site (“Site Contract”), the store itself (“Store Contract”), and associated retail shops (“Shops Contract”) (collectively, the “A101 Documents”). Both the A101 Documents and the A201 Document were derived from form contracts commonly used in the construction industry. The final drafts of the A101 and A201 Documents apparently replaced the Initial and Modified Initial Construction Contracts. On November 17, 2006, Nordic sent fully executed copies of the A101 Documents to Safeway.

B. The Contract Documents

The A101 Documents are the controlling contract documents; they also enumerate the documents that comprise the whole of the contract documents, including by reference to or incorporation of those other documents. Although the A201 Document, which contains an arbitration provision, is referenced in the A101 Documents, the parties disagree over whether the A101 Documents also incorporate the Supplementary Conditions, which purport to delete the arbitration provision. In relevant part, each of the three A101 Documents begins:

ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement; these form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein.... An enumeration of the Contract Documents, other than Modifications, appears in Article 8.

Article 8 in each of the three A101 Documents, entitled Enumeration of Contract Documents, purports to enumerate the specific documents that comprise the Contract Documents. In the Store Contract, Article 8 provides the following:3

ARTICLE 8 ENUMERATION OF CONTRACT DOCUMENTS
§ 8.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated as follows:
[[Image here]]
§ 8.1.3 The Supplementary and other Conditions of the Contract are those contained in the Project Manual dated, and are as follows:
Document Title Pages
[522] [[Image here]]
§ 8.1.4 The Specifications are those contained in the Project Manual dated as in Section 8.1.3, and are as follows: (Either list the Specifications here or refer to an exhibit attached to this Agreement)
Title of Specifications exhibit: Exhibit A attached hereto and made a part hereof.
[[Image here]]
§ 8.1.7 Other documents, if any, forming part of the Contract Documents are as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Safeway, Inc. v. Nordic PCL Construction, Inc., 312 P.3d 1224, 130 Haw. 517, 2013 WL 5823693, 2013 Haw. App. LEXIS 626 (hawapp 2013).

312 P.3d 1224 (Safeway, Inc. v. Nordic PCL Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Napuaowailupe v. Blue Tile Beach House
547 P.3d 1189 (Hawaii Intermediate Court of Appeals, 2024)
Akana v. Hawai'i State Ethics Commission
542 P.3d 291 (Hawaii Intermediate Court of Appeals, 2024)
Barranco v. 3D Sys. Corp.
307 F. Supp. 3d 1075 (D. Hawaii, 2018)