Safe Environment, Inc. v. Pollution Control Hearings Board

841 P.2d 1327, 68 Wash. App. 177, 1992 Wash. App. LEXIS 497
CourtCourt of Appeals of Washington
DecidedDecember 28, 1992
DocketNo. 29300-1-I
StatusPublished
Cited by3 cases

This text of 841 P.2d 1327 (Safe Environment, Inc. v. Pollution Control Hearings Board) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Safe Environment, Inc. v. Pollution Control Hearings Board, 841 P.2d 1327, 68 Wash. App. 177, 1992 Wash. App. LEXIS 497 (Wash. Ct. App. 1992).

Opinion

Coleman, J.

The Puget Sound Air Pollution Control Agency (PSAPCA) and the Pollution Control Hearings Board (PCHB) appeal the Superior Court's judgment entered September 4, 1991, dismissing the civil penalty against Safe Environment, Inc. (SEI). PSAPCA and PCHB argue that the Superior Court incorrectly construed PSAPCA regulation 1, article 10, section 10.04 as requiring an asbestos contractor to dispose only of asbestos which the contractor itself removed during the process of demolition. We reverse.

SEI was hired by Guarino Excavating, Inc., to remove asbestos from several single-family homes prior to demoli[179]*179tion. Before giving Guarino Excavating an estimate, SEI visited the house at 7505 219th S.W. in Edmonds. The house appeared to have been vandalized. Windows and doors had been removed, and asbestos siding was scattered around the site.

SEI filed with PSAPCA a notice of intent to remove asbestos for a demolition project. The completion date of the project was fisted as April 27, 1990. On April 26, 1990, PSAPCA conducted a routine inspection of the Edmonds property. Although no one was at the site, the inspector found tools and other signs that work was in progress. On April 30, 1990, the inspector returned to the property. The tools were gone, indicating that SEI had finished the project. However, the inspector found several small pieces of dry cement asbestos board (CAB) on the property.

PSAPCA issued SEI a notice and order of civil penalty for violation of its asbestos handling regulations. Specifically, PSAPCA alleged: (1) "failure to adequately wet asbestos materials that have been removed or stripped to ensure that they remain wet until they are collected for disposal"; (2) "failure to collect asbestos materials that have been removed or stripped for disposal at the end of each working day"; and (3) "failure to contain asbestos materials that have been removed or stripped in a controlled area at all times until transported to a waste disposal site." PSAPCA imposed a fine of $1,000. SEI appealed the penalty to the PCHB, which affirmed the violations but reduced the penalty from $1,000 to $500, with $250 suspended provided there were no air pollution violations for 3 years. The PCHB stated:

In their "work on an asbestos project" . . . they left behind asbestos material that was not wet when PSAPCA discovered it, nor had it been collected or contained in a control [sic] area. We conclude SEI violated Sections 10.04(b)(2)(iii)(A) and (B) and (C) when they concluded the job and left asbestos material on the ground in the condition it was subsequently discovered.

SEI appealed the order to the Superior Court, which vacated the order and dismissed the penalty. PSAPCA appeals.

[180]*180The sole issue on appeal is whether a contractor who was hired to remove asbestos from a building is strictly liable for any asbestos found on the property prior to demolition. PSAPCA regulation 1, art. 10, § 10.04(b) provides:

(b) It shall be unlawful for any person to cause or allow the removal or encapsulation of asbestos material or to work on an asbestos project unless:
(2) The following procedures are employed:
(iii) Asbestos materials that have been removed or stripped shall be:
(A) Adequately wetted to ensure that they remain wet until they are collected for disposal; and
(B) Collected for disposal at the end of each working day; and
(C) Contained in a controlled area at all times until transported to a waste disposal site[.]

This section presents two alternatives: It is unlawful (1) to cause or allow asbestos removal or encapsulation in violation of the section, or (2) to work on an asbestos project in violation of the section.

Although PSAPCA initially charged SEI under the "cause or allow" part of the section, the PCHB affirmed the penalty on the basis that SEI "worked on an asbestos project" in violation of the section. An "asbestos project" is defined in the regulations as:

[T]he construction, demolition, repair, maintenance, or renovation of any public or private building or mechanical piping equipment or systems.involving the demolition, removed, encapsulation, salvage, or disposal of the material releasing, or likely to release, asbestos fibers into the air.

PSAPCA regulation 1, art. 10, § 10.02(f). The definition of "asbestos removal” is "to take out or strip off asbestos materials." PSAPCA regulation 1, art. 10, § 10.02(g).

A

Standard of Review

The Administrative Procedure Act (APA) defines the scope of judicial review of PCHB decisions. The APA provides:

[181]*181The court shall grant relief from an agency order in an adjudicative proceeding only if it determines that:
(d) The agency has erroneously interpreted or applied the law;
(e) The order is not supported by evidence that is substantial when viewed in light of the whole record before the court, which includes the agency record for judicial review, supplemented by any additional evidence received by the court under this chapter . . ..

RCW 34.05.570(3)(d), (e). In this case, the Superior Court reversed the PCHB based on subsections (d) and (e) above.

When reviewing questions of law, the court is "entitled to 'substitute its determination for that of the agency, although the agency's determination is entitled to substantial weight.'" Asarco, Inc. v. Puget Sound Air Pollution Control Agency, 112 Wn.2d 314, 317, 771 P.2d 335 (1989) (quoting Renton Educ. Ass'n v. Public Empl. Relations Comm'n, 101 Wn.2d 435, 441, 680 P.2d 40 (1984)). In this case, the PCHB determined that, as a matter of law, SEI was responsible for any asbestos material at the site, "regardless of who may initially have caused a piece of asbestos to he at a particular spot." The Superior Court found that the PCHB erroneously interpreted the law as imposing strict liability on contractors and that there was insufficient evidence that the asbestos found on the site came from SEI's removal project.

B

Construction of the Term "Asbestos Project"

SEI argues that it cannot be charged with improper handling while working on an asbestos project, as defined, supra, because demolition of the Edmonds house had not begun when the inspector found the asbestos. According to SEI, the regulation requires an ongoing demolition project "where asbestos material was either being released or was likely to be released into the air." (Footnote omitted.) Brief of Respondent, at 21. To support this contention, SEI cites United States v. Syracuse Univ., 32 Env't Rep. Cas. 1535 (N.D.N.Y. 1990), in which the court construed a regulation [182]*182requiring removal of "friable asbestos from a facility being demolished or renovated before any wrecking or dismantling that would break up the materials. . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William Dickson Co. v. Puget Sound Air Pollution Control Agency
914 P.2d 750 (Court of Appeals of Washington, 1996)
Espinosa v. Roswell Tower, Inc.
910 P.2d 940 (New Mexico Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
841 P.2d 1327, 68 Wash. App. 177, 1992 Wash. App. LEXIS 497, Counsel Stack Legal Research, https://law.counselstack.com/opinion/safe-environment-inc-v-pollution-control-hearings-board-washctapp-1992.