Sabre Indus v. Module X Solutions

CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 2, 2021
Docket19-30887
StatusUnpublished

This text of Sabre Indus v. Module X Solutions (Sabre Indus v. Module X Solutions) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sabre Indus v. Module X Solutions, (5th Cir. 2021).

Opinion

Case: 19-30887 Document: 00515730446 Page: 1 Date Filed: 02/02/2021

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

FILED February 2, 2021 No. 19-30887 Lyle W. Cayce Clerk

Sabre Industries Incorporated,

Plaintiff—Appellee Cross-Appellant,

versus

Module X Solutions, L.L.C.; Kristen Schoonover Erler, as the Independent Executrix of the Succession of Steven L. Schoonover,

Defendants—Appellants Cross-Appellees.

Appeal from the United States District Court for the Western District of Louisiana USDC No. 5:15-CV-2501

Before Barksdale, Southwick, and Graves, Circuit Judges. Per Curiam:* This appeal in a diversity action arises from a jury trial regarding a business dispute between parties to a Joint Venture Agreement (“JVA”) in the telecommunications shelter manufacturing industry. We AFFIRM.

* Pursuant to 5th Circuit Rule 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5th Circuit Rule 47.5.4. Case: 19-30887 Document: 00515730446 Page: 2 Date Filed: 02/02/2021

No. 19-30887

I. In 2013, Steven Schoonover had previously owned telecommunications manufacturing companies, but he had for a few years been out of the shelter business. He approached Peter Sandore, the CEO of Sabre Industries, Inc. (“Sabre”) about getting back into the industry. Those discussions ultimately led to Schoonover forming Module X Solutions, L.L.C. (“MXS”) at Sandore’s encouragement. Sandore and Schoonover intended that MXS would assist in expanding Sabre’s market share by increasing production capacity, which would in turn provide Schoonover and MXS with a steady stream of guaranteed work. On April 24, 2014, Sabre and MXS executed the JVA, in which Sabre agreed to provide MXS with “telecommunications and non- telecommunications work concerning, but not limited to, the manufacture of shelters, building systems and [other] products as agreed upon between the parties.” The JVA had an initial term of two years, with an option to extend at the term’s end. “Sabre agree[d] to award an annual quantity of orders to MXS equal to three hundred (300) shelters,” awarding at least seventy-five shelters in any three-month period. Sabre’s two-year obligation to award 300 shelters per year was subject to the following limitation: If volume awarded to MXS by Sabre falls below 75 shelters in any rolling 3 month period, MXS will have the right to termi- nate the agreement with a sixty (60) day notice. Notice will in- clude a thirty (30) day remedy period within which Sabre can choose to award the agreed upon volume or allow the agree- ment to terminate.

The JVA then defines Sabre’s “default” as “awarding [fewer] than 75 units in a 3 month period or less than 300 units in a 12 month period, subject to the notice and cure period[.]”

2 Case: 19-30887 Document: 00515730446 Page: 3 Date Filed: 02/02/2021

The JVA contemplated that large companies like Allied Fiber, Verizon, and AT&T would generate the bulk of the shelter orders that Sabre would assign to MXS. Shortly after executing the JVA, Sabre assigned MXS an Allied Fiber shelter project, but, because MXS was still getting up to speed in its production capacity, MXS asked Sabre to cast five concrete shelters for Allied Fiber. After Sabre assigned MXS the Allied Fiber project, MXS began dealing directly with Allied Fiber. MXS never paid Sabre for the work Sabre did on the Allied Fiber project. At the time, MXS depended heavily on Sabre for generating work, and MXS contends that Sabre breached its obligations under the JVA by assigning too few shelter orders, causing MXS’ cash shortage and inability to pay Sabre for the Allied Fiber project. It is undisputed that MXS never notified Sabre of any alleged breach on Sabre’s part. On April 6, 2015, Sabre, citing MXS’ failure to pay for the Allied Fiber shelters, notified MXS that it was terminating the JVA. On October 8, 2015, Sabre sued MXS in federal court for breaching the JVA. MXS counterclaimed that Sabre breached the JVA by awarding insufficient shelter orders, and MXS also asserted claims for fraud and misrepresentation by Sandore in inducing Schoonover to form MXS. Sabre moved for partial summary judgment on its breach-of-contract claim regarding MXS’ failure to pay for the Allied Fiber shelters. The parties’ primary dispute regarding partial summary judgment pertains to whether the JVA encompassed the Allied Fiber project, or whether this was a separate, collateral agreement between the parties. The district court refused to consider an affidavit from Schoonover—MXS’ primary evidence on the issue—because the district court concluded that Schoonover’s prior deposition testimony contradicted the affidavit. The district court then concluded that the JVA encompassed the Allied Fiber project and entered partial summary judgment in Sabre’s favor on its breach-of-contract claim.

3 Case: 19-30887 Document: 00515730446 Page: 4 Date Filed: 02/02/2021

The district court also entered partial summary judgment on several other claims and defenses not at issue in this appeal. The parties tried their remaining claims before a jury. Although the district court had concluded that MXS breached the JVA, contract claims and defenses remained for both parties, and both parties tried their breach- of-contract claims. After a two-week trial, the jury: (i) concluded that MXS breached the JVA by failing to pay for the Allied Fiber project; (ii) rejected MXS’ defenses to its breach; (iii) rejected MXS’ breach-of-contract claim against Sabre; (iv) awarded Sabre $423,708.00 for MXS’ breach regarding the Allied Fiber project; (v) rejected MXS’ and Sabre’s fraud claims; and (vi) found for MXS on its negligent misrepresentation claim and awarded $2,150,211.00, which mirrored MXS’ valuation of its lost-contract damages. The district court denied the parties’ post-trial motions to set aside the jury verdict or for a new trial. The JVA includes an attorney’s fee provision. Because Sabre prevailed on its contract claim and MXS did not, the district court awarded Sabre $1,101,145.00 in attorney’s fees. Both parties appealed, raising numerous points of reversal. II. We begin with MXS’ arguments. MXS first contends that the district court erred in excluding Schoonover’s affidavit and so should not have en- tered partial summary judgment on Sabre’s contract claim regarding the Al- lied Fiber project. In concluding that the JVA encompassed the Allied Fiber project, the district court relied on Schoonover’s deposition testimony that an Allied Fiber project described in an emailed spreadsheet was “JVA re- lated.” Pointing to a later-submitted affidavit by Schoonover, however, MXS asserts that this spreadsheet refers to a different Allied Fiber project, rather than the one at issue in this case. According to MXS, because it was not then capable of completing all the work, the parties formed a separate agreement, outside the JVA’s scope, wherein Sabre agreed to cast the shelters, which

4 Case: 19-30887 Document: 00515730446 Page: 5 Date Filed: 02/02/2021

MXS would finalize. MXS thus argues that its failure to pay Sabre for the disputed Allied Fiber project did not implicate the JVA. “It is well settled that this court does not allow a party to defeat a mo- tion for summary judgment using an affidavit that impeaches, without expla- nation, sworn testimony.” S.W.S. Erectors, Inc. v. Infax, Inc., 72 F.3d 489, 495 (5th Cir. 1996) (citing Thurman v. Sears, Roebuck & Co., 952 F.2d 128, 137 n.23 (5th Cir. 1992)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S.W.S. Erectors, Inc. v. Infax, Inc.
72 F.3d 489 (Fifth Circuit, 1996)
Mid-Continent Casualty Co. v. Chevron Pipe Line Co.
205 F.3d 222 (Fifth Circuit, 2000)
Hopwood v. State of Texas
236 F.3d 256 (Fifth Circuit, 2000)
Logan v. Burgers Ozark Country Cured Hams Inc.
263 F.3d 447 (Fifth Circuit, 2001)
Mathis v. Exxon Corporation
302 F.3d 448 (Fifth Circuit, 2002)
Rivera v. Union Pacific Railroad
378 F.3d 502 (Fifth Circuit, 2004)
Energy Management Corp. v. City of Shreveport
467 F.3d 471 (Fifth Circuit, 2006)
Keenan v. DONALDSON, LUFKIN & JENRETTE, INC.
575 F.3d 483 (Fifth Circuit, 2009)
Schaumburg v. State Farm Mutual Automobile Insurance
421 F. App'x 434 (Fifth Circuit, 2011)
Goodner v. Hyundai Motor Co., Ltd.
650 F.3d 1034 (Fifth Circuit, 2011)
Denise Lawson Seidman v. American Airlines, Inc.
923 F.2d 1134 (Fifth Circuit, 1991)
Willie L. Thurman v. Sears, Roebuck & Co.
952 F.2d 128 (Fifth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Sabre Indus v. Module X Solutions, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sabre-indus-v-module-x-solutions-ca5-2021.