Sabia Construction, LLC v. Palisades Fire House, LLC

New Jersey Superior Court Appellate Division·Decided July 24, 2026·No. A-2280-24·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-2280-24

SABIA CONSTRUCTION, LLC,

Plaintiff-Appellant/ Cross-Respondent,

v.

PALISADES FIRE HOUSE, LLC and JOSEPH GIANFORTE,

Defendants-Respondents/ Cross-Appellants.

Submitted April 28, 2026 – Decided July 24, 2026 Before Judges Susswein and Augostini.

On appeal from the Superior Court of New Jersey, Law Division, Hudson County, Docket No. L-3181-22.

Dana Wefer, attorney for appellant/cross-respondent.

Castano Quigley Cherami, LLC, attorneys for respondents/cross-appellants (Gregory J. Castano Jr.

and Schuyler Abbott, on the briefs).

PER CURIAM

This appeal arises from a dispute concerning the renovation of an old firehouse and construction of a twenty-unit residential building in Jersey City. Plaintiff Sabia Construction, LLC brought a breach of contract action against defendants Palisades Fire House, LLC (PFH) and Joseph Gianforte for non- payment of $419,013.40 in "change orders" that exceeded the original construction contract bid of $7,800,000. Following a bench trial, the trial court found that the parties had settled the change order claims and based on that finding, dismissed all claims and counterclaims. After reviewing the record in light of the governing legal principles, we affirm. We also affirm the trial court's denial of defendants' motion for counsel fees.

I.

We discern the following facts and procedural history from the record.

A. The Project

Plaintiff is a general contracting company, owned and operated by brothers Anthony Sabia (Anthony) and Joseph Sabia (Joseph).1 PFH owns commercial property in Jersey City that contained an abandoned firehouse. Arthur Pronti is a principal of PFH and Pronti Construction Company (a non-

1 Because the Sabia brothers share a common surname, we refer to them by their first names. We mean no disrespect in doing so.

A-2280-24

party to this case). Gianforte is an employee of PFH, engaged as its project manager.

On August 19, 2019, PFH engaged plaintiff to renovate the abandoned firehouse and build a twenty-unit residential building and adjoined commercial gym on its Jersey City property. Plaintiff and PFH executed a standard industry contract, form AIA101-2007, which incorporated the project specifications in attachment A and the form's standard terms and conditions. The contract was signed by Anthony and Pronti. Pursuant to the contract, plaintiff was to provide labor, services, and materials to PFH in exchange for compensation totaling $7,800,000.

Construction began in or around August 2019 but encountered some delays attributable to the COVID-19 pandemic and other unforeseen construction obstacles, such as difficult blue stone removal at the start of demolition. Construction was completed and the final city inspections were passed in or around May 2022. A certificate of occupancy was issued on June 7, 2022. The parties have no dispute regarding the quality of construction or the work performed.

A-2280-24

B. The Contract Terms

Under the contract, Anthony was designated as plaintiff's representative and Gianforte was designated as PFH's representative. Lee Levine was designated as the architect but was later replaced by Dirk Garlick sometime around March 2021, when Levine resigned for "personal reasons." Gianforte estimated that Garlick replaced Levine when the project was approximately thirty percent complete.

Under section 4.2 of the contract, the architect was charged with the responsibility of "Administration of the Contract," which included making site visits (§ 4.2.2), issuing certificates for payment due to plaintiff as the contractor (§ 4.2.5), preparing change orders (§ 4.2.8), determining the dates of substantial completion and final completion (§ 4.2.9), and issuing the final certificate of payment (§ 4.2.9).

Section 9.3 of the contract provided for incremental progress payments to be made throughout construction, which were triggered when an application for payment was made by plaintiff. The contract provided in pertinent part:

At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. Such application shall be notarized, if

A-2280-24

required, and supported by such data substantiating the Contractor's right to payment as the Owner or Architect may require, such as copies of requisitions from Subcontractors and material suppliers, and shall reflect retainage if provided for in the Contract Documents.

Under section 9.4 of the contract, that "Application for Payment" would then be certified as "properly due" by the architect by signing the Certificate for Payment.

Anthony testified that initially, Levine was making site visits approximately every one to two weeks and performed site inspections. But when Garlick replaced Levine, the pattern changed. Garlick never came to the site and was never involved with changes to the project. Anthony testified that the parties "change[d] the way the project was functioning" and that "once [Levine] was removed from the job, [Gianforte and Pronti] told [Anthony] just to send [payment requisitions] to them directly. That they didn't need the architect's signature." Once Levine left, the requests for payment were never signed by the architect.

In addition, the contract permitted changes to the agreed upon work through a "change order," subject to agreement by the owner, contractor and architect, unless it was a "minor change," in which case only the approval of the

A-2280-24

architect was required. A "change order" is defined in section 7.2.1 of the contract as

a written instrument prepared by the Architect and signed by the Owner, Contractor, and Architect stating their agreement upon all of the following:

1. The change in the Work;

2. The amount of the adjustment, if any, in the Contract Sum; and

3. The extent of the adjustment, if any, in the Contract Time.

Anthony testified that he prepared change orders throughout construction and sent them to defendants via email. However, these orders either went "unanswered" or Anthony was told "[Pronti's] reviewing it" or "[w]e'll sit down, and we'll work it out." As with the payment requisitions, Garlick also never signed the change orders. Anthony had no interactions with Garlick until the final certificate of occupancy was issued.

The court reluctantly allowed Amin Terouhid to testify as an expert on behalf of plaintiff in order to demonstrate for the court "if the contract had been administered [by the architect], basically what the architect would have done ." The court cautioned that Terouhid's testimony was permitted only to the extent it aided the trier of fact, not to interpret the contract terms as a matter of law ,

A-2280-24

and that it was further limited by the court's credibility and probative value findings.

Terouhid opined as to the importance of the role of the architect:

So typically, the architect has the role of fair[] and impartial review of change orders, among other duties.

So they're supposed to receive the change order requests and evaluate if that is really a change. In other words, is that an additional work or modifies the scope of work as stipulated in the contract? And then if that's a change, they would specify if it has a cost impact, it has a time impact, or any impact on other aspects of the project. And then once they approve that, as the independent reviewer, they can then bring that to the attention of the owner, and the owner formally issues the change order. And after that, that becomes part of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Sabia Construction, LLC v. Palisades Fire House, LLC, (N.J. Ct. App. 2026).

Sabia Construction, LLC v. Palisades Fire House, LLC (Sabia Construction, LLC v. Palisades Fire House, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anthony D'agostino v. Ricardo Maldonado (068940)
78 A.3d 527 (Supreme Court of New Jersey, 2013)
Jewish Center of Sussex Cty. v. Whale
432 A.2d 521 (Supreme Court of New Jersey, 1981)
Brundage v. Estate of Carambio
951 A.2d 947 (Supreme Court of New Jersey, 2008)
Continental Bank v. Barclay Riding Academy, Inc.
459 A.2d 1163 (Supreme Court of New Jersey, 1983)
Martindale v. Sandvik, Inc.
800 A.2d 872 (Supreme Court of New Jersey, 2002)
Atlantic Northern Airlines, Inc. v. Schwimmer
96 A.2d 652 (Supreme Court of New Jersey, 1953)
Nevets C.M., Inc. v. Nissho Iwai American Corp.
726 F. Supp. 525 (D. New Jersey, 1989)
Weil v. Express Container Corp.
824 A.2d 174 (New Jersey Superior Court App Division, 2003)
Weichert Co. Realtors v. Ryan
608 A.2d 280 (Supreme Court of New Jersey, 1992)
Cesare v. Cesare
713 A.2d 390 (Supreme Court of New Jersey, 1998)
Albright v. Burns
503 A.2d 386 (New Jersey Superior Court App Division, 1986)
Peskin v. Peskin
638 A.2d 849 (New Jersey Superior Court App Division, 1994)
Nolan v. Lee Ho
577 A.2d 143 (Supreme Court of New Jersey, 1990)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Rendine v. Pantzer
661 A.2d 1202 (Supreme Court of New Jersey, 1995)
Conway v. 287 Corporate Center Associates
901 A.2d 341 (Supreme Court of New Jersey, 2006)
Rova Farms Resort, Inc. v. Investors Insurance Co. of America
323 A.2d 495 (Supreme Court of New Jersey, 1974)
Cedar Ridge Trailer Sales, Inc. v. NAT. COMMUN. BANK
711 A.2d 338 (New Jersey Superior Court App Division, 1998)
Packard-Bamberger & Co., Inc. v. Collier
771 A.2d 1194 (Supreme Court of New Jersey, 2001)