S. Ward Hamilton Co. v. Channell Chemical Co.

242 Ill. App. 320, 1926 Ill. App. LEXIS 104
CourtAppellate Court of Illinois
DecidedNovember 17, 1926
DocketGen. No. 30,709
StatusPublished

This text of 242 Ill. App. 320 (S. Ward Hamilton Co. v. Channell Chemical Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. Ward Hamilton Co. v. Channell Chemical Co., 242 Ill. App. 320, 1926 Ill. App. LEXIS 104 (Ill. Ct. App. 1926).

Opinion

Mr. Justice Thomson

delivered the opinion of the court.

The parties to this case entered into a contract on October 3, 1919, by which the plaintiff, S. Ward Hamilton Company, agreed to manufacture and sell to the defendant, Channell Chemical Company, 3,000,000 mop centers. There were three sizes specified in the contract, numbered 3, 4 and 10. The contract called for 750,000 of No. 3, 1,500,000 of No. 4, and 750,000 of No. 10. Under the terms of the contract, the defendant agreed to pay the plaintiff $51.50 per thousand for the No. 3 centers; $46.50 for the No. 4, and $56.50 for the No. 10. The plaintiff undertook to deliver 10,000 centers per day, “If ordered by first party (defendant) in following quantities:” 2,500, No. 3; 5,000, No. 4; and 2,500, No. 10. Deliveries were to be made within one week from the date of the order, and the contract provided that deliveries on No. 4 centers were to begin within eight weeks from the date of the contract; on No. 3, within nine weeks, and on No. 10, within ten weeks. The plaintiff agreed to keep 50,000 No. 4 centers on hand available for immediate delivery, and 25,000 of each of the other sizes. The contract also provided as follows: “The first party (defendant) agrees to accept delivery of the entire 3,000,000 mop centers within eighteen (18) months from date of first delivery.”

The first delivery under the contract was made on December 19, 1919, about IQ weeks after the making of the contract. Between that date and July, 1921, the plaintiff delivered, and the defendant paid for, 2,059,-943 centers, which were all the centers either paid for by the defendant or manufactured by the plaintiff, under the contract. The plaintiff brought this action by reason of the alleged breach of the contract by the defendant in failing to order or take the remainder of the centers, contemplated by the contract, amounting to 904,057.

After alleging the number of centers of each kind taken and paid for by the defendant under the contract, the plaintiff’s declaration alleged that “thereafter the plaintiff * * * did * * * make up a large quantity of mop centers and offered and was ready and willing to deliver to the said defendant the balance of said mop centers * * * and requested the defendant to accept and pay for the same * * *, yet the defendant failed to do so, to the damage of the plaintiff in the sum of $50,000. ’ ’ According to the affidavit of claim, the plaintiff’s claim was made up of $24,500 in loss of profits, $12,000 in ‘ ‘ depreciation of the materials which the plaintiffs purchased,” in order to fill the contract, and $4,000 for dies made specifically for this contract, making a total of $40,500.

The defendant pleaded the general issue, payment in full, and accord and satisfaction. The issues thus joined were submitted to a jury, resulting in a verdict finding the issues for the plaintiff and assessing its damages at the sum of $25,375. Judgment was thereupon entered for the plaintiff, for that amount, to reverse which the defendant has perfected this appeal.

In support of its appeal, the defendant first contends that the trial court erred in denying its motion for a peremptory instruction, for several reasons. It is contended that the plaintiff failed to prove its case as alleged in its declaration. In our opinion, that contention is not supported by the record. It is true that the proof does not show that the plaintiff made up “a large quantity of mop centers,” beyond those taken and paid for by the defendant, as the declaration alleges. But the declaration also alleges that the plaintiff “offered and was ready and willing to deliver to the said defendant, the balance of the said mop centers,” and requested the defendant to accept and pay for them but that the latter refused to do so.

The evidence submitted in behalf of the plaintiff tends to show that on July 11, 1921, the plaintiff had on hand, ready for delivery, a large quantity of centers of the different sizes, amounting in value to approximately $19,000 at the contract price; that the plaintiff had then been carrying “a large inventory for something like eight months, expecting them to take deliveries,” and that during the previous six months, there had been “no regular deliveries, as called for in the contract.” The record shows that representatives of the plaintiff called at the plant of the defendant in November, 1920, to see “why they were not resuming deliveries,” telling the defendant that plaintiff “had a large quantity of mops on hand and did not feel as though we could carry them any longer”; that the defendant represented that its business was very poor and they could not take the centers in large quantities at that time but they hoped business would pick up after the first of the year; that the parties “had continual conferences with reference to mops, after that time, for at least two or three months,” and that at such a conference held in July, 1921, the plaintiff insisted it must have an immediate settlement for all the centers it then had on hand. The result of that conference was that the defendant gave the plaintiff three trade acceptances, one for $4,963.63, due in 60 days, one for $4,963.63, due in 90 days, and another for $9,927.29, due in 120 days, in payment for all the centers which the plaintiff then had on hand, and asked the plaintiff to hold them at its factory until the defendant requested delivery, and that all of them were afterwards delivered to the defendant. It appears from the evidence submitted by both parties that at this time the defendant had begun the manufacture of its own mop centers, and the plaintiff’s evidence is to the effect that the defendant requested the plaintiff not to “make up any more mops at the present time because we don’t know how well they will go because we are making a new style mop.” The evidence submitted by the plaintiff is further to the effect that some time later, the witnesses stating they could not fix the time definitely, within several months, representatives of the plaintiff again saw the defendant, asking what the defendant “was going to do about the balance of the contract,” and the defendant’s representative said they didn’t want any more mops. Some effort was made to see if the defendant could make some use of the material the plaintiff had remaining on hand for the purposes of this contract, but it came to nothing. The record shows that there were times when the plaintiff was behind in deliveries and others when, as already stated, the defendant requested the plaintiff to make no more deliveries until further notice. The record also shows that there were times when the defendant was asking the plaintiff to make deliveries on one of the sizes, far in excess of the daily quantity called for by the contract, saying that it was experiencing a large demand for that size but little demand for the others. In our opinion, this proof sufficiently supported the plaintiff’s declaration to require the trial court to submit it to the jury.

It is further contended that the trial court should have given the jury the peremptory instruction requested by the defendant, because, on the plaintiff’s own theory of the case, recovery could not be had on the original contract entered into by the parties, because that contract expired by its own terms, 18 months after the first delivery was made in December, 1919, namely, in June, 1921, and that, after that time, in July of that year, the parties entered into a new arrangement or contract. The evidence on this point is conflicting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago, Milwaukee & St. Paul R. R. v. Hall
90 Ill. 42 (Illinois Supreme Court, 1878)
Kingman & Co. v. Hanna Wagon Co.
52 N.E. 328 (Illinois Supreme Court, 1898)
Chicago & Eastern Illinois Railroad v. Donworth
67 N.E. 797 (Illinois Supreme Court, 1903)
Lauth v. Chicago Union Traction Co.
91 N.E. 431 (Illinois Supreme Court, 1910)
Lyons v. Chicago City Railway Co.
101 N.E. 211 (Illinois Supreme Court, 1913)
Stadler v. Chicago City Railway Co.
180 Ill. App. 313 (Appellate Court of Illinois, 1913)
Newcomb v. Chicago City Railway Co.
192 Ill. App. 74 (Appellate Court of Illinois, 1915)
Central Trust Co. v. John M. Smyth Merchandise Co.
222 Ill. App. 347 (Appellate Court of Illinois, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
242 Ill. App. 320, 1926 Ill. App. LEXIS 104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-ward-hamilton-co-v-channell-chemical-co-illappct-1926.