S & Q Construction Co. v. Palma Ceia Development Organization

179 Cal. App. 2d 364, 179 Cal. App. 364, 3 Cal. Rptr. 690, 1960 Cal. App. LEXIS 2243
CourtCalifornia Court of Appeal
DecidedApril 1, 1960
DocketCiv. 18314
StatusPublished
Cited by19 cases

This text of 179 Cal. App. 2d 364 (S & Q Construction Co. v. Palma Ceia Development Organization) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S & Q Construction Co. v. Palma Ceia Development Organization, 179 Cal. App. 2d 364, 179 Cal. App. 364, 3 Cal. Rptr. 690, 1960 Cal. App. LEXIS 2243 (Cal. Ct. App. 1960).

Opinion

BRAY, P. J.

Plaintiff appeals from a judgment in favor of defendants denying damages for an alleged breach of contract.

Questions Presented

1. Does the fact that Palma Ceia was an unlicensed contractor compel judgment in plaintiff’s favor?

2. Does the evidence support the court’s findings (a) that defendants did not breach the contract, (b) that plaintiff did?

3. Were the findings unsupported, contradictory, and did they fail to cover the issues ?

Record

The controversy arises out of a contract entered into August 21, 1954, between plaintiff as subcontractor and defendant Palma Ceia as general contractor for the construction in the city of Hayward of a sanitary pumping station, a sanitary sewer main line (referred to as force main) and a gravity sewer line (referred to as gravity line). The work was to be performed in a subdivision being developed by defendants Branden and Branden Construction, Inc. These two were joined as defendants on the theory that they were principals and agents of Palma Ceia in the said contract. The complaint contained three counts, (1) for breach of contract, (2) for foreclosure of mechanic’s lien, and (3) for fraud. Defendants answered and cross-complained (later *367 an amendment was allowed to include a counterclaim). To conform to proof plaintiff was permitted to file an amended complaint setting up a fourth count, alleging that the contract was illegal because defendants were not licensed contractors. Plaintiff’s motion for nonsuit on the cross-complaint was denied. Defendants’ motion for nonsuit was granted as to the mechanic’s lien count but denied as to the other three counts. * Judgment was entered on all counts in favor of defendants and in favor of plaintiff on defendants’ cross-complaint and counterclaim. Defendants do not appeal.

1. Effect of Lack of License.

Admittedly Palma Ceia did not have a contractor’s license. Plaintiff did. Such license was required. (Bus. & Prof. Code, §§ 7028, 7031, 7056 and 7057.) Plaintiff contends that the lack of license made the contract void, and that as plaintiff had such license and did not discover until during the trial that defendant Palma Ceia did not, plaintiff was not in pari delicto and is entitled to recover on a quantum meruit and that defendant Palma Ceia may not assert any defense based on the contract. The court found that Palma Ceia did not have a contractor’s license but that “The failure to have a license in no way prevents said defendant, or any of them, from asserting and proving their answer and defense.” The court correctly expressed the law in California in this statement. It is well settled that the failure to obtain a required contractor’s license will bar the contractor from recovering for his work in an action brought by him, but will not bar him from offsetting as a defense sums which would otherwise be due him under the illegal contract. “It is to be noted that the statute merely prohibits a contractor from maintaining or bringing an action upon a contract which he has entered into pertaining to the contracting business. It does not prohibit him when sued from setting up as a defense any sums which may be equitably due him from the plaintiff upon such illegal contract. Such a contract is not malum in se but merely malum prohibitum.” (Marshall v. Von Zumwalt (1953), 120 Cal.App.2d 807 [262 P.2d 363].) The contractor’s license statute cannot be used as a shield to avoid a just obligation. (Norwood v. Judd (1949), 93 Cal.App.2d 276 [209 P.2d 24].) The courts will not *368 impose penalties on a contractor for noncompliance with the licensing requirements other than that provided by the statute.

2. Sufficiency of the Evidence.

This is a typical conflict of evidenec case in which the trial court resolved the conflict in favor of the defendants. Plaintiff in its exceedingly lengthy briefs comments on the credibility of witnesses and details evidence which possibly could have supported a judgment in its favor. The rule is so well settled that this court is bound by the findings of the trial court on conflicts where there is substantial evidence to support those findings, that it does not require the citation of authorities. In considering plaintiff’s contentions concerning the findings we will refer principally to the evidenee which supports them.

(a) Defendants Did Not Breach the Contract.

The contract made time of the essence and provided that progress payments were to be made “progressively on the 8th day of each month for all work completed during the preceding month ending on the 30th or 31st day thereof,” less 10 per cent retention. The sums retained were to be paid 35 days after completion of all work, provided that said work was accepted by the city of Hayward. The contract provided that plaintiff was to be paid for all of the work specified in the contract, “the following lump sums set forth opposite the following respective items:

“Schedule A—Pump Station...........$41,010.00
“Schedule B—Force sanitary sewer main line .............. 24,810.00
“Schedule C—Gravity sewer line....... 26,309.00
Total......$92,129.00.”

September 14, 1954, during the progress of the work, plaintiff was given a change order affecting the force line. This work amounted to $10,050. Progress payments were made for the work completed during September and October.

Plaintiff notified defendants on November 24 that it claimed to have completed all work under the contract and requested completion payment and that notice of completion be filed. The contract does not provide for a completion payment, but only for the progress payments and the 10 per cent retention, which is not payable until 35 days after completion. *369 Thereafter and on December 2 plaintiff submitted a bill requesting payment of $18,183, which was the balance of the contract price and the price of the work under the change orders then unpaid. The parties concede that under the terms of the contract the price of the change orders work would be added to the contract price and considered in figuring the progress payments. It is plaintiff’s contention that on December 8 he was entitled to a progress payment of 90 per cent of this $18,183 and that the failure to pay it constituted a breach by Palma Ceia of the contract. The court found that on December 8 there was nothing due from defendants to plaintiff. Certainly plaintiff was not entitled to the amount requested at that time as even under plaintiff’s contention that the contract was completed on November 24, the 35 days after completion had not yet run.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rodgers v. HB Construction CA2/5
California Court of Appeal, 2023
Daggett v. Feeney
397 P.3d 297 (Alaska Supreme Court, 2017)
UDC-Universal Development, L.P v. CH2M Hill
181 Cal. App. 4th 10 (California Court of Appeal, 2010)
Holland v. MORSE DIESEL INTERNAT., INC.
104 Cal. Rptr. 2d 239 (California Court of Appeal, 2001)
Ranchwood Communities Limited Partnership v. Jim Beat Construction Co.
49 Cal. App. 4th 1397 (California Court of Appeal, 1996)
Broffman v. Newman
213 Cal. App. 3d 252 (California Court of Appeal, 1989)
R. M. Sherman Co. v. W. R. Thomason, Inc.
191 Cal. App. 3d 559 (California Court of Appeal, 1987)
Sumner Development Corporation v. Shivers
517 P.2d 757 (Alaska Supreme Court, 1974)
Vitek, Inc. v. Alvarado Ice Palace, Inc.
34 Cal. App. 3d 586 (California Court of Appeal, 1973)
Schantz v. Ellsworth
19 Cal. App. 3d 289 (California Court of Appeal, 1971)
Vaughn v. DeKreek
2 Cal. App. 3d 671 (California Court of Appeal, 1969)
Davis Co. v. Superior Court
1 Cal. App. 3d 156 (California Court of Appeal, 1969)
Dahl-Beck Electric Co. v. Rogge
275 Cal. App. 2d 893 (California Court of Appeal, 1969)
Culbertson v. Cizek
225 Cal. App. 2d 451 (California Court of Appeal, 1964)
Steinwinter v. Maxwell
183 Cal. App. 2d 34 (California Court of Appeal, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
179 Cal. App. 2d 364, 179 Cal. App. 364, 3 Cal. Rptr. 690, 1960 Cal. App. LEXIS 2243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-q-construction-co-v-palma-ceia-development-organization-calctapp-1960.