S. Dearborn Envtl. Improvement Ass'n, Inc. v. Dep't of Envtl. Quality

917 N.W.2d 603, 502 Mich. 349
CourtMichigan Supreme Court
DecidedJuly 17, 2018
DocketNo. 154524; No. 154526
StatusPublished
Cited by90 cases

This text of 917 N.W.2d 603 (S. Dearborn Envtl. Improvement Ass'n, Inc. v. Dep't of Envtl. Quality) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. Dearborn Envtl. Improvement Ass'n, Inc. v. Dep't of Envtl. Quality, 917 N.W.2d 603, 502 Mich. 349 (Mich. 2018).

Opinion

Bernstein, J.

**355In this case, we consider how long an interested party has to file a petition for judicial review of a Michigan Department of Environmental Quality (DEQ) decision to issue a permit for an existing source of air pollution. We hold that MCL 324.5505(8) and MCL 324.5506(14) provide that such a petition must be filed within 90 days of the DEQ's final permit action. Therefore, the circuit court correctly denied AK Steel Corporation's (AK Steel's) motion to dismiss pursuant to MCR 2.116(C)(1) because the petition for judicial review was timely filed 59 days after the final permit action in this case. Accordingly, we affirm the judgment of the Court of Appeals in part, albeit for different reasons, and remand this case to the circuit court for further proceedings.1

I. FACTS AND PROCEDURAL HISTORY

AK Steel operates a steel mill within the Ford Rouge Manufacturing complex in Dearborn, Michigan. Before being acquired by AK Steel in 2014, the steel mill was operated by Severstal Dearborn, LLC (Severstal). The steel mill is subject to air *606pollution control and permitting requirements under the federal Clean Air Act,2 **35642 USC 7401 et seq ., and the Natural Resources and Environmental Protection Act (NREPA), MCL 324.101 et seq . In order to comply with the Clean Air Act, Part 55 of the NREPA requires the DEQ to promulgate rules to establish a permit-to-install program, MCL 324.5505(2), and an operating-permit program, MCL 324.5506(4).

In 2006, the DEQ issued Severstal a permit to install3 titled "PTI 182-05," which authorized the rebuilding of a blast furnace and the installation of three air pollution control devices at Severstal's steel mill. In the years that followed, the permit was revised twice, first in 2006 (PTI 182-05A) and again in 2007 (PTI 182-05B). Each successive permit modified and replaced the preceding permit.

Emissions testing performed in 2008 and 2009 revealed that several emission sources at the steel mill exceeded the level permitted by PTI 182-05B. The DEQ sent Severstal a notice of violation, and after extended negotiations, they entered into an agreement, pursuant to which Severstal submitted an application for PTI 182-05C. The DEQ issued the permit on May 12, 2014, after a period of public comment and a public hearing as prescribed by the NREPA, MCL 324.5511(3). The DEQ stated that the purpose of PTI 182-05C was to correct inaccurate assumptions about **357pre-existing and projected emissions and to reallocate emissions among certain pollution sources covered by the permit to install.

On July 10, 2014, 59 days after PTI 182-05C was issued, appellee South Dearborn Environmental Improvement Association, Inc. (South Dearborn)4 and a number of other environmental groups appealed the DEQ's decision by filing a petition for judicial review in the Wayne Circuit Court.5

AK Steel purchased the steel mill a short time later and filed a motion to dismiss pursuant to MCR 2.116(C)(1), arguing that South Dearborn's petition was untimely filed and thus the circuit court lacked jurisdiction over the case.6 According *607to AK Steel, while MCL 324.5505(8)7 and **358MCL 324.5506(14)8 provide a right to appeal the issuance or denial of an operating permit9 and a permit to install for a new source, and state when such appeals must be filed, neither statute applies to a permit to install for an existing source.10 Instead, AK Steel argued that South Dearborn's right to appeal a permit to install for an existing source is based in MCL 600.631 of the Revised Judicature Act, MCL 600.101 et seq ., and that the period in which to file an appeal is thus governed by MCR 7.123(B)(1) and MCR 7.104(A). AK Steel claimed that South Dearborn's appeal was untimely because it was not filed within 21 days, as required by those court rules.

The circuit court disagreed. The court noted that MCL 324.5506(14) states, "A petition for judicial review is the exclusive means of obtaining judicial review of a permit and shall be filed within 90 days after the final permit action." Relying heavily on the Legislature's **359use of an indefinite article, the circuit court found that the phrase "a permit" in MCL 324.5506(14) included the permit to install appealed in this case. Therefore, South Dearborn had 90 days from the date that the fourth successive permit was issued to file a petition for judicial review. Accordingly, the circuit court held that South Dearborn's petition was timely filed and denied AK Steel's motion to dismiss.

AK Steel appealed in the Court of Appeals, which affirmed the result, but on different grounds. In the Court of Appeals' view, "[t]he circuit court erred by ignoring the plain context of [ MCL 324.5506(14) ] and placing far too much importance on the Legislature's use of the indefinite article 'a.' " South Dearborn Environmental Improvement Ass'n, Inc. v. Dep't Of Environmental Quality , 316 Mich. App. 265, 273, 891 N.W.2d 233 (2016) ( SDEIA ). Rejecting the circuit court's reasoning, the Court of Appeals held that the appeals period outlined in MCL 324.5506(14) applies *608only to operating permits. Id . at 274, 891 N.W.2d 233. The Court of Appeals determined that MCL 600.631 and MCR 7.119 governed this appeal because, in its view, the contested-case provisions of the Administrative Procedures Act, MCL 24.201 et seq ., applied to the permitting decision pursuant to MCL 24.291(1). Id . at 277, 891 N.W.2d 233. On this basis, the Court of Appeals held that the petition was timely because it was filed within the 60-day period provided by MCR 7.119 and MCR 7.104(A). Id . at 277-278, 891 N.W.2d 233.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Desmond Ricks v. State of Michigan
Michigan Court of Appeals, 2025
20251121_C369413_36_369413.Opn.Pdf
Michigan Court of Appeals, 2025
Robert Davis v. Janice Winfrey
Michigan Court of Appeals, 2025
Mary Theresa Wade v. Corepark Investments LLC
Michigan Court of Appeals, 2025
The Walt Disney Company v. Rachael Eubanks
Michigan Supreme Court, 2025
Dine Brands Global Inc v. Rachael Eubanks
Michigan Supreme Court, 2025
Kevin Androsian v. City of Taylor
Michigan Court of Appeals, 2025
20250121_C370623_42_370623.Opn.Pdf
Michigan Court of Appeals, 2025
20250116_C366592_63_366592.Opn.Pdf
Michigan Court of Appeals, 2025
20241218_C369545_41_369545.Opn.Pdf
Michigan Court of Appeals, 2024
20241218_C365559_38_365559.Opn.Pdf
Michigan Court of Appeals, 2024
State v. Groce
2024 UT App 166 (Court of Appeals of Utah, 2024)
Shannon Blackman v. Tyler David Millward
Michigan Court of Appeals, 2024
In Re Nothnagel Estate
Michigan Court of Appeals, 2024

Cite This Page — Counsel Stack

Bluebook (online)
917 N.W.2d 603, 502 Mich. 349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-dearborn-envtl-improvement-assn-inc-v-dept-of-envtl-quality-mich-2018.